What is the work center hierarchy in capacity planning?
A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel
A group of alternative work centers providing a cumulative available capacity for production
A group of work centers in a production line being used in sequence for production
A group of alternative work centers for production, structured in hierarchy levels by priorities
A work center hierarchy is a business object in PP/DS that defines the structure and sequence of resources that are used for a production process. You use this object to represent the logical and physical dependencies of the resources and to control the scheduling and sequencing of the operations or orders. A work center hierarchy allows you to modelthe production flow and capacity more realistically and ensure the technical feasibility of the production plan1
A work center hierarchy can also be used to cumulate the available capacity and capacity requirements of the resources in capacity planning. You can cumulate the available capacities from subordinate work centers to a superior work center level in order to determine the total available capacity for the superior work center. This way, you can use a work center hierarchy as a group of alternative work centers that provide a cumulative available capacity for production23
References:
Which standard item categories can you select inside a bill of material (BOM)?
Note: There are 2 correct answers to this question
Work item
Variable-size item
Non-stock item
WBS item
You can select the following standard item categories inside a bill of material (BOM):
where does the system check master data selection settings during the creation of planned orders and production orders?
Note: There are 3 Correct answers to this question.
in the bill of material (BOM)
in the work centers
in the MRP controller
In the routing
in the production version
The system checks the master data selection settings during the creation of planned orders and production orders in the following places:
What does a line hierarchy in repetitive manufacturing represent?
A production line with more than one work center
A production line with prioritized work centers
A production line with a parallel sequence in the routing
A production line with an alternative sequence in the routing
A line hierarchy in repetitive manufacturing represents the structure of a production line that consists of multiple work centers. A line hierarchy is a master data object that defines the sequence and the relationship of the work centers that are involved in producing a material. A line hierarchy can be split into different levels, such as line segments, processing stations, or takt areas, to reflect the complexity and the variability of the production line. A line hierarchy can be used for planning and scheduling operations, controlling material flow, and monitoring production performance12.
The other options are not correct for the following reasons:
References:https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/48b24fbadbee4e0b9dae0e2b72762e68/db8151ba8ca14106bf037a1546cde6a9.html
https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/9231f9504a62eb5ee10000000a44538d.html
You are trying to create a production order and NO valid production version can be selected. What could be the reasons?
Note: There are 2 correct answers to this question.
NO bills of material (BOMs) are assigned to the production versions.
All production versions for the material are locked.
The order lot size is NOT within the validity range of a production version.
NO production lines are assigned to the production versions..
A production version is a master data object that links a bill of material (BOM) and a routing or a production process model (PPM) for a material. A production version is required for creating a production order in SAP S/4HANA, as it determines the components, operations, and resources that are needed for producing the material. You can create a production version manually or automatically using the CS_BOM_PRODVER_MIGRATION02 report1.
If you are trying to create a production order and no valid production version can be selected, it could be because of the following reasons:
The other options are not valid reasons for not being able to select a production version for creating a production order:
References:
Your company manufactures materials whose specifications differ for each manufacturing process. Which application do you have to use in SAP S/4HANA to be able to track and use this information in all areas of logistics?
Engineering change management
Quality management
Process order management
Batch management
You have to use batch management in SAP S/4HANA to be able to track and use the information about materials whose specifications differ for each manufacturing process in all areas of logistics. Batch management is a function that allows you to manage materials that are produced or procured in batches, where each batch has a unique identifier and can have different characteristics or specifications. With batch management, you can:
References: [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 92; [SAP Help Portal: Batch Management].
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?
The planned order is converted to a production order.
The planned order's component availability is checked.
The planned order generates capacity requirements
The planned order's components are copied to the picking list.
When you assign a planned order to a production line manually, using the planning table in repetitive manufacturing, the system generates capacity requirements for the planned order. The capacity requirements are calculated based on the production line, the quantity, and the production rate of the planned order. The system also checks the availability of the production line and displays any capacity overload or underload. The planned order is not converted to a production order, nor is the component availability or the picking list affected by the manual assignment. References: SAP Help Portal - Assigning Planned Orders to Production Lines, SAP S/4HANA Production Planning and Manufacturing Certification Guide - Chapter 7: Repetitive Manufacturing
When you create a sales order
When can consumption of planned independent requirements take place for planning strategy 40 (Planning with final assembly?
When MRP creates a dependent requirement
When MRP creates a planned order
When you create a sales order
When MRP creates a planned order
Planning strategy 40 (Planning with final assembly) is a make-to-stock strategy that uses planned independent requirements to trigger the procurement and production of the necessary assemblies and components before receipt of the sales orders. As soon as the sales order is received, it consumes the planned independent requirements and adjusts the master plan to suit the current requirements situation. This means that the important feature of this planning strategy is that you can react quickly to customers’ requirements. The consumption of planned independent requirements can take place when you create a sales order, as well as when you change or delete a sales order. References: Planning with Final Assembly (40), Sample Scenario: Strategy 40, Outlining Make-to-Stock Production
What does forecasting in the demand planning cycle include?
Note: There are 3 correct answers to this question
One-off events
Past quotation quantities
Past sales order quantities
Market intelligence
Past production planning quantities
which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?
you can use mass processing to set production orders to technically complete
you can use the production scheduling profile to automatically set orders toI technically complete
You can use trigger points to automatically create rework orders via confirmation.
You can use mass processing to read PP master data for production orders
References:
Which of the following processes lead to an entry in the MRP planning file?
Note: There are 3 correct answers to this question.
Changing the storage bin in warehouse management
Changing the procurement type in the product master
Changing the operation times in the production data structure
Changing the stock in inventory management
Changing the purchasing contract in materials management
The MRP planning file is a list of all materials relevant to the planning run. The system sets an entry in the planning file for a material when there is a change that affects the material requirements planning, such as changes to stock, requirements, receipts, or MRP data in the material master. The following processes lead to an entry in the MRP planning file:
which actions does the system perform by default when you save a confirmation for a finished
product in repetitive manufacturing?
Note: There are 3 Correct answers to this question.
Posting of production costs to the production cost collector
posting of goods receipt for the product
Reduction of associated capacity requirements
Archiving of document for assembly scrap
Material staging for next order in sequence
When you save a confirmation for a finished product in repetitive manufacturing, the system performs the following actions by default12:
Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?
Note: There are 2 correct answers to this question.
Work Center
Production Version
Material
plant
The Advanced Planning flag is a field that indicates whether a data object is relevant for planning with Production Planning and Detailed Scheduling (PP/DS) in SAP S/4HANA. PP/DS is a component of Advanced Planning that provides more precise and flexible planning capabilities for critical products and resources. You can set the Advanced Planning flag for the following data objects:
The production version (B) and the plant (D) are not data objects that can have the Advanced Planning flag. The production version is a master data object that defines the combination of a bill of material (BOM) and a routing or a production process model (PPM) for a material. The production version does not have a separate flag for PP/DS, but it inherits the flag from the material and the work center. The plant is an organizational unit that represents a physical location where materials are produced or stored. The plant does not have a flag for PP/DS, but it is assigned to a location in PP/DS that represents the geographical or logical grouping of plants for planning purposes. References:https://blogs.sap.com/2018/02/12/ppds-for-sap-s4hana-advanced-planning-a-powerful-planning-and-scheduling-tool/
https://learning.sap.com/learning-journeys/explore-integrated-business-processes-in-sap-s-4hana-/advanced-planning_ae824eb6-4bf8-4720-a48f-ba86929a14de
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
Scheduling agreement schedule line
Purchase Order
Planned Order
Production Order
A production planning run in Advanced Planning (PP/DS) is a process that optimizes the supply and demand situation for a set of materials and locations within a given planning horizon. The possible results of a production planning run are:
You can you use capacity availability checks for production orders, which settings have to be made for this?
Note: There are 2 Correct answers to this question?
The relevant for finite scheduling indicator must be set.
A checking rule must be assigned to the work centers
An overall profile must be assigned in the checking control
The scope of check must be defined in customizing.
To use capacity availability checks for production orders, you need to make the following settings:
References:
In the Capacity Scheduling Table, which settings can you select for the planning strategy?
Note: There are 3 correct answers to this question.
Finiteness level
Fixed pegging
Scheduling control
Planning mode
Direction
The planning strategy settings in the Capacity Scheduling Table determine how the system schedules the operations or orders on the resources. You can select the following settings:
References:
What do you need to consider when working with material master numbering in SAP S/4HANA?
Note: There are 2 correct answers to this question.
Material numbering is defined cross-client.
Material numbering is defined at client level.
The maximum material number length is 18 for external numbers and 18 for internalnumbers.
The maximum material number length is 40 for external numbers and 18 for internal numbers
Material numbering is the process of assigning unique identifiers to materials in the system. Material numbering is defined at the client level, which means that the same material number can be used for different materials in different clients. However, within a client, the material number must be unique for each material. The material number can be either external or internal. External material numbers are entered manually by the user, while internal material numbers are generated automatically by the system. The maximum material number length is 40 characters for external numbers and 18 characters for internal numbers. The material number length can be customized in the configuration app Define Material Number Lengths1. The material number can also be formatted with prefixes, suffixes, and templates in the configuration app Define Material Number Formats2. References: Define Material Number Lengths | SAP Help Portal, Define Material Number Formats | SAP Help Portal
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
Kanban
Material requirements planning
Backflushing
Production order release
If the available stock is zero and the discontinuation date is in the past, the material requirements planning (MRP) process will be affected. MRP will not create any planned orders or purchase requisitions for the discontinued component. Instead, it will create a discontinuation indicator in the MRP list and a discontinuation message in the exception message list. This will inform the planner that the component is no longer available and that a follow-up material should be used instead. References: [SAP Help Portal] - Discontinuation of Materials.
For a production version to be valid and consistent, what requirements must be fulfilled? Note:There are 3 correct answers to this question.
The deletion flag must NOT be set for the bill of material (BOM) or the routing
The lot size range must be within the lot size range of the assigned routing.
The assigned routing and bill of material (BOM) must be valid in the entirevalidity period.
The assigned routing must be a rate routing.
The assigned routing must NOT have alternative sequences
A production version is a combination of a BOM and a routing that defines how a material is produced. For a production version to be valid and consistent, the following requirements must be fulfilled:
TESTED 19 Apr 2025
Copyright © 2014-2025 DumpsTool. All Rights Reserved