Winter Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpt65

SPS Questions and Answers

Question # 6

True or False: Many Scrum Teams working on the same product create coordination

challenges that can be fully addressed by creating a communication plan.

A.

True

B.

False

Full Access
Question # 7

Scenario B: Six Team Nexus with complex dependencies

A six team Nexus is developing a complex product, with different parts of the product that only

certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside

the Nexus that are required for some of the work. In past Sprints the Nexus encountered

challenges dealing with the many dependencies between Scrum Teams.

Some individual Scrum Teams in this Nexus have said that they do not see how the work they

are doing is contributing to the product's progress. What is the best remedy for this situation?

(choose the best answer)

A.

During Nexus Sprint Planning, have all the teams plan the Sprint together in one

room, so they can see what other teams are working on.

B.

During Nexus Sprint Planning, ensure that all Scrum Teams understand the Nexus

Sprint Goal.

C.

Ask the Scrum Master to explain to the teams that the Product Owner can choose

which features to work on, as she has the final say.

D.

During Nexus Sprint Planning, ask each Scrum Team to create a Sprint Goal that

describes the purpose of the Sprint.

Full Access
Question # 8

During Cross-Team Refinement, the ordered Product Backlog (1 through 9) is mapped out so

the Nexus can visualize dependencies. For example, PBI 5 for Team Orange is dependent on

Team Red completing PBI 1.

All else being equal, which PBI is most concerning?

(choose the best answer)

A.

PBI 2, because it has the most dependencies.

B.

PBI 1, because it is on the top of the Product Backlog.

C.

PBI 1, because it is the first piece of work with a dependency.

D.

PBI 2, because there is a dependency with a different team on work that occurs

within the same Sprint.

Full Access
Question # 9

Scenario A: Nexus Sprint Review with Five Scrum Teams

There are five Scrum Teams working on a product. During the Nexus Sprint Review, the teams

present the results of the Sprint. After introductions, each team takes time to present their work

for inspection by individually showing the new features they have built. They are not using a

shared environment. The stakeholders do not provide much feedback. The event ends and

people filter out of the room.

What could help this Nexus create a single Integrated Increment for inspection at the Nexus

Sprint Review?

(choose the best answer)

A.

Reserve the last few days of the Sprint for testing and integration.

B.

Enforce a Definition of Done across the entire Nexus that includes integration.

C.

Have the Nexus Integration Team integrate all the work as early as possible.

D.

Have a Sprint dedicated to integration.

Full Access
Question # 10

How should Product Backlog items be chosen when multiple Scrum Teams work from the same

Product Backlog?

(choose the best answer)

A.

The Scrum Teams choose the Weighted Shortest Job First.

B.

The Developers pull work in agreement with the Product Owner.

C.

Each Scrum Team takes an equal number of items.

D.

The Scrum Team with the highest velocity pulls Product Backlog items first.

E.

The Product Owner should provide each team with its own Product Backlog.

Full Access
Question # 11

If two Scrum Teams are added to a product that previously had only one Scrum Team, what will

be the immediate impact on the productivity of the original Scrum Team?

(choose the best answer)

A.

Its productivity is likely to stay the same.

B.

Its productivity is likely to decrease.

C.

Its productivity is likely to increase.

Full Access
Question # 12

What are three benefits of self-managing Scrum Teams?

(choose the best three answers)

A.

Increased rule compliance.

B.

Increased self-accountability.

C.

Increased creativity.

D.

Increased commitment.

E.

Increased accuracy of estimates.

Full Access