Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
Which process provides information for the project board to review a completed stage and confirm continued business justification?
Where should decisions regarding the tailoring of the project be recorded?
What should be considered when defining the number of management stages in a project?
What is described as an organization's unique attitude towards risk taking
Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
Which role is responsible for appointing the senior user in a project that is independent from a program?
Which product describes the method the project will use to engage with corporate, programme management or the customer?
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
Identify the missing words in the following sentence.
The 'managing a stage boundary' process should be executed [ ? ] a management stage.
According to PRINCE2, which characteristic is necessary for an effective project board?
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project
To meet the minimum requirements for applying the progress theme, what must be considered?
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
According to PRINCE2, why might there be more than one business case for a project?
Which product defines how the project board should approve the management products produced during the 'initiating a project' process?
Who is responsible for documenting any tailoring of the business case theme?
Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?
Identify the missing words in the following sentence.
The 'starting up a project" process is triggered when a [ ? J is available.
Which process has the objective of confirming that acceptance criteria have been met?
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
Which report must be used to inform the project board of a predicted deviation from agreed stage limits?
Which are purposes of the 'directing a project' process?
1. To enable the project board to be accountable for a project's success by making key decisions
2. To enable the project board to authorize work packages
3. To enable the project board to prepare the communication management approach
4. To enable the project board to exercise overall control of a project
What process provides information on a team’s work to the project manager?
A new team member has joined the project team and wants to understand who else is on the project team, and who they report to.
Which management product should the team member review?
Which statement describes the context of the 'initiating a project" process?
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
Which term is defined as the means by which an organization transitions from its current state to the target state?
What must be produced to meet the minimum requirements when applying the change theme?
Which term is defined-as the amount and type or risk that the business is willing to take in pursuit of is objectives?
What statement describes how the project manager should ensure effective communication within a project?
Identify the missing word in the following sentence.
[ ? ] is the measurable decline resulting from a negative outcome.
The project manager reviews whether there has been a Change in the way team members relate to each other.
Which principle is the project manager applying as part of the 'people' element?
When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
Why is it crucial that the Project Product Description clearly defines acceptance methods?
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
Which does the Executive need to ensure is in place before the project is initiated?
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
Which product documents the information needed to demonstrate continued business justification?
Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
What product is used to maintain a record of those who have an interest in the project and their information requirements?
Which of the following statements about quality assurance and Project Assurance is true?
The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?
In which process should the specified quality methods he used to/prove that a product meets its quality criteria?
Which is a description of a purpose of the 'managing product delivery’ process?
Which term is defined as the means by which an organization transitions to a desired future state?
According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?
Which action contributes to achieving the ‘ensure continued business justification’ principle?
What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?
What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?
The project management team heeds t document quality antral events, such as testing
According to the guidance for effective quality management, haw should the events be documented?
Identify the missing word in the following sentence.
An (?) is the result of change, normally affecting real-world behavior and circumstances:
Which details the identified threats and Opportunities related in the project?
The project manager needs to understand what makes the outputs acceptable to the users.
In which step of the 'planning' technique should this occur?
The project manager needs to document how risk management will be undertaken during the project.
In which step of the 'risk management’ technique should the project manager document this?
Which management product Soul guide the Project management team on how to manage multiple aspects of the project?
Which statement about capability and competency within a project is CORRECT?
The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual
products being worked on.
Which part of effective issue management is the project manager applying?
Which statement describes a purpose of the 'starting up a project’ process?
According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.
Which management product should the project manager produce?
The project manager needs to record what will make file Users satisfied with the final product
Where should the project manager record this?
Which plan should only be produced if the project is large and complex enough?
The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.
Which principle is the project board applying?
Which is a description of a purpose of the communication management approach?
The project manager needs to confirm that operational teams are responsible for the running of the outputs.
During which step of the ‘organizational design and development’ technique should the project manager ensure this?