Black Friday Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

CDCS Questions and Answers

Question # 6

You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.

Which location for the temperature/humidity measurement should you recommend for the audit?

A.

At the back/rear of the server at 50 mm/2 inch

B.

At 1.5 meters/5 feet above the floor in the middle of the cold aisle

C.

At the front/intake of the server at 50 mm/2 inch

D.

At 1.5 meters/5 feet above the floor in the middle of the hot aisle

Full Access
Question # 7

When shielding material reaches its saturation point, what will be the impact?

A.

The shielding material will reach its optimal shielding performance state.

B.

The shielding material will no longer be able to attenuate (reduce) additional EMF.

C.

The shielding material will increase its permeability factor.

D.

The shielding material will reach its maximum electrically charged state.

Full Access
Question # 8

You are working on the design of a new facility. The electrical riser of the building with high current power is located close to the area where sensitive IT equipment in the computer room will be located.

What should you recommend to reduce the amount of EMF coming from the electrical riser?

A.

Install single-phase power cabling

B.

Install three-phase power cabling based on three individual core wires

C.

Install bus bar trunking

D.

Install three-phase power cabling based on a combined cable (e.g. XLPE etc.)

Full Access
Question # 9

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.

To which feed will the output of the UPS be synchronized?

A.

The UPS will not synchronize to any of the feeds but use an internal clock to set the output voltage and frequency

B.

Depends on the setting of the UPS, as the UPS can normally be set to either feed

C.

Feed A

D.

Feed B

Full Access
Question # 10

A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.

The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.

The exhaust temperature is 29 °C/84 °F and 45% RH.

The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.

The pressure under the raised floor is approximately 25 Pa/0.1 inch H₂O.

Analyze the situation and indicate what the most likely cause is for this server to crash.

A.

Dust inside the server causing issues with convection-based heat transfer

B.

The exhaust temperature is exceeding the ASHRAE recommended values

C.

The raised floor pressure is too low and/or the raised floor tile % opening is not adequate

D.

No cause could be determined as the CFM/CMH of the air conditioning equipment is not stated

Full Access
Question # 11

From the options indicated, what is the correct starting point for the raised floor installation?

A.

Point A

B.

Point B

C.

Point C

D.

Point D

Full Access
Question # 12

A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.

What type of generators should be installed?

A.

Standby generators should be installed in at least an N+1 configuration

B.

Continuous generators should be installed, at least in an N+1 configuration

C.

A combination of standby-, prime-, and continuous-generators, as the duration of the power outage is unpredictable. The total available capacity of the generators should be at least 500% of the data center load

D.

Continuous generators should be installed; no N+1 configuration is needed as the generators willrun all the time

Full Access
Question # 13

The air intake of the mission-critical server at the top of the rack is measuring 25 °C/77 °F.

Is this acceptable?

A.

Yes, this is allowed according to the standards and guidelines

B.

As long as it does not exceed the average server room temperature of 38 °C/100 °F

C.

Depends on the ANSI/TIA-942 Rating the data center needs to comply with

D.

No, the temperature needs to be 20 °C/68 °F

Full Access
Question # 14

When installing a raised floor, can we use a spirit level bar to level the floor?

A.

Yes, spirit level bars can be used as long as their length is longer than 60 cm/2 ft (the size of a typical raised floor tile).

B.

No, because using a spirit level bar, a measurement error will be transferred from pedestal to pedestal.

C.

Yes, but spirit level bars can only be used in the vertical plane.

D.

Yes, using a spirit level bar for raised floors higher than 40 cm is preferred.

Full Access
Question # 15

When designing a data center network, your company wants to minimize the number of network switches to manage.

What type of physical cabling layout would be the best choice?

A.

ToR (Top of Rack) design

B.

EoR (End of Row) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout

Full Access
Question # 16

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.

Full Access
Question # 17

An air-conditioner unit needs to be selected. Two types are available:

Unit-A has a Sensible Heat Ratio (SHR) of 0.7.

Unit-B has a Sensible Heat Ratio (SHR) of 0.9.

From an efficiency point of view, which one should be selected?

A.

It does not matter, as the Sensible Heat Ratio has nothing to do with efficiency.

B.

Not relevant, as Sensible Heat Ratio is only specified for air-conditioner equipment to indicate the ratio between intake temperature and exhaust temperature.

C.

Unit A

D.

Unit B

Full Access
Question # 18

The noise levels in the data center are approximately 91 dB (A).

Do employers need to take precautions?

A.

No, anything less than 100 dB (A) is acceptable.

B.

There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.

C.

As long as the data is compliant to ISO/IEC 27001 it is acceptable.

D.

Yes, since it is mandated by regulations.

Full Access