Weekend Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

AgilePM-Practitioner Questions and Answers

Question # 6

Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?

A.

Is an external consultant.

B.

Has good leadership skills.

C.

Has experience of working with the company previously.

D.

Has a good, technical understanding of the work of the other professionals engaged in the project.

E.

Is an authority on local planning applications.

Full Access
Question # 7

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

Full Access
Question # 8

Which 2 statements represent appropriate entries for the Prioritised

Requirements List?

A.

Creation of a new coffee shop insurance product on the existing website

is expected to increase the insurance company's revenues by up to 10%

per week.

B.

All correspondence sent to coffee shop owners by the new system should

contain the XAN logo in the top left hand corner of the page.

C.

Further website developments to allow existing customers to access

services online are NOT to be included within the scope of this project.

D.

The Business Visionary will provide a formal acceptance of the coffee

shop insurance product.

E.

An assessment will be made of the effectiveness of the techniques used

on the project, in line with the principles of Agile Project Management.

Full Access
Question # 9

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Full Access
Question # 10

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.

D.

Source and hire a web developer with experience in developing online

financial transaction functionality.

E.

Consolidate and circulate an agenda for the workshop.

Full Access
Question # 11

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

Full Access
Question # 12

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Full Access
Question # 13

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?

A.

Refuse to discuss any detailed requirements in the early phases.

B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.

C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.

D.

Capture the Marketing Director's requirements in detail but leave the

input of others until later in the project.

Full Access
Question # 14

Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?

A.

Try to secure formal agreement as to how many hours per week the

marketing assistants will spend on the project.

B.

Accept that members of the Solution Development Team will be

inconsistent.

C.

Make each Timebox as long as possible to ensure the marketing

assistants have enough time to complete any work allocated to them

within the boundaries of the Timebox.

D.

Schedule the two marketing assistants to work at different times so they

can hand matters over to one another.

Full Access
Question # 15

The Web Content Manager has provided the Web Developer with a mock up

of the 'Contact Us' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads 'Delete' instead of 'Cancel'.

What action should the Web Content Manager take?

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Full Access
Question # 16

Which 2 statements represent appropriate entries for the Development

Approach Definition?

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called 'WebMatrix' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Full Access
Question # 17

A difference of opinion on the outcome of an earlier project has created a

'them and us' culture between the Sales Department and the Operations

Department.

What action should the Project Manager take to resolve this?

A.

Allow the different skillsets to work independently of one another so as

not to create further conflict.

B.

Brief the team and the Business Visionary on the use of an Agile Project

Management approach and the requirement to collaborate.

C.

Appoint only those members of staff who are prepared to work

collaboratively.

D.

Circulate a copy of the Business Case to all members of the Solution

Development Team and project-level roles and invite feedback.

Full Access
Question # 18

Which 2 actions should the Team Leader take to implement the new Must

Have requirement?

A.

Consolidate and circulate an agenda for the workshop.

B.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

C.

Discuss the development interfaces and dependencies with the Solution

Development Team to ensure the associated Timebox is appropriate.

D.

Agree to de-scope Should Have and/or Could Have requirements to allow

for the new Must Have functionality.

E.

Source and hire a web developer with experience in developing online

financial transaction functionality.

Full Access
Question # 19

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

'all members of the project understand and accept the DSDM approach'.

What action should the Project Manager take?

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Full Access
Question # 20

Which 2 actions should the Workshop Facilitator take to implement the new

Must Have requirement?

A.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

B.

Consolidate and circulate an agenda for the workshop.

C.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

D.

Assess the impact of the additional development costs on the original

Business Case.

E.

Encourage all parties to contribute, irrespective of their views.

Full Access
Question # 21

Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.

2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.

3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.

4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.

5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.

Column 2:

A) Thought

B) Action

C) Conversation

Full Access
Question # 22

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Full Access
Question # 23

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?

A.

Yes, because only Must Have requirements should be fully understood.

B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.

C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.

D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.

Full Access
Question # 24

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

At the beginning of Solution Development Timebox A, the Timebox is being

planned in detail. Although Foundations was conducted at a high level, the

Prioritised Requirements List was baselined. Now the Solution Development

Team is setting detailed acceptance criteria against each requirement.

Is this an appropriate approach to setting detailed acceptance criteria?

A.

Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.

B.

Yes, because the Solution Development Team members will be setting acceptance criteria for the first time during Solution Development Timebox A.

C.

No, because the Solution Development Team should NOT be involved in setting acceptance criteria.

D.

No, because acceptance criteria should be set in detail against each requirement during Foundations.

Full Access
Question # 25

Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.

Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully

meet Hoy Hall requirements, after deployment.

2. Developing a fully functioning in-house system, developed and hosted by Architecture

Angels IT Operations team.

3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's

specification.

4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,

until a suitable system can be implemented at the site.

5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.

Column 2

    Maintainability is a required attribute of the initial delivered solution

    Deliver first, re-engineer later

    Short-term, tactical solution

Full Access
Question # 26

The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the

agreement of the team.

Which Agile principle MOST influences this course of action?

A.

Deliver on time.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Full Access
Question # 27

A three-month timeframe has been specified to catch the seasonal sales window.

Which Agile principle MOST influences this course of action?

A.

Focus on the business need.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Full Access
Question # 28

Which 2 actions should the Workshop Facilitator take when preparing for the workshop?

A.

Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.

B.

Invite the Marketing Director to create a summary of the content they believe the system should hold and why.

C.

Assign ownership of the workshop to the Software Developer.

D.

Ask the IT Operations Manager to prepare the agenda for the workshop.

E.

Research other hotel reservation systems to form an opinion on what the content should be.

Full Access
Question # 29

Which information could be recorded on an ‘empathy map’ for the marketing staff?

A.

The Promotions Team Leader has noted that staff have raised concerns about how the change may reduce their sales during the seasonal promotions.

B.

The Marketing Manager has identified potential stakeholders, drawn symbolic figures of each of them and positioned them on a visual diagram.

C.

The Marketing analyst staff have made a list of potential stakeholders and plan to share this with everyone else at the next sales meeting.

D.

During a meeting of Brand Team Leaders, each participant created a list of stakeholders and then compared these lists in small groups.

Full Access
Question # 30

The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.

Which action is MOST likely to promote success in the induction of the change agent network to the Operational delivery processes workstream?

A.

Allocate bonus payments to change agents who deliver quicker than planned.

B.

Ensure that the CEO, as Sponsor, allows time to get to know the change agents.

C.

Transfer the change agents for a short period to help the other three workstreams.

D.

Negotiate that the change agents have direct authority to implement changes.

Full Access
Question # 31

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Do the measures to be monitored by the CEO represent appropriate ‘leading’, result-oriented measures for the effectiveness of the change interventions?

A.

No, because ‘leading’ metrics must be based on quantitative data.

B.

No, because these metrics are lagging, output-focused indicators.

C.

Yes, because these indicators will identify if UniCo sales continue to decline.

D.

Yes, because these metrics monitor benefits realization at senior management level.

Full Access
Question # 32

When receiving instruction on practical skills, which approach is MOST valuable to the learner?

A.

Practicing new skills until consistency is achieved.

B.

Observing repeated demonstrations of the skill by the instructor.

C.

Group discussion of how to learn the new skills.

D.

Presentation of how the new skills relate to the organizational change.

Full Access
Question # 33

The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.

Which approach is MOST likely to be relevant when deciding on the size of the change network for the Operational delivery processes workstream?

A.

Immediately assign two change agents as the fulfillment of the new contract will focus the change.

B.

Recruit change agents mainly from the IT support staff experiencing the most change.

C.

Select change agents in the Applications and IT Support areas to cover both locations.

D.

Involve as many agents as possible from the Selco staff to utilize their experience.

Full Access
Question # 34

Which is the BEST reason to remind learners of related knowledge or skill they already possess?

A.

Enables learners to understand how they learn.

B.

Helps learners plan to use immediately what they learn.

C.

Increases learners’ understanding of what the new learning will enable them to do.

D.

Reduces learners’ concerns about new learning.

Full Access
Question # 35

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Within Sales, which 2 people would be the BEST candidates to use as change agents, based on the descriptions given?

A.

The Sales Director, who is keen to sell mobile applications to clients and manages the department.

B.

One of the existing long-standing members of the Sales staff, who is good at getting things done across the organization.

C.

One of the existing members of the Sales staff, who is resistant to the change but is diligent and responsible in all tasks.

D.

One of the new members of the Sales staff, who has previous experience selling mobile applications.

E.

The Sales Administrator, who ensures that the sales processes run smoothly and works with all levels of Sales staff.

Full Access
Question # 36

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions. Answer the following questions about the use of David Rock's SCARF framework to increase the motivation for change.

On seeing plans for the office move, the Selco staff are worried that some desk allocations do not have access to natural light. The relocation leadership team held a workshop as soon as the issue was raised and has allocated these desks to be ‘hot-desks,’ not used by staff permanently based in the office.

Is this an appropriate approach to reward the brain in the need for ‘certainty,’ and why?

A.

No, because a change solution needs to be permanent to achieve ‘certainty.’

B.

No, because the resolution of the issue should be delegated to those affected.

C.

Yes, because loss of ‘certainty’ mostly affects those at lower organizational levels.

D.

Yes, because ‘certainty’ is rewarded when issues can be resolved promptly and openly.

Full Access
Question # 37

The Change Manager has read Goleman's articles on the Hay-McBer six dimension model of organization climate. This gives leaders practical ways that

leadership style can improve organizational culture and performance as measured by staff surveys.

Answer the following question about recommendations a change manager could make to the CEO applying these six dimensions to improve climate across the

organization.

Column 1 is a list of recommendations the Change Manager has made to the CEO seeking to initiate or support a change in the organizational culture. For each

recommendation in Column 1, select from Column 2 the 'dimension' in organizational climate MOST likely to improve as a result. Each selection from Column 2 can be

used once, more than once or not at all.

Full Access
Question # 38

Which 2 actions demonstrate empathy?

A.

Allow people to think independently and plan for themselves how this Change Programme could be incorporated.

B.

Hold a weekly progress meeting with key UniCo and Selco staff dedicated to the delivery of the new contract.

C.

Provide statistical data on the general trends in the mobile application industry to help people rationalize why this change is necessary.

D.

Reschedule plans to allow extra time for those IT support staff who are finding it difficult to try out the new processes.

E.

Encourage the CEO to discuss their previous concerns about the new company direction with staff who feel uncertain.

Full Access
Question # 39

The Legal Specialist has reviewed the plans for the rebranding work and has assessed how this will affect current and future contracts. They are now pressing the Change Manager to establish the deadlines and to schedule when their input will be most needed.

Which preference does this behavior BEST display?

A.

Thinking.

B.

Feeling.

C.

Judging.

D.

Perceiving.

Full Access
Question # 40

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Are the measures and source data to be monitored by the Human Resources and Facilities Manager likely to have any of the limitations of data analytics?

A.

No, because reporting on staff data should only be carried out by Human Resources.

B.

No, because internal processes are likely to ensure a good data quality.

C.

Yes, because the volume of the source data is likely to be unmanageable.

D.

Yes, because the source data is unlikely to provide ‘real-time’ accuracy.

Full Access