A project manager is assigned to lead a design for a new version of an existing
product with the technology and operations teams. The project manager organizes a joint
requirements session to determine the most practical ideas. The project manager was advised
that the session may become chaotic.
What should the project manager do to ensure the session is interactive, productive, and
efficient?
A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?
Eight people have been working on a project for an extended period of time. The
scope has changed significantly and the product owner has been replaced multiple times. The
team members are feeling disassociated from the project.
What should the project manager do to ensure team alignment with the goals?
A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.
What should the project manager ask the team to do?
Due to a recent company merger, a project manager from company B has been
assigned to a team that is comprised of team members from company A. At the start of the
project, conflicts arise due to a lack of clarity on processes and the project manager's
relationship with company B.
What should the project manager do to resolve this conflict?
A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.
What should the project manager do?
In an agile team, some of the team members are coming forward to ask for more
autonomy on the project. What should the project manager do in this situation?
A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?
In an ongoing project, stakeholders have been approaching team members for status
reports and changes without consulting the project manager. What should the project
manager do to ensure a successful project?
A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule
What should the project manager do?
A project manager is appointed to manage an infrastructure project that spans
across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.
What should the project manager do to ensure good collaboration between the remote project team members?
A project to implement a new process is still in development. When implemented,
the company will benefit by a reduction in utility costs. The project financial evaluation
indicates a payback of 3 years.
What should the project manager do to expedite the project delivery?
A newly appointed product owner is working with a project team that is using agile
for the first time. The product owner is constantly disrupting various team members throughout
the day to discuss progress. This has resulted in the team feeling micromanaged and
frustrated because of the constant disruptions.
How should the project manager proceed?
A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget
What should the project manager do?
A project manager working on a large-scale network implementation is frustrated
with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.
What should the project manager do first to proceed with this change?
During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.
In order to reach a consensus and have a successful project completion, what should the
project manager do first?
A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed
To what type of communication is the team member referring?
us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?
A project manager is assigned to a project related to taxes, which will be managed
using an agile approach. By reviewing lessons learned from a previous project, the project
manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?
A project team delivered a critical deliverable to the customer. The customer
complained that the maintenance manual was not included.
What should the project manager do next?
An agile team has started a new project. When should the project manager organize their first team retrospective?
A protect manager has just finished planning for a project when the client adds a new project team member The project manager Knows that the new team member only works remotely and is not in the main office. In addition, the new team member engages with decisions quickly in a face-to-face environment, but is slow to respond otherwise.
How should the project manager reflect this in their planning?
Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.
What should the project manager do to resolve this issue and help the team move on to the next iteration?
An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work
What should the project manager do?
A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback
What should the project manager do to resolve the issue?
The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?
The project manager realizes that the product owner has a lot of potential but is lacking communication skills. How should the project manager help the product owner to develop these skills while executing the project?
One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
A project manager is developing a project baseline schedule and has started to
assign team members to the project activities according to their function. What should the
project manager do in this phase?
A project manager is leading a project at a contracting company, and the project
team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.
What should the project manager do to avoid this situation in the future?
Vendor A submitted a bid for US$500,000. There is a 65% probability that the
vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come
in ahead of schedule for a savings of US$50,000.
What should the project manager determine as the value of the vendor's bid?
A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage
What should the project manager do?
A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.
How should the project manager handle this situation?
A project manager has been assigned with initiating a large project to deliver
complex equipment. Part of the project will be the result of a long research process, but once
this is completed, the other part of the project must be incrementally delivered to the
customer.
Which approach should the project manager choose for this project?
A customer interacts directly with a Scrum team and continually requests changes in
priorities. This causes confusion among the team members and they complain to the project
manager.
What should the project manager do?
A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.
What should the project manager do in this situation?
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?
A project manager is assigned to deliver an innovative solution that is part of a
brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.
How should the project manager bridge the gap and ensure the project delivers the expected
business value?
An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.
What should the project manager do?
A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met
How should the project manager approach the stakeholder?
A project team member has lost enthusiasm and is experiencing low morale for a
project they were once excited about. What should the project manager do?
A project manager is leading an electrical project that spans five towns. The project
manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?
A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.
What should the project manager do to ensure effective communication throughout the project?
During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements
Which technique should the project manager use to resolve this issue?
Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.
What should the project manager do to engage the stakeholders?
A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?
During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead
handle this situation?
A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.
What should the project manager do?
A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.
What should the project manager do?
A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs
to be delivered to the customer as a ready-to-use product .
Based on this scenario, what should the project manager focus on throughout the project life cycle?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.
What should the project manager do?
A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.
What should the project manager do?
A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools
In order to deliver the project successfully, what should the project manager focus on as part of the plan?
A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay
Which three actions should the project manager take to encourage engagement? (Choose three)
A project manager was recently assigned to a new project that is about to start. The
organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?
What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
The project team is planning a schedule with limited information. The team |s having
issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)
A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?
A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new
Hems
Match the risks on the left lo the correct category on the right.
A project manager for a construction site realizes the importance of stakeholder
relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.
What should the project manager do to customize the stakeholder engagement plan?
A project is approaching its project closure phase, and the project manager receives
an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.
Which three actions should the project manager ask the project specialist to take? (Choose
three)
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings?
A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.
What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?
A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.
What should the project manager do?
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.
What does the project lead need to do to prevent a risky situation in the next iterations?
A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix
What should the project manager do with regard to community engagement in this situation''
A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery
How should the project manager avoid this situation in the future?
A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation
What should the project manager do?
In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?
A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to
take action in advance to ensure the project succeeds.
What should the project manager do?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
During a kick-off meeting at the start of project execution, the vendor presents a
migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.
What should the project manager do?
A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing
Which three corrective actions should the project manager perform? (Choose three)
A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.
What should the project manager do?
During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred
What should the project manager do to address this issue?
An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?
A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.
How should the project manager proceed?
A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?
Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.
What tool should the project manager use to conduct meetings with the project team and clients?
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.
What should the project manager do?
A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in
one of the project teams.
What should the project manager do?
A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?
A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team
What should the project manager do to resolve this?
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase
What should the team do next?
A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?
A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?
During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables
How should the project manager mitigate this risk without compromising the completion date?
A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.
What is the appropriate course of action for the project manager to pursue?
At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.
What should the project manager do to start building the product faster?
A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit
Which two rules are appropriate tor the project manager to instill in the team? (Choose two)
A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented
What should the project manager do?
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs
How should the project manager ensure the work continues smoothly?
A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.
What should the project manager do moving forward?
A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
How should the project manager resolve this situation in their new role as servant leader?
A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.
Knowing that there are no additional funds available, how should the project manager proceed?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.
How should the team share tacit knowledge?
A project manager needs the team to define the steps and identify the risks of migrating data to a new system.
What type of leadership should the project manager use to accomplish this?
Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.
What should the project manager do to address this concern?
During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.
What should the project manager do to reduce exposure?
A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.
What should the project manager do next?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members
Which three actions should the project manager take? (Choose three)
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards
in order to ensure this, what should the project manager define and document?
A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.
What should the project manager do next?
A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.
What should the project manager have done*?
A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
A project manager became aware of misunderstandings between a key stakeholder
and a team member with regard to some of the features defined in the project scope. What
should the project manager do?
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
During the final iteration of the execution phase, the project has a cost performance
index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.
How should the project manager avoid a budget shortfall?
It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.
What should the project manager do?
During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining
What should the project manager do?
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?
A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.
What technique is the project manager applying?
An IT project manager has been referred to a new, highly rated vendor that provides quality assurance professional services, The project manager plans to engage the quality assurance vendor on a new project, but their rates do not fit into what was budgeted for the project.
What should the project manager do next?
A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be
enough to add business value.
With the project on a fixed budget, what should the project manager do next?
A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?
Throughout an entire project, the project manager took notes at every meeting with
team members. These notes provided useful insights from key stakeholders, which later
resulted in increased value to the project. The project manager thought it would be helpful to
keep these notes as a future reference for other project managers within the organization.
Where should the notes be located?
A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.
What should the project manager do to address the concem9
A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.
In what type of analysis should the project manager use this information?
A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided
details to the customer 2 weeks ago and set up a weekly conference call to effectively
communicate with them, but the customer has not been participating in the calls.
How should the project manager handle this situation?
The main project stakeholder was fired and replaced by another stakeholder. The
new stakeholder reviewed the project scope and requested numerous changes, arguing that
the stakeholder's team is unhappy with the results to date.
What should the project manager do?
A project manager is leading a project that is implementing an assembly line.
During the quality review meeting, a team member reports an issue stating that the product
being developed has discrepancies with the one requested by the customer.
What should the project manager do?
A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?
An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed
What action should the project manager take?
A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project
How should the project manager report this cost?
A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?
A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?
A project has been running successfully for 2 months. At a regular project meeting,
the team raises several potential obstacles to future progress. The obstacles include vendor
delivery performance, technical performance of a subsystem, and conflict with another division of the organization.
What should the project manager do next?
A business improvement opportunity to reduce energy usage has been identified.
The project manager has assembled a team that includes site engineers to deliver this project.
However, due to production imperatives, the site engineers may not be fully focused on the
project.
How should the project manager manage the team?
A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.
Which distribution list should the project manager use when sending out invitations?
A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
During the executing phase, a project manager is reviewing the issue log and finds
there are outstanding high-priority issues that are still open. Most of the open issues require
effort from external domain experts who are not on the project team.
What should the project manager do?
A project manager who works for a company involved in several industries is asked
to lead a software development project for a government agency. The company attempted to
execute similar projects for other industries before but was unsuccessful.
What should the project manager do to ensure project success?
A company is conducting a digital transformation project that has a hard deadline.
The marketing team wants to combine this implementation with a new product, and the newly
assigned project manager is not aware of all the dependencies.
Using a hybrid approach, what should the project manager do to ensure the dependencies are
taken into consideration?
The change control board (CCB) has approved a change request to add a new
component within a product. The operations manager discovers the change after its approval
and complains that the implementation of the change will cause significant disruption to the
production line.
What should the project manager do first?
A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.
How should the project manager address this?
A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?
A project manager is working on a highly complex project. During the execution of
the project, the local government changed certain environmental regulations, which could
potentially delay the project.
What immediate action should the project manager take?
A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)
What should the project manager do to control this situation?
A project manager has been assigned with initiating a large project to deliver complex equipment Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.
Which approach should the project manager choose for this project?
A project manager is managing a government project that targets the development of
small businesses in remote towns. The project team is having difficulty conducting
entrepreneurship training in some of the targeted towns because the local municipal
governments will not authorize the training. As a result of the delay, project implementation is at risk.
What is a probable reason for this?
A project manager is working with a team that is new to agile. One of the more
influential stakeholders struggles with the nature of agile. The project manager knows that this
stakeholder is needed as an advocate and wants to do everything possible to make the
stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's
performance?
A company has always acquired very specialized services from local companies for
its projects. During the planning stage for a regulatory project, the project manager is informed
that local vendors would not be able to operate due to an unexpected major event. There is an
option to hire the same services from companies in other countries.
What should the project manager do in this situation?
A project manager is assigned to a new water treatment plant project that has been
delayed for many years. It is revealed in the project charter that the sponsors of this project
are from three different business units. This is the first time the sponsors have ever
implemented such a project.
What should the project manager do?
In the planning phase, a project manager receives identified risks from the sponsors
and subject matter experts (SMEs) and wants to develop a risk response strategy for them.
What should the project manager do first?
A key project stakeholder does not attend any of the project meetings and is
providing false information that the project team is not delivering on time. What should the
project manager do to address this situation?
A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?
A newly hired team member just joined the project team and reports directly to the
project manager. In the first week, this new member tells the project manager that there is a
task priority conflict with hard, dependent tasks on the critical path.
What should the project manager do to handle the conflict?
A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.
What should the project manager do?
A project manager receives a request for proposal (RFP) from a client. The client
is very clear about the requirements. A requirements analysis must be done in the first
month of the project, and the client wants to see a demo of the work completed every two
weeks.
What project approach should the project manager use?
A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.
What are the first two actions the project manager should perform? (Choose two)
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
On a transformational project, the project manager is confronted with resistance
from the stakeholders. To overcome this and gain acceptance of the change, what should
the project manager do first?
In a multinational project, stakeholders are in different time zones. The project
manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the
project sponsor that they know very little about the project.
What should the project manager do?
During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant
business value. What should the project manager do?
Close to the end of a project, a customer claims that some deliverables have not
been met and starts initiating change requests. What should the project manager do next?
An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.
What should the team do?
After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project
How should the project manager handle this situation?
A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.
What is the first thing the project manager should do"?
One of the service providers on a complex project has been facing resource
availability problems over the last six months. However, the service provider has assured the
project manager that the deliverables will be on time.
How should the project manager address this situation?
After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.
How should the project manager handle this situation?
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?
On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.
Who is responsible for analyzing the new requirement and making the final decision?
A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.
What should the project manager do next?
A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area
What should the project manager do first?
A project manager is assigned to a new project. The project management office
(PMO) and the project manager agree that this is the right opportunity to include daily
standup meetings. The project team has never used such tools, and a few members are
challenging the decision.
What should the project manager do in this situation?
Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.
What should the project manager do next?
A project manager is working with an agile team. A key stakeholder who does not
join the sprint planning session is very unhappy, as the delivery date for the final product has
been pushed back three times. What should the project manager do?
A team has been working together for several months and has successfully
delivered work. A new team member has joined the team but is having difficulty
contributing.
What should the project manager do to help the new team member integrate effectively?
An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?
A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?
A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?
A large company has agreed on a business case for an environmental project. The
project will cause some major changes in their operations, such as reduction in paper use,
which will obviously affect all of the users.
What is the first thing the appointed project manager should do?
A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.
How can the project manager convey these benefits to the stakeholders?
A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.
How should the project manager communicate the organizational culture and project goal to these stakeholders?
At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.
What should the project manager do next?
A company is planning a digitization project. Which action should the project
manager take first when defining the project scope?
A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?
Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.
How should the agile project leader resolve this situation?
A project started 12 months ago and is currently on iteration 12 of 14. The team
has performed well and completed all deliverables on time. However, some team members
are starting to complain about the length of the project, creating a risk for lack of
performance at this critical stage.
What should the project manager do as a servant leader to mitigate this risk?
A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.
What immediate action should the project manager take to improve the situation?
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?
A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is
frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.
What should the project manager do?
At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.
What should have been done to avoid this situation?
A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.
How should the project manager handle this situation?
A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager
schedules a meeting with the two stakeholders to resolve the issue.
What role does the project manager play in this situation?
During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?
A company Is helping their client launch an Innovative product. During the sprint review, the product owner identifies that the product does not include key features that were previously prioritized as part of the product backlog.
What should the project manager do next?
A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?
A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?
At the end of the last iteration, the customer rejects the deliverables since they did
not meet the customer's expectations. What should the project manager have been done
to prevent this situation?
A project needs to purchase a specific piece of equipment, as stated in the
project documents and approved by the project sponsor. The procurement division is
questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.
What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?
A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.
What should the project manager do?
Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)
A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings
What should the project manager do?
An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager
do with many tasks still open on the Kanban board?
A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.
What should the project manager do?
A product owner has an idea for a new product but is struggling to define the
features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?
A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.
What should the newly assigned project manager do first to understand the issues?
During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.
How should the PMO implement a better way to report the project's health?
A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.
What should the project manager have done to avoid this issue?
A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?
In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.
What should the project manager do to handle this situation?
A project manager receives feedback from the customer's leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?
A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team
requests a change in the sprint goals and sprint backlog items.
What should the project manager do?
An agile project has just started, and the backlog is being prioritized. The
customer wants to prioritize business value over identified risks.
How should the customer’s request be managed?
For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.
A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?
The project manager has recently received funding approval for a training program
for the entire project team but has not yet defined the most effective training course. One
team member submitted a request for specialized training that is required for the project.
How should the project manager handle this request?
A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.
What should the project manager do next?
A supplier was supposed to mobilize a government-issued, licensed piece of
equipment two days ago, but did not. The procurement manager was informed that the
supplier failed to check the validity of the license, which expired last week. The supplier had
already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.
Which action should the project manager take?
During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.
What should the project manager do first?
As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.
What should the project manager do?
A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?
A project manager for a building construction project is planning to go on vacation
midway through the project execution phase. What should the project manager do first to
ensure the team is empowered and deadlines are met?
A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?
The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.
What should the project manager do to ensure timely delivery?
A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.
What should the project manager do?
A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.
What should the project manager do?
A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?
A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?
A project manager is assigned to a strategic communication project that involves
subject matter experts (SMEs), interns, and new recruits. The project manager discovers
that the project is not gaining much traction due to knowledge gaps from the interns. The
budget for training is exhausted and the project needs to be delivered without delay.
Which two actions should the project manager take? (Choose two)
An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.
Which release strategy should the project manager recommend?
A company has agreed to run a transformation project using agile approaches.
During the implementation, there is pushback from the functional groups that the project is moving too fast.
What should the project manager have done at the beginning of the project to prevent this from happening?
The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.
How should the project manager approach this situation?
Match the project situation on the left to the meeting on the right where the situation could occur.
Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable
What should the project manager do next?
During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.
What two actions should the project manager take to prevent the team from being unqualified? (Choose two)
A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version
How can the project manager prevent this outcome in the new project?
During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?
During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?
A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?
During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level
What should the project manager do next with this opportunity?
A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches
What should the project manager do about the development team's request"?
At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?
After a meeting with the customer, the project manager receives special recognition because the project is always on schedule Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.
What should the project manager do in the project team meeting?
A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished
How should the project manager approach this situation?
A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.
How should these conflicts be resolved?
The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies
What should the project manager do?
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time
How should the project manager address this situation?
A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members
What is the cause for this communication gap?
A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?
A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project
What should the project manager do first to determine a governance approach for the project?
A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email
What should the project manager do?
A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks
Drag each risk type on the left to its correct example on the right
An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?
As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change
What should the project manager do?
A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year
Which project approach suits the scenario?
Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement
What should the project manager do next?
An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply
Which two actions should the project manager take? (Choose two)
Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members
What should the project manager do?
A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.
What should the project manager do to address this issued
A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.
How should the project manager respond’
A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.
What should the project manager do first to prevent the project from going further off track?
In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?
A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required
How should the project manager assist the product owner?
A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.
Which two actions should the team take to engage this new team member? (Choose two)
A food company is developing a new product using a predictive approach, and the product is currently in the testing phase Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach At the end of one of the iterations, a new regulation related to the product is enacted.
What should the project manager do next?
A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed
Which two actions should the project manager take? (Choose two)
The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right
A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.
What should the project manager have done to avoid this?
Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them
What strategy should the project manager use to resolve this conflict in the meeting?
A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.
How should the project manager respond'?
A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?
In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control
How should the project manager report the project status to key stakeholders?
In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?
Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished
What should the project manager have done differently?
A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right
At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?
An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?
During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization
What should the project manager do first?
An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project
Drag the mitigation strategy on the left to the project manager's actions on the right
During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.
What should the project manager do to prioritize this critical impediment?
A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)
A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.
What training should the project manager choose for their team to help with this situation?
During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.
What should the project manager calculate to address this critical budgetary situation? (Choose two)
A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project
What should the project manager have the project team update to ensure proper communications to stakeholders?
A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support
What approach should the project manager take?
A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.
How should the project manager plan the delivery of the project?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?
A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities
How should the stakeholder be engaged in the project?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented
What should the project manager do?
One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate
What interpersonal skill did the project manager use?
A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped
What should the project manager do?
A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago
What should the project manager do to analyze the involved stakeholders?
A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.
Which two documents should the project manager update as soon as possible? (Choose two)
A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated
What should the project manager do to address this issue?
A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
Drag the organizational characteristics on the left to the correct scenario on the right
A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery
Which two actions should the project manager take to mitigate this risk? (Choose two)
A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.
What should the project manager do first?
A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships
Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)
A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?
A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule
What can the project manager do to move the team to the norming phase?
A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.
How can the project manager promote empowerment and accountability among the team?
An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?
A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done?
A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful
What should the project manager do in this scenario?
After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.
What should the project manager do in order to gather the information needed from stakeholders?
The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.
What should the project manager do?
After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?
A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does
not have a requirement for it.
What should the project manager do?
During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific
component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality
management plan and there is no reference to this component.
What should the project manager do next?
During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.
What should the project manager do next?
A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.
What should the project manager do first?
A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.
What should the project manager have done to avoid this situation?
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.
What should the project manager do?
A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.
What should be me project manager's response?
While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because
of that, each feature is taking longer than initially estimated.
What should the project manager do to address the issue?
A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional
managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.
What should the project manager do?
A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.
What should the project manager do In this scenario?
A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.
What should the project manager do?
A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.
How should the project manager respond to this request?
The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could
resolve the bottleneck, and the project manager has been informed.
What should the project manager do next?
A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.
What should the project manager have done to avoid this situation?
The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:
• The marketing director is the key stakeholder. as the project will create a new product for the company.
• The finance director is providing funding and does not have much time to follow the tracking of the project.
• The sales representatives assigned to the team provided some negative feedback on the requirements
• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.
What should the project manager do?
In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?
A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?
During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project
manager is not sure if some of the project deliverables will be fully compliant with the new requirements.
What should the project manager do?
At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting
with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.
What should the project manager do to assess the priorities and meet the new objective?
In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in
conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?
A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of
the team. What should the project manager do?
A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.
What should the project manager do first?
A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)
needs visibility of the regulatory constraints while maintaining a degree of flexibility.
Which tool can the project manager use?
A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.
Which technique will best serve this purpose?
A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk
materialized and the project time line had to be extended by 2 months.
Which two actions should the project manager take? (Choose two)
An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.
The team estimates the risk level as low.
What should the project manager do?
A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.
What should the project manager do?
A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is
seeking the project manager's recommendation on how to approach this request.
What should the project manager do to help the product owner?
An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.
What should the project manager, who is responsible for this project, do to mitigate this risk?
A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a
predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams
are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current
impediments.
What should the project manager do?
A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,
* Actual progress = 2 units
* Planned progress = 3 units
* Actual cost (AC) = 2 units
* Budgeted cost = 3 units
What statement should the project manager make to the project steering committee?
A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?
A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.
What should the project manager do?
A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.
What should the project manager do?
A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even
though reports have been sent on a weekly basis.
What should the project manager do to ensure all stakeholders are receiving proper information about the project?
A project manager is working on a software development project. The project manager and the project team identified the project risks. As the
project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.
At what point did the project manager move the risk from the risk register to the issue log?
A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?
A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.
What should the project manager do?
A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.
What should the project manager do?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience
performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for
the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.
Which stakeholders should the project manager include in the stakeholder engagement plan?
A project team needs to follow regulatory compliance guidelines that are mandatory for the project. What should the project manager do to ensure compliance adherence?
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the
quality standards required by regulations.
What should the project manager have done to avoid this?
During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.
What should the project manager do next?
A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday
morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team
What should the project manager do?
During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that
could become unmanageable with time. What should the project manager do?
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.
What should the project manager do next?
The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?
An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.
Who should the project manager contact to help the team accelerate the delivery?
An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they
are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.
What should the project manager do to get commitment from the sales agents?
Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the
company’s competitive advantage. What should the project manager do?
A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project
stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.
What should the project manager do?
An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.
What should the project manager do?
An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing
the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.
What should the project manager do?
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What
should the project lead do next?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.
What should the project manager do?
A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager
do to address this situation?
A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,
What should the project manager, as a servant leader, do to address this situation?
A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team
members who are confused about the next steps and the final outcome of the project.
What should the new project manager do?
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start
activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the
project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.
What should the project manager do?
A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of
risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk
mitigation plan.
What should the project manager do?
A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.
What should the project manager do to create a positive environment?
A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.
A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.
What should the project manager do?
A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly.
This uncertainty from the junior engineers is now slowing progress.
‘What should the project manager do?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.
What should the project manager do in this situation as a servant leader?
In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.
What should the project manager do?
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail
the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.
What should the project manager do next?
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.
How can the project manager ensure that the appropriate acceptance criteria are applied to the features?
Drag the communication event on the left to the main subject discussed during the event on the right.
A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The
resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
What should the project manager do?
A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of
completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next
milestone. This change can be perceived as poor performance by the current assignees.
What should the project manager do?
A team needs to implement a mandatory compliance regulation in a product, which is required for its release. While nearing the product release, when completeness was
being verified, it was found that the compliance part was not implemented in the project.
What should the project manager do next?
A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team
interactions must be considered.
How should the project teams interact in their meetings?
During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.
How should the project manager address this issue?
A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.
How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?
A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.
What should the project manager recommend?
During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.
How should the project manager handle this issue?
A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule, with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.
What should the project manager do first?
A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project.
What should the project manager have done to prevent this?
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
Some of the more experienced members of a project team have complained about the project manager. The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.
What should the project manager do when made aware of these issues?
An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started
working at the company. In the first meeting with the project manager, the director demands a weekly project status report.
What should the project manager do?
A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.
How should the project manager deal with the situation?
An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.
How should the facilitator proceed?
A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project, customer satisfaction is
a big issue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service
team is overwhelmed with these unresolved queries.
Which two actions should the project manager take to correct this problem? (Choose two)
A large construction project is progressing well as per the project objectives. The project manager would like to report the project's value to the project sponsor and seek the
next phase of funding closure.
What should the project manager do?
A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process
What should the project manager do?
The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.
What should the project manager do first?
A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.
One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?
A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no
longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects,
and there is no capacity for any developer to take on additional work.
What should the project manager do next to fulfill this resource need?
A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.
Which scheduling method should the project manager use to develop the schedule?
A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns
that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.
Which action should the project manager take to procure the vehicles?
A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.
What should the project manager do?
A project manager is leading a hybrid project funded by a time and materials (T&M) agreement. The project was completed, and the client
accepted the delivery of the product. One week later, the client asked the project manager to fix two defects they found in the product. The project
manager responded with an estimate of time and money and asked the client to confirm this. The client disagreed and insisted that the work
should be done for free because it is a defect in the product.
What should the project manager have done to prevent this?
A senior vice president requested the creation of more agile teams to run projects of varying lengths and complexities in parallel with each other.
This will impact the amount of time the project managers will be able to dedicate to each project. The project managers typically dedicate 50% of
their time to projects regardless of their complexity.
What should the project manager do as a servant leader to help achieve this transformation?
A project manager is starting a new project, and the project team is located in different countries. The team was going to use a specific tool to hold virtual meetings.
However, that tool is not available in one team member's country.
How should the project manager deal with this situation?
An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and followup calls with key stakeholders. The team seems to be disengaged.
How should the project manager approach this situation?
A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?
Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?
A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.
What should the project manager do to address the issue?
A project manager works in a matrix organization and is managing an internal software development project that is intended to reduce conflicts in the company's internal tracking system. During development, the project manager is informed that the software has to account for an unexpected change to government accounting requirements. The development team was able to make the change with no additional cost; however, the project manager notices that the testing costs are beginning
to exceed the testing budget.
What should the project manager do?
A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor
management team will not derive any benefits from the project. However, the project requires support from the vendor management head.
What should the project manager do next?
A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.
What should the project manager do next?
While monitoring a project at a work site, the project manager notices that the site team’s work breaks have increased by a few minutes every week. How should the project
manager approach this?
An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.
What should the project manager do to help the project team?
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?
A project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager's emails are very harsh.
What should the project manager do to solve this situation?
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will
take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6
months.
What should the project manager do to align stakeholders’ needs and expectations?
During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.
What should the project manager do first?
A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.
What should the project manager have done to prevent this from happening?
A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.
What should the project manager do?
A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose two)
A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version
is not clear to the stakeholders.
What should the project manager do to increase value delivery?
A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?
A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.
What should the project manager do next?
A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project
time lines have slipped, and the staff is overwhelmed .
What should the project manager do to help the company meet their financial objectives?
A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders.
What should the internal project manager do first?
A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.
What should the project manager have done to avoid this setback?
A stressful situation has presented some challenges for the team. The project manager notices stress behavior in some of the team members, and it is beginning to spread across the group. The project manager needs to coach the team to change their mindset in order to be more efficient.
What should the project manager do?
After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are
being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting
market requirements.
What should the project manager do?
A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action.
What should the project manager do to avoid similar complaints?
During the execution of a project, a key stakeholder complains to the project manager about recent communications.
The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.
What should the project manager do?
A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the
original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.
What should the project manager do to resolve this conflict?
A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.
What should the project manager do first to evaluate the cultural differences within the organizations?
A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.
What should the project manager do?
A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not
be able to provide assistance for 1 week.
How should the project manager address this situation?
A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office
(PMO) recommends the project manager to lead the next similar project.
What should the project manager do next?
A project manager is leading a product feature rollout that will gain more subscribers for a video-streaming application. During the backlog grooming phase, the business stakeholders were unable to understand the feature integration with the product and raised concerns.
What can the project manager do to demonstrate the feature integration?
A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.
What should the project manager do next?
In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.
What should the project manager do?
Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.
What should the project manager do?
A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.
What should the project manager do?
An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project.
What should the project lead do?
A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be
engaged in how the project will be executed.
How should the project manager proceed?
A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.
What should the project manager do next?
A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on
the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.
Which life cycle should the project manager use for this project?
A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources
and has appointed a project manager.
What should the project manager recommend that the CEO do first?
A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.
What should the project manager do next?
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project
manager knows this team member could add value to the project.
What should the project manager do to get the most value from this team member?
Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?
A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.
What should the project manager do first to address the SPI trend?
A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not
shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.
What is the root cause of this issue?
An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project
execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.
What should the project manager have done to prevent this from happening?
A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.
What should the project manager do to ensure the project is completed on time with quality?
A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for
several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.
What should the project manager do next?
During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value. What should the
project manager do to address this concern?
A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.
Match the following common terms with their explanations that evaluate the buffers or constraints.
A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.
What should the project manager do?
A project manager is leading a project team composed of members with varying levels of knowledge and
experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.
What should the project manager do?