A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.
What document should the business analyst use to determine the relationship of the requirement to the business need?
After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides
enough information to check if the requirement has been met.
Which of the following would work best in this case?
A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.
What is the best approach to resolve this issue?
The business managers had clearly stated that the delivered website must simultaneously accommodate millions of users around the globe. However, within the first week of the production launch, the website crashes frequently.
This situation could have been averted if:
To reduce the amount of time and effort needed to create a product specification for a project, the business analyst plans to reuse:
Which function involves auditing both the quality requirements to resolve discrepancies and the results of quality control measurements to ensure that appropriate quality standards and operational definitions are being used?
While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis
favors a custom-developed solution, either built internally or using contract labor.
To prepare the recommendation, what should the business analyst do?
Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s)
versioning?
When determining the value of a business case, which tool or technique should be used?
A business analyst is reviewing a discrepancy report after a test session. The discrepancy report has revealed a defect that the business analyst must address.
Which of the following criteria should the business analyst use to identify the appropriate response to the defective test result?
When faced with a tight timeline, the project sponsor suggests that the project team start development without creating traceability artifacts. What should the business analyst do?
A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.
Which tool or technique could have been used by business analyst to avoid this situation?
The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.
What should the business analyst do?
Which solution should be chosen according to the completed weighted-ranking matrix?
When managing a product backlog, which statement best describes how to determine the value of backlog items?
How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?
Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?
A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.
What would be the most viable technique to use in this scenario?
A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?
A financial company deployed a new online product to their customers to invest in the stock market. The company notices a problem regarding financial calculations and starts the problem analysis. The company discovers that the new rules for taxes and fees were not implemented.
This problem could have been avoided by:
What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?
A project team delivers a solution based on the approved requirements and is confident that it meets the defined acceptance criteria.
What should the business analyst do to obtain signoff?
The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release.
Which is a possible reason why the requirement was not implemented?
The business analyst has been assigned to a project involving a low number of stakeholders. Which technique should be used to elicit requirements?
What should a business analyst do after discovering that two solution requirements conflict?
The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.
What should the business analyst have done to complete this request?
The document that defines the process for managing requirements revisions is the:
When a business analyst uses subject matter experts to define roles and identify influencers, which project artifact is created or updated?
A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.
Which model should the team employ to ensure the most effective representation of analysis boundary?
Which statement accurately depicts what changes can be made to requirements after they are baselined?
Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?
During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?
A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?
In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.
What task should the business analyst perform in order to identify these impacts?
What is a standardized, effective, and efficient way to manage changes to project documentation?
After implementation of the product, the customer reports defects. What is the best course of action to take?
The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?
A new business analyst has taken over on a project that is in the development phase. The project manager is looking for an update on requirements status.
What should the business analyst use to help communicate the status?
A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?
A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?
A business analyst has been asked to investigate a problem. This investigation will provide input towards developing a business case. The business analyst wants to first understand the company's current business processes.
Which technique should the business analyst use?
A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.
How could the business analyst address the end user's concerns about the new interface?
A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?
A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?
A company is developing a new e-commerce platform to enter a new market segment. Development is well under way when the government issues a new set of regulations.
Which course of action should the business analyst take?
A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new
functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create
project plans, schedule meetings, and provide meeting minutes.
In the scenario above, what is the role of the technical staff and testing team from Company A?
A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?
Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system. Which of the following has the business analyst defined?
During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement.
What should the business analyst have defined to avoid this?