Halloween Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

C_TPLM22_67 Questions and Answers

Question # 6

Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?

Please choose the correct answer.

Response:

A.

Internally-processed activities

B.

Externally-processed activities

C.

Service activities

D.

Scheduled activities

Full Access
Question # 7

What do you choose when creating a new network by copying an operative network?

There are 3 correct answers to this question.

Response:

A.

PS texts

B.

Relationships

C.

Milestones

D.

WBS elements

Full Access
Question # 8

Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?

There are 2 correct answers to this question.

Response:

A.

Activate milestone functions.

B.

Activate indicator sales document date for milestones.

C.

Create a billing plan assigned to a sales order item.

D.

Set up percentage of completion for milestones.

E.

Create a billing plan assigned to a WBS element.

Full Access
Question # 9

When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?

There are 2 correct answers to this question.

Response:

A.

Tasks

B.

WBS

C.

Activities

D.

Operations

Full Access
Question # 10

What are the various options available for creating a WBS BOM?

There are 2 correct answers to this question.

Response:

A.

Copying a Material BOM

B.

Copying a sales order BOM

C.

Copying other WBS BOM

D.

BOM copy function

Full Access
Question # 11

What happens if the appended indicator is not set and an order is appended?

Please choose the correct answer.

Response:

A.

Order planned value is not added to the WBS planned value

B.

Order planned value is deducted from the WBS planned value

C.

Order planned value increases the WBS element planned value

D.

Order planned value is multiplied to the WBS element planned value

Full Access
Question # 12

In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)?

There are 2 correct answers to this question.

Response:

A.

Project view

B.

Resource view

C.

Work center view

D.

Assignment view

Full Access
Question # 13

Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.

In this scenario planned costs are determined for which of the following?

There are 3 correct answers to this question.

Response:

A.

Primary costs for general costs activities

B.

Primary costs for material components

C.

Primary costs for service activities

D.

Activity inputs for internally-processed activities

Full Access
Question # 14

How are cost-relevant items determined for stock materials while using planned costs in networks?

Please choose the correct answer.

Response:

A.

Activity master record

B.

Activity detail screen

C.

Overhead costs screen

D.

Automatic account determination

Full Access
Question # 15

In which of the following is the Capacity planning Indicator set?

Please choose the correct answer.

Response:

A.

Control Key

B.

Work Center

C.

Requirement

D.

Task

Full Access
Question # 16

Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed?

Please choose the correct answer.

Response:

A.

Cost indicators

B.

Project cost indicators

C.

Operative indicators

D.

Billing indicators

Full Access
Question # 17

A costumer uses cross-company-code projects with a top billing element and an additional billing element underneath for each company code. Although the internal billing between the lower-level WBS elements has been performed

correctly, the results analysis summarizes all values to the highest billing elements.

How can we split the results to the different company codes? *

A.

Split the project into different projects according to each company code

B.

Settle the WBS elements to the highest billing element before you do the results analysis

C.

Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly

D.

Change the project structure so that it corresponds better to the company's organizational structure

Full Access
Question # 18

In which type of project stock G/L account determination for project stock is controlled differently from collective stock using specific valuation classes for sales order stock and project stock in the material master?

There are 2 correct answers to this question.

Response:

A.

Valuated project stock

B.

Non-valuate project stock

C.

Sales order stock

D.

Purchase order stock

Full Access
Question # 19

Which of the following information regarding cost activity is not relevant for the calculation of planned costs?

Please choose the correct answer.

Response:

A.

Control key

B.

The cost element is defaulted for cost activities based on the network profile

C.

A unit costing that enables detailed planning with multiple cost elements, or an invoicing plan

D.

Cost activities based on external services

Full Access
Question # 20

Can the user status forbid business transactions that the system status allows?

Please choose the correct answer.

Response:

A.

No, user status can only create a warning.

B.

Yes, by creating an appropriate status profile.

C.

Yes, if the status number of the user status is defined with higher priority.

D.

No, system status has a higher priority than user status.

Full Access
Question # 21

Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?

Please choose the correct answer.

Response:

A.

Budget release function

B.

Budget carry forward function

C.

Budget transfer function

D.

Budget Return function

Full Access
Question # 22

Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?

There are 3 correct answers to this question.

Response:

A.

Scheduling of subnetworks and subordinate internal orders

B.

Introduction of a configurable level concept for the targeted selection of

C.

Scheduling that takes available capacities and material availability into

D.

Improve performance through the targeted selection of subnetworks to be

E.

Detailed subnetwork monitor

Full Access
Question # 23

Externally processed activities give rise to planned costs that are equivalent to the prices of the following?

There are 2 correct answers to this question.

Response:

A.

Purchasing Info records

B.

Price in the activity

C.

Services costs

D.

Actual costs

Full Access
Question # 24

How are various stock types managed for each material component?

Please choose the correct answer.

Response:

A.

Account assignment category

B.

Material group

C.

Item Category

D.

Billing type

Full Access