You want to trigger inhouse production of a semifinished material before a sales order for the corresponding finished good is received.Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semifinished material?
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?
Note: There are 2 correct answers to this question.
You are trying to create a production order NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.
Your project uses process orders for the production of liquid chemicals.
What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.
What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
You use planning strategy Finite Scheduling with Reverse want to allow scheduling in the past. How can you parameterize this in the strategy profile?
You want to use capacity availability checks for production orders. Which settings have to be made for this?
Note: There are 2 correct answers to this question.
Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.
What determines whether the planned independent requirements in dem management are consumed by other requirements? Note: There are 2 correct answers to this question.
Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.
What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.
In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.
Which of the following processes lead to an entry in the MRP planning file? Note: There are 2 correct answers to this question.
You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
During production order creation several valid production versions are found. How does the system choose the production version?
How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.