New Year Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

PMI-SP Questions and Answers

Question # 6

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

A.

-$75,000

B.

-$42,000

C.

-$45,000

D.

-$65,000

Full Access
Question # 7

Fill in the blank with an appropriate phrase.

The __________ includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item.

Full Access
Question # 8

You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?

A.

The duration will increase, but the labor will stay the same.

B.

The duration will decrease as new team members are brought onto the project.

C.

Nothing, new resources will be incorporated into the project team.

D.

The duration will increase, but the labor will decrease.

Full Access
Question # 9

Once the project's WBS has been created what process may happen next?

A.

Estimate activity resources

B.

Define activities

C.

Estimate activity durations

D.

Sequence activities

Full Access
Question # 10

You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?

A.

Parametric estimate

B.

Definitive estimate

C.

Analogous estimate

D.

Bottom-up estimate

Full Access
Question # 11

You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?

A.

Project Human Resources Management Plan

B.

Project Staffing Management Plan

C.

Project Communications Management Plan

D.

Project Schedule Management Plan

Full Access
Question # 12

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

A.

Push technique

B.

Many-to-many

C.

One-to-one

D.

Pull technique

Full Access
Question # 13

Fill in the blank with the appropriate word. ____ management sets the boundaries for the project and is the foundation on which the other project elements are built.

Full Access
Question # 14

Which organizational theory explains the factors that promote performance of people in any organization?

A.

Herzberg's theory

B.

Maslow's Hierarchy theory

C.

McGregor's theory

D.

Expectancy theory

Full Access
Question # 15

Mary is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the project activities, she and the project team have agreed to crash the project work. What must be true of these project activities for crashing to be acceptable?

A.

The activities must be of fixed duration.

B.

The activities must be effort-drive.

C.

The activities must not be susceptible to the Law of Diminishing Returns.

D.

The activities must be risk-free.

Full Access
Question # 16

You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, the project sponsor, and ten members of your project team. What type of communication method are you using in this instance?

A.

Interactive communication

B.

Active communication

C.

Pull technique

D.

Push technique

Full Access
Question # 17

Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?

A.

Idea/mind mapping

B.

Delphi technique

C.

Nominal group technique

D.

Affinity diagram

Full Access
Question # 18

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?

A.

Five days

B.

Four days

C.

Eleven days

D.

Zero

Full Access
Question # 19

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

A.

80

B.

1.02

C.

102

D.

0.80

Full Access
Question # 20

Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

A.

-$75,500

B.

-$390,000

C.

-$487,500

D.

-$65,000

Full Access
Question # 21

You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

A.

A significant point in the project

B.

A goal of reaching a significant delivery of project benefits by an identified date

C.

An imposed date for the project to reach a given point

D.

The completion of a project activity that is crucial to project completion

Full Access
Question # 22

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

A.

Archive the project records.

B.

Summarize the project risks costs.

C.

Summarize the project variance.

D.

Close the project office.

Full Access
Question # 23

Which of the following individuals performs various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement?

A.

Seller

B.

Operations manager

C.

Functional manager

D.

Project manager

Full Access
Question # 24

John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the importance of communication in the project. He would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

A.

3000

B.

79

C.

80

D.

3160

Full Access
Question # 25

If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?

A.

You have added lag time to the project activities.

B.

You have added management reserve to the project activities.

C.

You have added lead time to the project activities.

D.

You have added float to the project activities.

Full Access
Question # 26

Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration process. The previous project schedule could best described as which one of the following?

A.

Organizational process asset

B.

Lessons learned documentation

C.

Process input

D.

Predecessor project

Full Access
Question # 27

A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.

A.

Performance control

B.

Execution scheduling

C.

Leadership

D.

Feasibility planning

Full Access
Question # 28

You are the project manager of the NHQ project. Your project has a budget of $1,258456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Based on the current performance value what should you report to management regarding the variance at completion?

A.

-$21,618

B.

-$62,922

C.

Zero - you would not know what this will cost until the project is complete.

D.

-$54,044

Full Access
Question # 29

You are the project manager of the GHQ Project. You are working with your project team to create the project network diagram. You have created the PND and are identifying the critical path with your team using your project management information system. All of the activities on the critical path are showing in red in the software that you are using to evaluate the critical path. What are schedule activities on the critical path called?

A.

Critical activities

B.

Action items

C.

High alert activities

D.

Red rated activities

Full Access
Question # 30

You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

A.

Project Schedule Management Plan

B.

Project Staffing Management Plan

C.

Project Human Resources Management Plan

D.

Project Communications Management Plan

Full Access
Question # 31

Which of the following processes involves the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to forecast the project results?

A.

Identify stakeholders

B.

Performance reporting

C.

Plan communications

D.

Stakeholder analysis

Full Access
Question # 32

Which of the following group activity techniques allows a large number of ideas to be sorted into groups for review and analysis?

A.

Idea/mind mapping

B.

Nominal group technique

C.

Delphi technique

D.

Affinity diagram

Full Access
Question # 33

You are the project manager of the NHQ Project and are trying to determine which seller you should choose for the project. You have received proposals from six vendors and they are all very good proposal, qualified to complete the project work, and the prices are close to the same. You would like to create method of ranking each vendor based and assign a score value to several different categories. Because the project is a high-profile project, you have assigned 25 points to experience and 10 points for all of the other categories to judge the vendors. This is considered what type of source selection process?

A.

Screening system

B.

Preferred vendor list

C.

Benefits-cost analysis

D.

Weighting system

Full Access
Question # 34

Which of the following allows activities to be done in parallel that would normally be done in sequence?

A.

Lag time

B.

Lead time

C.

Fast tracking

D.

Crashing

Full Access
Question # 35

John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has spent $325,000 on the project. But, he has completed only 40 percent of the project work till now. Management wants to know what the project's cost performance index is. What value will John report?

A.

0.76

B.

0.85

C.

0.80

D.

0.92

Full Access
Question # 36

Amy works as a project manager for BlueWell Inc. Her organization wants her to create a new warehouse. Which of the following documents will she create to define the business needs, the project justification, and the current requirements?

A.

Project scope

B.

Feasibility study

C.

Project charter

D.

Work breakdown structure

Full Access
Question # 37

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

A.

Project change control process

B.

Perform integrated change control process

C.

Configuration management

D.

Communications management

Full Access
Question # 38

Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?

A.

Communications management plan

B.

Issues log

C.

Project schedule

D.

Schedule management plan

Full Access
Question # 39

You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should be at the 45 percent milestone today, but due to some early delays you're running late. What is the planned value of your project?

A.

$950,000

B.

$2,375,000

C.

$1,055,543

D.

$938,260

Full Access
Question # 40

There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

A.

Scope baseline

B.

Activity attributes

C.

Activity list

D.

Activity resource requirements

Full Access
Question # 41

You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, the team leader of a project, provides you performance indexes of her project. The cost variance (CV) of her project is -20. What does this figure depict?

A.

Spending is right on target.

B.

Costs are lower than planned.

C.

The project is behind schedule.

D.

Costs are higher than planned.

Full Access
Question # 42

You are creating a status report to show how your project is progressing. Management is interested in several key activities and their status. You need to report work performance information to management. All of the following are example of work performance information you should include in your report except for which one?

A.

How the project is performing on its schedule.

B.

Performance of the selected project vendors

C.

Which activities have been started and which activities have been finished.

D.

Percent of completion for the in-progress activities

Full Access
Question # 43

You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

A.

Ideas to action

B.

Problem definition

C.

Problem solution generation

D.

Solution action planning

Full Access
Question # 44

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?

A.

-$45,789

B.

-$56,790

C.

There is not enough information to know.

D.

-$30,268

Full Access
Question # 45

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

A.

Project communications management plan

B.

Project reporting structure

C.

Project schedule

D.

Project scope management plan

Full Access
Question # 46

Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and distribute information to the stakeholders about the project costs, schedule, and performance. What term is assigned to this communication tool?

A.

Project management information system

B.

Table reporting

C.

Reporting system

D.

Communications management system

Full Access
Question # 47

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

A.

$227,140

B.

0.75

C.

0.95

D.

-$56,789

Full Access
Question # 48

Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of the project team members are scheduled to complete work on other projects. What input will most likely be of the biggest assistance as Wendy and the project team begin creating the duration estimate for this project?

A.

Project charter

B.

Project scope statement

C.

Project communications management plan

D.

Resource calendar

Full Access