Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for
this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance
Manager that it was a fixed price for a fixed specification' project. The Project Manager
has decided that the best way to tackle it would be to leave the development of the least
valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
The Marketing Director has insisted that detailed requirements for the new
coffee bar insurance web pages should be clearly defined in the early phases
of the project.
What action should the Project Manager take?
Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
'all members of the project understand and accept the DSDM approach'.
What action should the Project Manager take?
Which 2 statements represent appropriate entries for the Development
Approach Definition?
Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re-
engage this group and explore discrepancies in understanding.
Is this an appropriate application of Agile Project Management for this project?
Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully
meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture
Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's
specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,
until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
Maintainability is a required attribute of the initial delivered solution
Deliver first, re-engineer later
Short-term, tactical solution
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying
controls to the end of Development Timebox C.
What action should the Project Manager take when considering the End of Timebox Review?
The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are
four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and
to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The
Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully?
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
How should the Project Manager assist the plumbers to deliver the plumbing?
During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what
needed to be done before these would be acceptable.
Is this an appropriate application of Agile Project Management for this project?
How should the Project Manager assist the electricians to deliver the wiring?
Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.
Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column
2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.
Each selection from Column 2 can be used once, more than once or not at all.