Winter Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpt65

Prince2-Foundation Questions and Answers

Question # 6

Which is a responsibility of a risk owner?

A.

Identify risks to the project that might occur in their department

B.

Own and authorize the use of the risk budget to fund risk responses

C.

Manage, monitor and control all aspects of an assigned risk

D.

Determine project risk appetite

Full Access
Question # 7

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

A.

To identify responses to risks documented in the business case

B.

To identify information about the project environment and objectives

C.

To identify the roles to be involved in risk management activities

D.

To identify uncertainties that may impact on the delivery of the project objectives

Full Access
Question # 8

Which risk response is applied on a pain/gain basis?

A.

Share

B.

Accept

C.

Exploit

D.

Enhance

Full Access
Question # 9

Which process provides information for the project board to review a completed stage and confirm continued business justification?

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Full Access
Question # 10

Which is a minimum requirement for applying the risk theme?

A.

Threats must be assessed for their impact on the viability of the project

B.

A single role that is responsible for all risks must be defined

C.

The PRINCE2 risk management procedure must be followed

D.

Team managers must maintain their own risk registers

Full Access
Question # 11

Where should decisions regarding the tailoring of the project be recorded?

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Stage plan

Full Access
Question # 12

What should be considered when defining the number of management stages in a project?

A.

When the team managers are available

B.

When key decisions need to be made

C.

When highlight reports will be submitted

D.

When project support will be available

Full Access
Question # 13

Which is a purpose of the Starting up a Project process?

A.

Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate

B.

Define the means of communication between the project and corporate or programme management

C.

Define the project controls

D.

Record any identified risks in the Risk Register

Full Access
Question # 14

Why is the 'learn from experience' principle applied to a project?

A.

To enable the project team to repeat successes from previous projects

B.

To enable the project team to develop a business case for the project

C.

To allow the project to be divided into management stages

D.

To enable the project team to use tolerances to delegate authority

Full Access
Question # 15

What is described as an organization's unique attitude towards risk taking

A.

Risk appetite

B.

Risk management

C.

Risk evaluation

D.

Risk tolerance

Full Access
Question # 16

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

A.

Creating a product flow diagram

B.

Writing the product description

C.

Writing a project product description

D.

Documenting the plan

Full Access
Question # 17

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

A.

Risk category

B.

Risk description

C.

Risk response

D.

Risk status

Full Access
Question # 18

Which role is responsible for appointing the senior user in a project that is independent from a program?

A.

The project manager

B.

The executive

C.

Corporate, program management or the customer

D.

Project assurance

Full Access
Question # 19

Which is a purpose of the 'initiating a project' process?

A.

To decide if it is worthwhile to initiate a project

B.

To decide on the project approach

C.

To establish solid foundations for a project

D.

To identify the number of work packages required

Full Access
Question # 20

Which theme verifies that a project's products are fit for purpose?

A.

Business case

B.

Organization

C.

Quality

D.

Progress

Full Access
Question # 21

Which product describes the method the project will use to engage with corporate, programme management or the customer?

A.

Quality management approach

B.

Communication management approach

C.

Change control approach

D.

Benefits management approach

Full Access
Question # 22

Which describes an off-specification?

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

Full Access
Question # 23

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

A.

Controlling a Stage

B.

Closing a Project

C.

Directing a Project

D.

Managing a Stage Boundary

Full Access
Question # 24

Which statements about quality assurance and project assurance are CORRECT?

1. They are both independent of the project manager

2. They are both the responsibility of the project board

3. They are both independent from the project management team

4. They both assure that applicable standards are being used

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 25

Identify the missing words in the following sentence.

The project manager [ ? ] for day-to-day management of the project.

A.

and the project board are responsible

B.

and the team manager(s) are accountable

C.

has responsibility

D.

decides who is responsible

Full Access
Question # 26

Identify the missing words in the following sentence.

The 'managing a stage boundary' process should be executed [ ? ] a management stage.

A.

when a stage plan has been prepared for

B.

at the beginning of

C.

when all the delivery steps have been completed within

D.

at, or close to the end of,

Full Access
Question # 27

According to PRINCE2, which characteristic is necessary for an effective project board?

A.

An ability to delegate

B.

An attention to detail

C.

A calm management style

D.

A 'problem-solving' approach

Full Access
Question # 28

Which are characteristics of stakeholders?

1. They are often affected by the project

2. They agree with every project objective

3. They are only/always external to the corporate organization

4. They typically interact with the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 29

To meet the minimum requirements for applying the progress theme, what must be considered?

A.

How lessons will be learned

B.

How time-driven reports will be produced

C.

Which management products will be baselined

D.

Who is responsible for reporting on progress

Full Access
Question # 30

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

Full Access
Question # 31

According to PRINCE2, why might there be more than one business case for a project?

A.

There may be more than one management stage in the project

B.

The project may be in a commercial environment with a number of suppliers

C.

There may be more than one work package being delivered in the project

D.

The project may be in a programme environment

Full Access
Question # 32

Which is an objective of the 'managing a product delivery' process?

A.

To ensure the business case is regularly reviewed

B.

To assess whether the stage products have been approved

C.

To deliver the planned specialist products within tolerance

D.

To request authorization to start the next stage

Full Access
Question # 33

Which product defines how the project board should approve the management products produced during the 'initiating a project' process?

A.

Communication management approach

B.

Quality management approach

C.

Project plan

D.

Initiation stage plan

Full Access
Question # 34

Who is responsible for documenting any tailoring of the business case theme?

A.

Executive

B.

Business project assurance

C.

Project manager

D.

Corporate management

Full Access
Question # 35

What is a risk actionee responsible for?

A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

Full Access
Question # 36

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

A.

Increase the frequency of checkpoint reports

B.

Allow the team manager more flexibility to exceed cost tolerance

C.

Increase the frequency of event-driven controls

D.

Increase the frequency of escalations by the team manager

Full Access
Question # 37

Identify the missing words in the following sentence.

The 'starting up a project" process is triggered when a [ ? J is available.

A.

project business case

B.

project mandate

C.

stage plan

D.

work package

Full Access
Question # 38

Which process has the objective of confirming that acceptance criteria have been met?

A.

Controlling a stage

B.

Directing a project

C.

Managing product delivery

D.

Closing a project

Full Access
Question # 39

What must be done for a project to be a PRINCE2 project?

A.

The project must form part of a programme or portfolio

B.

The project must meet the minimum requirements for applying the themes

C.

The project must use the recommended approach to planning

D.

The project roles must be combined wherever possible

Full Access
Question # 40

Which is 3 purpose of the ‘plans! practice?

A.

To enable an event that requires project management consideration to be controlled

B.

To provide the standards against which the project products can be quality controlled

C.

To provide the basis of control against which a project's progress can be monitored

D.

To enable control of opportunities and threats, that could Impact on delivery of the business objectives

Full Access
Question # 41

What 15the purpose of the ‘progress! practice?

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Full Access
Question # 42

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

A.

corporate, programme management or the customer

B.

the project board

C.

the project manager

D.

the change authority

Full Access
Question # 43

What is an advantage of dividing the project into stages?

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

Full Access
Question # 44

What is the minimum number of management stages required by PRINCE2?

A.

Two stages: to initiate and to deliver the project

B.

One stage: to cover the whole project

C.

Three stages: to initiate, to deliver and to close the project

D.

Four stages: to start, to initiate, to deliver and to close the project

Full Access
Question # 45

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Full Access
Question # 46

Which is an objective of the 'directing a project' process?

A.

To create the plan to deliver the project product

B.

To select and appoint the project manager

C.

To design the project management team roles

D.

To give authority to deliver the project product

Full Access
Question # 47

Which are purposes of the 'directing a project' process?

1. To enable the project board to be accountable for a project's success by making key decisions

2. To enable the project board to authorize work packages

3. To enable the project board to prepare the communication management approach

4. To enable the project board to exercise overall control of a project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 48

Which is an assumption about the PRINCE2 customer/supplier environment?

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Full Access
Question # 49

How are team managers involved in tailoring PRINCE2 suit the project?

A.

Team managers are accountable for the tailoring of the work packages

B.

Team managers may advice on tailoring to improve the management of work packages

C.

Team managers should not be involved in tailoring PRINCE2

D.

Team managers should document the tailoring of the work packages

Full Access
Question # 50

What should the benefits management approach define?

A.

What actions will be taken to ensure the project's outcomes are achieved

B.

What will be used to record the effectiveness of the project's approaches

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Full Access
Question # 51

What process provides information on a team’s work to the project manager?

A.

Controlling a stage

B.

Directing a project

C.

Managing a stage boundary

D.

Managing product delivery

Full Access
Question # 52

A new team member has joined the project team and wants to understand who else is on the project team, and who they report to.

Which management product should the team member review?

A.

Project plan

B.

Project management team structure

C.

Role descriptions

D.

Project log

Full Access
Question # 53

Which statement describes the context of the 'initiating a project" process?

A.

The project is viewed from the perspective of the project board in this process

B.

This process should result in key stakeholders being committed to the project

C.

This process is triggered by the assembly of the project brief

D.

The 'controlling a stage' process will start immediately after this process

Full Access
Question # 54

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

A.

benefits, change, risk,

B.

benefits, quality, risk,

C.

change, quality, risk,

D.

benefits, change, quality,

Full Access
Question # 55

Which is a purpose of the quality theme?

A.

To check that the project is viable and achievable

B.

To ensure that the project outputs are agreed

C.

To ensure that formal issues are recorded

D.

To enable the project to be managed according to plan

Full Access
Question # 56

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Project product description

Full Access
Question # 57

Which describes a time-driven control?

A.

The dates for the project's end stage assessment included in the project plan

B.

The expected frequency of progress reports specified in a work package

C.

The expected dates for planned checks of specialist products included in a stage plan

D.

The planned exception assessment meeting to authorize a requested exception plan

Full Access
Question # 58

Which is an objective of the 'controlling a stage' process?

A.

To review the business justification for the project

B.

To replan the current stage when directed

C.

To develop products to defined quality criteria

D.

To produce a learn plan for the work package

Full Access
Question # 59

Which term is defined as the means by which an organization transitions from its current state to the target state?

A.

Change management

B.

change control

C.

Progress management

D.

Risk management

Full Access
Question # 60

Which statement about project roles is CORRECT?

A.

The project organization must be defined using the roles and responsibilities in PRINCE2

B.

The project team structure defined in PRINCE2 must be used, but other roles may be added

C.

The project board roles defined in PRINCE2 must be used, but other roles can be defined as required

D.

Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled

Full Access
Question # 61

What must be produced to meet the minimum requirements when applying the change theme?

A.

A change budget for the analysis of change

B.

Records of the decisions made on all issues

C.

Documents recording the version of each product

D.

Status reports on all products being produced

Full Access
Question # 62

Why does the project board review the PID during an end stage assessment?

A.

To confirm that project controls are adequate for the remainder of the project

B.

To notify the commissioning organization that the project has been authorized

C.

To review summarized progress to date and decide what to do next with the project

D.

To ensure that post-project reviews of operational performance are planned

Full Access
Question # 63

Which term is defined-as the amount and type or risk that the business is willing to take in pursuit of is objectives?

A.

Risk appetite

B.

Opportunity

C.

Risk tolerance

D.

Risk cause

Full Access
Question # 64

What statement describes how the project manager should ensure effective communication within a project?

A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

Full Access
Question # 65

Identify the missing word in the following sentence.

[ ? ] is the measurable decline resulting from a negative outcome.

A.

An exception

B.

A dis-benefit

C.

An off-specification

D.

A risk

Full Access
Question # 66

The project manager reviews whether there has been a Change in the way team members relate to each other.

Which principle is the project manager applying as part of the 'people' element?

A.

Manage by stages

B.

Focus on products

C.

Tailor to suit the project context

D.

Learn from experience

Full Access
Question # 67

Which is a responsibility of the project board?

A.

To manage the team managers and project support

B.

To ensure production of the project's outputs

C.

To ensure effective communication with external stakeholders

D.

To implement the change control approach

Full Access
Question # 68

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Full Access
Question # 69

How many tasks does the product-based planning technique describe?

A.

One

B.

Two

C.

Three

D.

Four

Full Access
Question # 70

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

A.

project cost tolerance

B.

stage cost tolerance

C.

Work Package cost tolerance

D.

product cost tolerance

Full Access
Question # 71

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

A.

Closing a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Full Access
Question # 72

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Full Access
Question # 73

Which is a purpose of a Lessons Log?

A.

Note any lessons that are raised in Checkpoint Reports

B.

Record that corrective action is being taken

C.

Escalate lessons to the Project Board

D.

Raise improvements with Project Assurance

Full Access
Question # 74

Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Full Access
Question # 75

What is the definition of a project outcome?

A.

A measurable improvement that is perceived as an advantage by one or more stakeholders

B.

The reason for the project

C.

The result of the change derived from using the project's outputs

D.

The project's specialist products.

Full Access
Question # 76

Why is it crucial that the Project Product Description clearly defines acceptance methods?

A.

Enables Project Assurance to authorize quality activities

B.

Defines how all project products will be reviewed and approved

C.

Defines how it will be proven that the completed project product meets the customer's expectations

D.

Provides confirmation that all project products have met their quality criteria

Full Access
Question # 77

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

A.

Only corporate or programme management

B.

Only the Project Board

C.

Only the Project Manager

D.

All levels of management

Full Access
Question # 78

Which two roles are linked by the Managing Product Delivery process?

A.

Corporate or programme management and Project Board

B.

Project Board and Project Manager

C.

Project Manager and Team Manager

D.

Team Manager and external supplier

Full Access
Question # 79

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

A.

Progress

B.

Change

C.

Organization

D.

Quality

Full Access
Question # 80

Which is a task of product-based planning?

A.

Identify activities and dependencies

B.

Write the Project Product Description

C.

Prepare the Work Packages

D.

Produce Product Status Accounts

Full Access
Question # 81

Which is an objective of the Directing a Project process?

A.

Create and authorize the project mandate

B.

Provide management control and direction

C.

Control the day-to-day running of the project

D.

Provide accurate progress information to the Project Manager

Full Access
Question # 82

Which is an objective of the Managing Product Delivery process?

A.

Sign-off completed Work Packages

B.

Ensure the Business Case is kept under review

C.

Report progress to the Project Board

D.

Ensure that work on products is authorized and agreed with the team

Full Access
Question # 83

Which is part of quality control?

A.

Undertake quality reviews

B.

Write Product Descriptions

C.

Provide assurance that the project is being conducted properly

D.

Document the customer's quality expectations

Full Access
Question # 84

Which is a purpose of the Initiating a Project process?

A.

Decide if it is worthwhile to initiate a project

B.

Decide on the project approach

C.

Establish solid foundations for a project

D.

Identify the number of Work Packages required

Full Access
Question # 85

Which is a purpose of the Controlling a Stage process?

A.

Produce a Team Plan for the work to be assigned to a Team Manager

B.

Select and implement actions that will resolve deviations from a plan within tolerance

C.

Obtain approvals for products delivered in a Work Package

D.

Update a Project Plan to incorporate the actuals from a Stage Plan

Full Access
Question # 86

Which does the Executive need to ensure is in place before the project is initiated?

A.

All Work Packages are authorized

B.

An understanding of how the project will contribute to corporate objectives

C.

The Project Plan has been approved

D.

The Project Initiation Documentation is complete

Full Access
Question # 87

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Full Access
Question # 88

Which is a purpose of the Quality theme?

A.

Establish how the project will ensure that all products created meet their requirements

B.

Establish quality assurance to maintain the quality management system

C.

Identify all the products of the project to ensure the scope has been adequately defined

D.

Determine the communication needs of the organization's quality assurance function

Full Access
Question # 89

Which is a recommended quality review team role?

A.

Project Manager

B.

Assurance

C.

Chair

D.

Producer

Full Access
Question # 90

Which is a true statement about PRINCE2 event-driven controls?

A.

Event-driven controls take place at predefined periodic intervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls

Full Access
Question # 91

Which is a true statement about acceptance criteria?

A.

Acceptance criteria are used to produce the customer's quality expectations

B.

Acceptance criteria are less specific and precise than customer's quality expectations

C.

Once agreed, acceptance criteria CANNOT be changed

D.

Acceptance criteria should be agreed between the customer and the supplier

Full Access
Question # 92

What takes place during the Closing a Project process?

A.

The post-project benefits reviews are performed

B.

Ownership of the project's products is transferred to the customer

C.

An End Stage Report is prepared for the final stage

D.

The project closure notification is reviewed and approved

Full Access
Question # 93

Which product documents the information needed to demonstrate continued business justification?

A.

Business Case

B.

Communication Management Strategy

C.

Project Product Description

D.

Quality Management Strategy

Full Access
Question # 94

What is an off-specification?

A.

A new requirement

B.

A quality tolerance

C.

A type of issue

D.

A major risk

Full Access
Question # 95

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

A.

a solution should be designed for

B.

an issue should be created for

C.

the agreed actions should be recorded for

D.

the chair will approve the solution to

Full Access
Question # 96

From whom does a Team Manager obtain approval for a completed product?

A.

Project Manager

B.

Project Support

C.

The authority defined in the Product Description

D.

Senior Supplier

Full Access
Question # 97

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

A.

Specify the desired result

B.

Provide the resources and skills to deliver the desired result

C.

Pay for the project

D.

Specify the benefits of the project

Full Access
Question # 98

Which should be funded from a change budget?

A.

The Starting up a Project process

B.

A fallback plan

C.

An agreed change to the scope of a project

D.

A change to a plan, within allocated tolerances, due to poor estimating

Full Access
Question # 99

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

A.

Those with a financial interest in the project

B.

Those who will manage the project on a day-to-day basis

C.

Those who will specify the desired outputs of the project

D.

Those who will create the project's outputs

Full Access
Question # 100

What product is used to maintain a record of those who have an interest in the project and their information requirements?

A.

Project Plan

B.

Communication Management Strategy

C.

Project Brief

D.

Project Product Description

Full Access
Question # 101

Which is an objective of the Closing a Project process?

A.

Review and approve the plan for project closure

B.

Review the performance of the project against its baseline

C.

Perform any post-project reviews

D.

Create a Benefits Review Plan

Full Access
Question # 102

Which of the following statements about quality assurance and Project Assurance is true?

A.

Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board

B.

Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager

C.

Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

D.

Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Full Access
Question # 103

Which is NOT one of the PRINCE2 integrated elements?

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Full Access
Question # 104

Which statement about the 'manage by stages’ principle is CORRECT?

A.

The project board should authorize multiple stages at the same time

B.

The end of a stage should provide a control point for the project board

C.

A project should have fewer, longer stages when the risk exposure is high

D.

A project should have separate stages to plan, deliver and close the project

Full Access
Question # 105

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?

A.

Gathering user inputs

B.

Accepting products

C.

Describing the quality management approach

D.

controlling quality

Full Access
Question # 106

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

A.

Managing product delivery

B.

controlling a stage

C.

Managing a stage boundary

D.

closing a project

Full Access
Question # 107

Which is a description of a purpose of the 'managing product delivery’ process?

A.

To agree requirements for the delivery of specific products between the project manager and the team manager

B.

To report progress towards the delivery of a stage’s products to the project board

C.

To recognize that the project has no further contribution make towards achieving project objectives

D.

To plan how the project will approach the work to deliver the project products

Full Access
Question # 108

Which term is defined as the means by which an organization transitions to a desired future state?

A.

Change management

B.

Risk management

C.

Issue management

D.

Communication management

Full Access
Question # 109

According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?

A.

Risk

B.

Scope

C.

Quality

D.

Cost

Full Access
Question # 110

What does qualitative analysis of a risk assess, as a minimum?

A.

How soon each risk might occur

B.

The fallback plan for each risk

C.

The likelihood and the effect of each risk on objectives

D.

The speed with which the effect of each risk will be felt

Full Access
Question # 111

Which action contributes to achieving the ‘ensure continued business justification’ principle?

A.

Producing separate business cases for each customer and supplier involved in the project

B.

Defining the products that the project must produce in order to control change effectively

C.

Establishing limits of authority on the project based on defined tolerances

D.

Adapting PRINCEZ to the scale of investment and the delivery approach

Full Access
Question # 112

What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

A.

Benefits sustainability

B.

Product sustainability

C.

Delivery sustainability

D.

Quality sustainability

Full Access
Question # 113

What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?

A.

Performance target

B.

Project baseline

C.

Integrated elements

D.

Project context

Full Access
Question # 114

The project management team heeds t document quality antral events, such as testing

According to the guidance for effective quality management, haw should the events be documented?

A.

In stage of team plans to allow mare accurate scheduling

B.

As quality tolerances in product descriptions

C.

As acceptance criteria in the project product description

D.

In the quality management approach to plan the testing

Full Access
Question # 115

Identify the missing word in the following sentence.

An (?) is the result of change, normally affecting real-world behavior and circumstances:

A.

outcome

B.

exception

C.

output

D.

off-specification

Full Access
Question # 116

Which details the identified threats and Opportunities related in the project?

A.

Risk management approach

B.

Project plan

C.

Risk register

D.

Business case

Full Access
Question # 117

Which is a feature of PRINCE2?

A.

It is naturally right=sized to the scale of every project

B.

It promotes improving processes for every project

C.

It replaces the need to apply specialist Industry-specific lifecycles

D.

It focuses on completing the project on time as its main objective

Full Access
Question # 118

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?

A.

Defining and analysing the products

B.

Organizing work packages

C.

Preparing estimates

D.

Preparing a schedule

Full Access
Question # 119

When does the ‘directing a project’ process start?

A.

When the project manager submits the project brief for approval

B.

When the request to authorize a project is received

C.

After the project has been authorized by the business layer

D.

After the project mandate has been received

Full Access
Question # 120

Which is a definition of management?

A.

Directing the execution of project tasks as agreed for the project

B.

Away of working that characterises a group of people

C.

Being accountable to the business for the success of the project

D.

The party responsible for commissioning the project

Full Access
Question # 121

The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management’ technique should the project manager document this?

A.

Identify: define context and objectives

B.

Identify: identify threats and opportunities

C.

Assess: prioritize risks

D.

Assess: combine risk profile

Full Access
Question # 122

Which management product Soul guide the Project management team on how to manage multiple aspects of the project?

A.

Project initiation documentation

B.

Project plan

C.

Business case

D.

Exception plan

Full Access
Question # 123

Which statement about capability and competency within a project is CORRECT?

A.

People who appear to have the same skills and experience will probably undertake the same tasks in different ways

B.

People within a team will perform equally when working with different people

C.

People who have participated in developing ways of working are more willing to be managed

D.

People working as team members often have conflicting priorities contrary to the project's needs

Full Access
Question # 124

The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual

products being worked on.

Which part of effective issue management is the project manager applying?

A.

Baselines

B.

Change budget

C.

Change control

D.

Issue resolution

Full Access
Question # 125

Which control is time-driven?

A.

The creation of a highlight report

B.

The completion of the PID

C.

The creation of an exception report

D.

The end of the financial year

Full Access
Question # 126

Which is a definition of management?

A.

Instructing the execution of tasks in line with agreed ways of working

B.

Translating stakeholder requirements into quality criteria

C.

Assigning people with specific skills and capabilities to work on multiple projects

D.

Defining, assuring, and accepting products back into the business

Full Access
Question # 127

Which statement describes a purpose of the 'starting up a project’ process?

A.

To appoint people ta the major rales in the project management team

B.

Ta agree how a team manager will report progress

C.

To provide Information so that the business can understand the cost of delivering the project

D.

To provide management control Listen the project manager and the team managers

Full Access
Question # 128

How does product-based planning help to determine the project approach?

A.

By Identifying the outputs that the project trust deliver

B.

By planning in detail how to deliver the outputs over a more predictable time scale

C.

By managing constraints to the planned completion date for the project

D.

By dividing the delivery of the project's outputs into stages which do not overlap

Full Access
Question # 129

How should the ‘progress’ practice be used?

A.

To define how the products will be delivered to enable control

B.

To predict whether the benefits will exceed the costs

C.

To identify opportunities that may make the project more successful

D.

To deliver change which will benefit people in their day-to-day work

Full Access
Question # 130

According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?

A.

Project executive AND senior user

B.

Senior supplier AND team manager

C.

Project executive AND project manager

D.

Project manager AND team manager

Full Access
Question # 131

How is uncertainty identified, assessed and controlled?

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Full Access
Question # 132

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Which management product should the project manager produce?

A.

Benefits management approach

B.

Business case

C.

Quality management approach

D.

End project report

Full Access
Question # 133

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Full Access
Question # 134

Which plan should only be produced if the project is large and complex enough?

A.

Project plan

B.

Stags plan

C.

Team plan

D.

Exception plan

Full Access
Question # 135

The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.

Which principle is the project board applying?

A.

Manage by exception

B.

Manage by stages

C.

Ensure continued business Justification

D.

Focus on products

Full Access
Question # 136

Which is a description of a purpose of the communication management approach?

A.

To document for stakeholders the future business required to meet project objectives

B.

To document how the project team should control its interactions with stakeholders

C.

To document how to use financial incentives to motivate project team members

D.

To document the responsibilities of project team members for testing whether products are acceptable to users

Full Access
Question # 137

How is Uncertainty Identified, assessed and controlled?

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Full Access
Question # 138

The project manager needs to confirm that operational teams are responsible for the running of the outputs.

During which step of the ‘organizational design and development’ technique should the project manager ensure this?

A.

Manage the ongoing changes to the project ecosystem

B.

Transition the project into the organizational ecosystem

C.

Understand the organizational ecosystem

D.

Develop the project ecosystem

Full Access