Easter Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

PSPO-II Questions and Answers

Question # 6

If a Product Owner finds themselves with more work to do than they can give attention to, what

strategy can help them achieve the things that need to be done?

(choose the best answer)

A.

Break the product into components, each with their own Product Owner, and create a

"Chief Product Owner" role who is responsible for the integrated product.

B.

Split the Product Owner role into "Business Product Owner" and "Technical Product

Owner" roles to spread the work.

C.

Delegate tasks like detailing Product Backlog items, interviewing users, and

analyzing data to Developers.

D.

All of the above.

E.

None of the above.

Full Access
Question # 7

Which of the following activities should a Product Owner never do?

(choose the best answer)

A.

Decide when to release the product Increment.

B.

Dictate the Sprint Goal.

C.

Accept work done during the Sprint.

D.

Establish a Product Goal.

Full Access
Question # 8

Complete this sentence: The more uncertain you are about customer needs or market desires

(choose the best two answers)

A.

the smaller each release should be.

B.

the more you should focus on validating customer needs.

C.

the more likely it is that you should invest in a different product.

D.

the more important a risk management plan becomes.

Full Access
Question # 9

As a Product Owner you become aware that the quality assurance criteria, defined in the

Definition of Done, were not met for the latest Increment. Which of the following statements are

true?

(choose the best four answers)

A.

The next Sprint may be interrupted when quality issues are encountered.

B.

The project manager cannot effectively update the plan.

C.

The indication of progress on the Product Backlog is not transparent.

D.

The Scrum Team should not release the Increment.

E.

The incomplete Sprint Backlog items should be returned to the Product Backlog.

Full Access
Question # 10

The only person who can abnormally terminate a Sprint is?

(choose the best answer)

A.

The Developers.

B.

The Scrum Master.

C.

The Product Owner.

D.

The Stakeholders.

Full Access
Question # 11

What percent of the time should a Product Owner dedicate to the Scrum Team?

(choose the best two answers)

A.

100%.

B.

Enough time to avoid the waste that is created by delaying answers to the

Developers.

C.

As much as the stakeholders want to budget. Business analysts take over the

role the rest of the time.

D.

40%, or more if the stakeholders agree.

E.

Enough time to ensure that the product Increment is valuable and useful.

F.

Just enough time to keep the Developers from complaining.

Full Access
Question # 12

An effective Product Owner must:

(choose the best answer)

A.

Ensure that every stakeholder need is met.

B.

Be the "expert" opinion for all Product Backlog items.

C.

Ensure that the team is as productive as possible.

D.

Be the single point of contact for all stakeholders.

E.

All of the above.

F.

None of the above.

Full Access
Question # 13

Your product’s Current Value is low, and your most recent three releases have failed to improve the Current Value, but the Unrealized Value of the product is high.

    Yourproduct cost ratiois 85%, meaning that you have a very low capacity to deliver new features.

    Yourtime-to-marketis also quite long.

As a Product Owner focused on the long-term viability of your product, which strategy should you pursue?

A.

Drop the product: since you have not been able to improve customer satisfaction, it is better to focus on some other opportunity.

B.

Seek out and eliminate the sources of waste to improve your Product Cost Ratio and Time to Market, building a foundation for future innovation.

C.

Focus on identifying and delivering high-value features with the limited capacity you have, trying to win customers and increase revenue.

Full Access
Question # 14

Who is responsible for the Sprint Backlog?

A.

The Developers.

B.

The Scrum Master.

C.

The Product Owner.

D.

The Scrum Team.

Full Access
Question # 15

What activities would a Product Owner typically undertake in the phase between the end of the

current Sprint and the next Sprint's Sprint Planning?

(choose the best answer)

A.

Working with the Quality Assurance departments on the Increment of the current

Sprint.

B.

There are no such activities. The next Sprint starts immediately after the current

Sprint.

C.

Updating the project plan with the stakeholders.

D.

Refining the Product Backlog.

Full Access
Question # 16

Your stakeholders are very demanding and each of them has at least one feature that they say

is essential for the next release. As the Product Owner, you have validated that the feature

requests are all valid requests and would likely add value to your product. What should you do?

(choose the best answer)

A.

Escalate to the steering committee to make the call.

B.

Wait until all essential features are complete before releasing the product.

C.

Release when you can satisfy at least a single outcome, even though not all features

are implemented.

D.

Pick the two most influential stakeholders and satisfy their needs, then release.

Full Access
Question # 17

A Product Owner is needed for every:

(choose the best answer)

A.

Product.

B.

Portfolio.

C.

Program.

D.

All of the above.

Full Access
Question # 18

The Developers have struggled to get all of their forecasted work done during the last three

Sprints. As a Product Owner what steps could you take to help the Developers improve their

ability to deliver a done Increment?

(choose the best two answers)

A.

Ask the Scrum Master to help the Developers learn techniques for improving

their ability to forecast work.

B.

The Product Owner can spend more time with the Developers.

C.

Ensure that all Developers are top performers.

D.

Add more people to the team so they can get more done.

Full Access
Question # 19

A "cone of uncertainty" can be used to do what?

(choose the best answer)

A.

Represent the relative level of difficulty for predicting the velocity of individual team

members.

B.

Rapidly identify and prioritize all uncertainties.

C.

Determine whether to cut quality, similar to the "Iron Triangle" of project

management.

D.

Visualize the uncertainty of the potential value that a Scrum Team delivers over time.

Full Access
Question # 20

Why should the Product Owner care that the Developers adhere to the Definition of Done?

(choose the best two answers)

A.

To influence the Total Cost of Ownership of the product.

B.

To have transparency into what has been done at the end of each Sprint.

C.

To be able to reprimand the team when they do not meet their velocity goal for

the Sprint.

D.

To ensure the Developers achieve a high level of productivity over time.

Full Access
Question # 21

If a Scrum Team uses Product Backlog refinement, when should it occur?

(choose the best two answers)

A.

The Product Owner takes the time between the Sprints to do it.

B.

Business Analysts in the organization should do this work for the Scrum Team 1-

2 Sprints ahead of the development Sprints.

C.

The Product Owner and the Developers can refine the Product Backlog during

any Sprint as needed, ideally in advance of the upcoming Sprint.

D.

The Product Owner must do this as essential work in Sprint 0.

E.

The Product Owner and the Developers do it in the current Sprint if they have

been unable to do it in preceding Sprints.

Full Access
Question # 22

In order to justify the price increase of a product, your primary objective should be to:

(choose the best answer)

A.

Reduce the price for a period of time before increasing it above the original price.

B.

Improve the value experienced by the customer.

C.

Reduce the number of features to make the product easier to use.

D.

Add more features to make the product more attractive.

Full Access
Question # 23

Which of the following would likely be the least effective way to enhance the agility of your

future product development?

(choose the least effective approach)

A.

Consider whether there is a significantly large enough market for your product.

B.

Form a holistic view of how the customer sees your product.

C.

Clearly understand the producer, buyer/consumer relationship.

D.

Lean on your organizational efficiency and existing architecture to build your product

aligned to the current organization.

Full Access
Question # 24

When many Scrum Teams are working on the same product, should all of their Increments be

combined every Sprint?

(choose the best answer)

A.

No, each Scrum Team stands alone.

B.

Yes, otherwise the Product Owner and stakeholders are unable to accurately inspect

the Increment.

C.

Yes, but only for Scrum Teams whose work has dependencies.

D.

No, that is far too hard and must be done in a hardening Sprint.

Full Access