New Year Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

RCDDv14 Questions and Answers

Question # 6

When designing a video communications network, which type of video communication link is two-person videoconferencing?

A.

Point-to-multipoint bidirectional

B.

Point-to-multipoint unidirectional

C.

Unidirectional

D.

PTP unidirectional

E.

PTP bidirectional

Full Access
Question # 7

Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

A.

Program performance report

B.

Communications management plan

C.

Communications log updates

D.

Information gathering and retrieval system

Full Access
Question # 8

What is used to facilitate MINOR changes to the Project Requirements?

Request lot Information (RFI)

A.

Punch list

B.

Field order

C.

Change order

D.

Change order request

Full Access
Question # 9

Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly. Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)

A.

Lower dB loss values

B.

Stretching of copper conductors and breakage of optical fiber strands

C.

Increased Interference levels

D.

Reduced expected useful life and performance

E.

Slippage between the cable core and the sheath

Full Access
Question # 10

What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?

A.

After the contract is awarded and before project close out

B.

As part of the contract bid process to prevent project delays

C.

Before the contract is awarded

D.

At the beginning of the close out process

Full Access
Question # 11

What would prevent a program manager from completing program closure once a program has been completed?

A.

Failure to update the financial management plan

B.

Failure to update the benefits register

C.

Incomplete realization of all program benefits

D.

Failure to obtain program steering committee approval

Full Access
Question # 12

A new program manager joins a mufti-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization

At the next stakeholder meeting, what should the program manager present to address their concerns?

A.

Program charter

B.

Program scope assessment results

C.

Business case and program roadmap

D.

Expected program benefits management plan

Full Access
Question # 13

A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning the program manager should consider which of the following stakeholder aspects?

A.

Attitude about the program external political position and technical expertise

B.

Level of influence and participation and attitude about the program

C.

Expectation of program benefits, level of influence, and organizational culture

D.

Level of support/opposition technical expertise, and organizational culture

Full Access
Question # 14

A company hires a program manager to create a healthcare management system. After five months the program manager identifies an opportunity to integrate an online medical solution, which could provide additional value to the stakeholders. The program sponsor approves the change in scope.

The program manager should ensure that the results obtained by this opportunity are working in tandem with which of the following?

A.

Critical success factors

B.

Key performance indicators

C.

Benefits management plan

D.

Stakeholder engagement plan

Full Access
Question # 15

When designing cable tray pathways under an access floor, what is the MINIMUM free space that should exist between the top of the cable tray side rails and the underside of the stringers?

A.

25 mm (1 in)

B.

51 mm (2 in)

C.

71 mm (3 in)

D.

101.60 mm (4 in)

Full Access
Question # 16

Which requirement does the ICT distribution designer provide to the Mechanical Engineer in charge of the HVAC design for a Telecommunication Space?

A.

The heat load (BTU (calories/hour) of all equipment installed within the space

B.

Location of the telecommunications own dedicated electrical distribution panel

C.

The quantity and size of HVAC vents needed for the room

D.

Location and size of condensate drain

Full Access
Question # 17

Exhibit:

What does this international symbol stands for?

A.

Teletypewriter/text telephone

B.

Public internet station

C.

Public telephone

D.

Public telephone with a shelfette

E.

Public telephone with access to high-speed internet connection

Full Access
Question # 18

A program manager learns that their company's organizational strategy has changed This change impacts one component project of a program misaligning it with both the program objectives and the new organizational strategy This component project, however, is already 90 percent complete.

What should the program manager do next?

A.

Immediately submit a component project closure request to the program sponsor so that resources can be reallocated to strategically aligned component projects.

B.

Assess the impact of closure on other component projects, and generate a recommendation for submission to the program governance board

C.

Recommend that the component project manager complete work activity to deliver benefits to the organization

D.

Update the benefits management plan to reflect the impact of the change on the program and its intended benefits

Full Access
Question # 19

When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

A.

Taxes

B.

Permits

C.

Inspection

D.

Licensing

E.

Safety

Full Access
Question # 20

A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components' strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools

Which of the following must be addressed?

A.

Program performance monitoring and controlling

B.

Program management information system (PMIS)

C.

Program delivery management

D.

Program roadmap

Full Access
Question # 21

A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase Tracking and reporting of actual benefits realized is one part of the review

What is the other part of the review"?

A.

Tracking and reporting on benefits management plan

B.

Identifying factors Influencing delivery of benefits

C.

Demonstrating that other stage gate requirements have been met

D.

Gathering additional stakeholders' requirements

Full Access
Question # 22

A voice over IP network that converges voice capabilities with softphones. Video communications, instant messaging is referred to as

A.

Ethernet network communications

B.

unified communications.

C.

mesh communications services

D.

converged communications

E.

unified fabric architecture

Full Access
Question # 23

An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building C. Both ends are terminated with SC connectors. What is the loss budget for the above fiber link?

A.

2.95 dB

B.

3.40dB

C.

3.90 dB

D.

4.35 dB

Full Access
Question # 24

A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations The high-level scope of this transformation encompasses three main areas.

1. The technology area—assessing which technology/tooling should be retained for the target data center

2. The policies and procedure area-aimed at establishing a common set of processes supporting the new way of delivering services

3. The HR area-assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions

You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase

Which document should be present m your business case?

A.

A detailed plan showing dependencies among the constituent protects

B.

A comprehensive analysis of the different compensation packages offered in the 16 countries

C.

An inventory detailing all physical and logical components in place and the employees in scope

D.

A cost/benefit analysis of the different scenarios, presenting their respective contributions

Full Access
Question # 25

A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.

What should the program manager do to ensure the success of the program?

A.

Meet with the vice president of purchasing to discuss the risks associated with preselecting a solution before the requirements have been gathered

B.

Host a kick-off meeting, request preliminary requirements from the marketing department, conduct a design session present the steering committee with a solution that meets the requirements: and meet with interested vendors

C.

Ask a senior marketing executive to act as the program sponsor and participate on the steering committee: require steering committee representation from the IT legal, and other key departments, validate that the chosen solution meets the requirements

D.

Initiate the program and begin a formal request for proposal (RFP) to validate the chosen solution and gam the confidence of the legal department

Full Access
Question # 26

Which two of the following are ADVANTAGES of aerial pathways? (Select two options.)

A.

Quick to install

B.

Has a low initial installation cost

C.

Affect the aesthetic appearance of the property

D.

Economical over a long life

E.

Readily accessible for maintenance

Full Access
Question # 27

Identify the core switch(es) and server(s) of the data center in the diagram below by dragging the appropriate term into each box in the diagram.

Full Access
Question # 28

What is the MINIMUM clearance needed between the front of the telephone booth and any wall or fixture for most installations?

A.

300 mm (12 in)

B.

450 mm (18 in)

C.

610 mm (24 in)

D.

914 mm (36 in)

E.

2.4 m (8 ft)

Full Access
Question # 29

A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years

What is the expected time of delivery?

A.

1.25 years

B.

1 50 years

C.

175 years

D.

1 00 years

Full Access
Question # 30

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs The program manager establishes earned value (EV) metrics and determines that the program has a budget of USS2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000

Based on this information, the program manager determines which of the following?

A.

The schedule is US%30.000 under budget

B.

The cost is US$20.0O0 under budget

C.

The schedule is US$10.000 over budget

D.

The cost is USS20.000 over budget

Full Access
Question # 31

The program manager wants to increase the team's commitment to the program objectives. The program manager should do which of the following?

A.

Work with the sponsor lo identify the organization's best practices

B.

Work with the program stakeholders and program management office to identify the organization's best practices

C.

Work with the program management office to identify the organization's best practices

D.

Work with the sponsor, program stakeholders, and the program management office to identify the organization's best practices

Full Access
Question # 32

The transfer of unwanted signals may occur over one path or several paths. What method addresses the mitigation or suppression of unwanted signals?

A.

Mounting heights in racks and cabinets

B.

Bonding and grounding

C.

Signal coupling

D.

The use of unshielded cables

Full Access
Question # 33

A program delivers incremental benefits but is far from closure. The company completes an acquisition and defines new strategic objectives.

What should the program manager do next?

A.

Evaluate the impact of the new strategic objectives through a change request

B.

Integrate the new acquisition into the program to include the new strategic objectives

C.

Assess the impact of the new acquisition on the contract management plan

D.

Review the benefits management plan to assess the continued validity of the program

Full Access
Question # 34

A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?

A.

Program sponsor

B.

Communications manager

C.

Project manager

D.

Program manager

Full Access
Question # 35

After new private equity owners acquire an enterprise, they want to improve its value by reducing costs A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed A strategic component project presents significant risk to organizational objectives due to Its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to Implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility Implementation of this component project may now begin, but is already one month behind schedule The program manager now perceives significantly more risk to the larger program due to this delay.

What should the program manager do to address this risk with the program sponsor and governance board?

A.

Share the concerns with the program sponsor to confirm understanding of the new development Next, update the program budget, implementation plan, and risk management plan for governance board approval

B.

Update the component project's risk register, issue log, implementation plan, and risk management plan next, meet with the program sponsor to revise the program budget. Implementation plan, and risk management plan for governance board approval

C.

Revise the program budget and Implement the component project by managing It closely to recover the month-long delay Next, update the component's project and risk management plans for governance board approval

D.

Update the program budget, and task the component project manager with implementing the plan next, submit a change order for approval to apply more resources to reduce the larger program's risk profile

Full Access
Question # 36

Identify the fibers below as either single mode (SM) or multi-mode (MM) by dragging the appropriate term into each oval.

Full Access
Question # 37

Telecommunications systems typically combine multiple digital data streams into one data stream. What is this process called?

A.

Time division multiplexing (TDM)

B.

Wave division multiplexing (WDM)

C.

Coarse wave time division multiplexing (CWTDM)

D.

Coarse wave division multiplexing (CWDM)

Full Access
Question # 38

An ICT distribution designer is designing a backbone cabling network that is specified for a campus network including several links approaching 2000 m (6562 It) and data rates of 100 Gb/s What optical fiber type(s) should be used?

A.

OM3 fiber

B.

OM4 fiber

C.

Both OS1 and OS2 fiber

D.

Both OS2 and OM3 fiber

Full Access
Question # 39

A program to implement a company's new system is nearing completion and the program manager attempts to close the program However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.

To prevent this concern in the future, which of the following should occur?

A.

Collaboration with the operational staff to develop the benefits sustainment plan

B.

Communication of the new capabilities" benefits to the operational staff

C.

Development and execution of a benefits transition plan to prepare the operational areas

D.

Identification of the risk in the program risk register and development of a plan to address the risk

Full Access
Question # 40

An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what appeared to be a significant risk resulted in a negligible risk.

What should the program manager recommend to stakeholders for future similar situations?

A.

Accept the risk

B.

Seek an expert opinion

C.

Establish an on-call risk response team

D.

Review the risk severity matrix

Full Access
Question # 41

A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end What should be completed first to close all appropriate contracts?

A.

Certify contract completion

B.

Conduct a procurement audit to review the procurement process

C.

Assess all contracts to ensure all agreed conditions are mot

D.

Review contract management plan for completeness

Full Access
Question # 42

What step can be a phase of the Bidding and Negotiating process?

A.

Prepare necessary change orders

B.

Identifying any conflicts that may become apparent

C.

Creating a response evaluation

D.

Identifying potential value engineering opportunities

Full Access
Question # 43

A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.

What should the program manager do next?

A.

Ask the finance department to increase the program budget

B.

Escalate the issue to the program governance board

C.

Ask key stakeholders to influence the program sponsor

D.

Direct component project managers to archive all relevant project documents

Full Access