New Year Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

PMI-PBA Questions and Answers

Question # 6

A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.

What document should the business analyst use to determine the relationship of the requirement to the business need?

A.

Traceability matrix

B.

Requirements management plan

C.

Requirements package

D.

Reliability matrix

Full Access
Question # 7

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Full Access
Question # 8

A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?

A.

Meet with the customer and apologize for misunderstanding the business's need.

B.

Suggest re-estimating the requirement and following the change control process.

C.

Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.

D.

Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.

Full Access
Question # 9

The business managers had clearly stated that the delivered website must simultaneously accommodate millions of users around the globe. However, within the first week of the production launch, the website crashes frequently.

This situation could have been averted if:

A.

quality attributes were captured and tested.

B.

critical business requirements were accommodated and tested.

C.

nonfunctional requirements were identified and tested.

D.

essential product requirements were captured and tested.

Full Access
Question # 10

To reduce the amount of time and effort needed to create a product specification for a project, the business analyst plans to reuse:

A.

quantitative analysis.

B.

risk assessments.

C.

qualitative analysis.

D.

requirements.

Full Access
Question # 11

What should the business analyst do during the first steps of a project?

A.

Identify stakeholders and their interests.

B.

Identify the classes of users and their requirements.

C.

Align the sponsor expectations along the project goals.

D.

Evaluate the sources for requirements and prioritize them.

Full Access
Question # 12

Which function involves auditing both the quality requirements to resolve discrepancies and the results of quality control measurements to ensure that appropriate quality standards and operational definitions are being used?

A.

Quality control

B.

Quality assessment

C.

Quality management

D.

Quality assurance

Full Access
Question # 13

While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis

favors a custom-developed solution, either built internally or using contract labor.

To prepare the recommendation, what should the business analyst do?

A.

Perform solution evaluation.

B.

Formulate a weighted-ranking matrix.

C.

Review the stakeholder analysis.

D.

Recommend the SVP's choice, as it is most likely to be adopted.

Full Access
Question # 14

Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s)

versioning?

A.

Statement of work

B.

Project plan

C.

Problem or opportunity statement

D.

Traceability matrix

Full Access
Question # 15

When determining the value of a business case, which tool or technique should be used?

A.

Variance analysis

B.

Cost-benefit analysis

C.

SWOT analysis

D.

Feasibility analysis

Full Access
Question # 16

A business analyst is reviewing a discrepancy report after a test session. The discrepancy report has revealed a defect that the business analyst must address.

Which of the following criteria should the business analyst use to identify the appropriate response to the defective test result?

A.

Inspect the requirements traceability matrix to verify if the requirement is connected to a use case.

B.

Determine if the defect is in the solution developed, in the original requirement, or in the test case.

C.

Verify that the corresponding requirement was appropriately signed off by the requesting stakeholder.

D.

Perform an impact analysis and open a change request to include the revised requirement in the next baseline.

Full Access
Question # 17

Which of the following would be the best practice in product validation?

A.

The measurement of the requirement should be based on the average of two or more evaluations.

B.

There should be two separate measurements for evaluating each functional requirement.

C.

Two or more testers should test the product using the same test cases so that their evaluations are consistent.

D.

The evaluation criteria should be the same as what was used to measure the requirement.

Full Access
Question # 18

When faced with a tight timeline, the project sponsor suggests that the project team start development without creating traceability artifacts. What should the business analyst do?

A.

Start development activities without traceability items.

B.

Explain the value of requirements traceability.

C.

Negotiate for a quick approval of a reduced set of traceability artifacts.

D.

Eliminate traceability activities for the project.

Full Access
Question # 19

A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.

Which tool or technique could have been used by business analyst to avoid this situation?

A.

Prototyping

B.

Surveys

C.

Document analysis

D.

Decision tree

Full Access
Question # 20

The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.

What should the business analyst do?

A.

Develop a change control process.

B.

Obtain approval from the project sponsor.

C.

Document changes as they occur.

D.

Hold firm on scope and reject changes.

Full Access
Question # 21

Which solution should be chosen according to the completed weighted-ranking matrix?

A.

Outsource the development.

B.

Purchase off-the-shelf software.

C.

Develop in-house software.

D.

Enhance the existing system.

Full Access
Question # 22

When managing a product backlog, which statement best describes how to determine the value of backlog items?

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Full Access
Question # 23

How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

A.

Create prototype proof-of-concept models.

B.

Conduct requirement walkthrough sessions.

C.

Review performance data with the project sponsor.

D.

Talk to distinct testing groups to check testing status.

Full Access
Question # 24

What is one benefit of documenting the change control process?

A.

Stakeholders are shielded from how changes are assessed.

B.

Stakeholders know how to request changes.

C.

Stakeholders have a schedule of changes to be deployed.

D.

Stakeholders understand the difficulty of managing requirements.

Full Access
Question # 25

Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?

A.

Decision tree

B.

Functional decomposition

C.

Expected monetary value

D.

Weighted criteria

Full Access
Question # 26

A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.

What would be the most viable technique to use in this scenario?

A.

A review of the solution prototype

B.

A brainstorming session

C.

A use-case development session

D.

A review of the previous version

Full Access
Question # 27

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Full Access
Question # 28

A financial company deployed a new online product to their customers to invest in the stock market. The company notices a problem regarding financial calculations and starts the problem analysis. The company discovers that the new rules for taxes and fees were not implemented.

This problem could have been avoided by:

A.

using a table that shows each applicable business rule with the implemented functional requirement.

B.

implementing an automated issue tracking system to facilitate the tracing of defects to the requirements.

C.

involving a business analyst during all phases of system development.

D.

rolling back the operations using a contingency process in order to avoid loss and client dissatisfaction.

Full Access
Question # 29

What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?

A.

Validate the requirements deemed important by the stakeholders.

B.

B. Obtain approval from engineering for partial testing of the requirements.

C.

Negotiate with the client to standardize the requirements.

D.

Assign a verification method to each requirement.

Full Access
Question # 30

Which document best provides the boundaries for product development?

A.

Scope definition

B.

Requirements baseline

C.

Project plan

D.

Scope document

Full Access
Question # 31

A project team delivers a solution based on the approved requirements and is confident that it meets the defined acceptance criteria.

What should the business analyst do to obtain signoff?

A.

Contact the sponsor.

B.

Contact the stakeholder who provided the majority of requirements in the traceability matrix.

C.

No signoff is necessary.

D.

Refer to the RACI matrix to identify who is responsible for signoff.

Full Access
Question # 32

The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release.

Which is a possible reason why the requirement was not implemented?

A.

The requirements management plan was not updated with the change.

B.

The scope management plan was not updated with the change.

C.

The requirements traceability matrix was not updated with the change.

D.

The schedule management plan was not updated with the change.

Full Access
Question # 33

The business analyst has been assigned to a project involving a low number of stakeholders. Which technique should be used to elicit requirements?

A.

Survey

B.

Interview

C.

Document analysis

D.

Interface analysis

Full Access
Question # 34

What should a business analyst do after discovering that two solution requirements conflict?

A.

Consult the sponsor(s) and log the constraint.

B.

Perform an impact analysis and propose a lower-cost alternative.

C.

Update the requirements baseline and upload it to the project repository.

D.

Communicate the conflict to stakeholders and facilitate a resolution.

Full Access
Question # 35

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.

What should the business analyst have done to complete this request?

A.

A Set up a change control board to track the number of rejections.

B.

Limit the number of rejected requirements on the project.

C.

Track rejected requirements in the system requirements verification matrix.

D.

Spend more time up-front reviewing the requirements to limit rejections.

Full Access
Question # 36

The document that defines the process for managing requirements revisions is the:

A.

project management plan.

B.

change management plan.

C.

communications management plan.

D.

scope management plan.

Full Access
Question # 37

Which of the following is a method for requirements change control?

A.

Communication management

B.

Scope analysis

C.

Requirements management

D.

Baselining

Full Access
Question # 38

When a business analyst uses subject matter experts to define roles and identify influencers, which project artifact is created or updated?

A.

Stakeholder register

B.

RACI matrix

C.

SWOT analysis

D.

Stakeholder management plan

Full Access
Question # 39

A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.

Which model should the team employ to ensure the most effective representation of analysis boundary?

A.

Data flow diagram

B.

Context diagram

C.

State diagram

D.

Entity relationship diagram

Full Access
Question # 40

Which statement accurately depicts what changes can be made to requirements after they are baselined?

A.

Requirements can be changed only with sponsor approval.

B.

Requirements can be changed through a defined process.

C.

Requirements cannot be changed once development begins.

D.

Requirements cannot be changed once user acceptance testing begins.

Full Access
Question # 41

Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?

A.

PEST analysis

B.

B. Force-field analysis

C.

Feasibility analysis

D.

Gap analysis

Full Access
Question # 42

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?

A.

Requirements cards

B.

Requirements baseline

C.

Requirements management tool

D.

Requirements traceability matrix

Full Access
Question # 43

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

A.

How requirement changes will impact the requirements baseline

B.

How requirement changes will be implemented

C.

How requirement changes will impact the validation plan

D.

How requirement changes will be communicated

Full Access
Question # 44

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Full Access
Question # 45

What is a standardized, effective, and efficient way to manage changes to project documentation?

A.

A configuration verification and audit system

B.

A requirements traceability matrix

C.

A configuration management system

D.

A change control board

Full Access
Question # 46

After implementation of the product, the customer reports defects. What is the best course of action to take?

A.

Compare reported defects with user acceptance test results.

B.

Escalate the issue to the project manager since the acceptance was given by the customer.

C.

Do nothing since the solution is now the responsibility of the operations manager.

D.

Involve the end users and plan a new round of acceptance tests to check the gaps.

Full Access
Question # 47

The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?

A.

Create a requirements traceability matrix for review and approval by the customer.

B.

Create a requirements baseline approval form for the customer to review and approve.

C.

Request that the customer create a baseline of the requirements in the contract specification.

D.

Perform a variance analysis on the design specification and report the results to the customer.

Full Access
Question # 48

A new business analyst has taken over on a project that is in the development phase. The project manager is looking for an update on requirements status.

What should the business analyst use to help communicate the status?

A.

Project charter

B.

Communication plan

C.

Business analysis plan

D.

Traceability matrix

Full Access
Question # 49

A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?

A.

Distribution of project changes

B.

Requirements status during the project development cycle

C.

Number of requirements approved vs. number of requirements rejected

D.

Number of requirements tested and approved

Full Access
Question # 50

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?

A.

Request that the project manager identify all affected project stakeholders.

B.

Provide all signed-off project documentation to the stakeholders for information purposes only.

C.

Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.

D.

Solicit feedback and add requirements to the project backlog.

Full Access
Question # 51

A business analyst has been asked to investigate a problem. This investigation will provide input towards developing a business case. The business analyst wants to first understand the company's current business processes.

Which technique should the business analyst use?

A.

Observation

B.

RAC! matrix

C.

MoSCoW

D.

User stories

Full Access
Question # 52

A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.

How could the business analyst address the end user's concerns about the new interface?

A.

Consult the stakeholder register to evaluate if the user has authority to influence the project.

B.

Develop a prototype to gather functional requirements.

C.

Develop a use case package to support the user interface.

D.

Document the business data objects using an entity relationship diagram.

Full Access
Question # 53

A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?

A.

1

B.

2

C.

3

D.

4

Full Access
Question # 54

A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?

A.

Work breakdown structure

B.

Requirements management plan

C.

Use cases

D.

Traceability matrix

Full Access
Question # 55

A company is developing a new e-commerce platform to enter a new market segment. Development is well under way when the government issues a new set of regulations.

Which course of action should the business analyst take?

A.

Evaluate if the new set of regulations is aligned with the business case.

B.

Evaluate the impact of the change on the project schedule.

C.

Obtain management sign-off on the new set of regulations.

D.

Check the traceability matrix to identify affected use cases.

Full Access
Question # 56

A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new

functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create

project plans, schedule meetings, and provide meeting minutes.

In the scenario above, what is the role of the technical staff and testing team from Company A?

A.

Accountable

B.

Consult

C.

Responsible

D.

Inform

Full Access
Question # 57

A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.

How can the business analyst determine the impact on existing requirements?

A.

Perform a stakeholder analysis.

B.

Review the requirements traceability matrix.

C.

Use time-boxing to defer the new requirement.

D.

Update the use case documentation.

Full Access
Question # 58

What can a business analyst use to track requirements documentation?

A.

Affinity diagram

B.

Data dictionary

C.

Business rules matrix

D.

Version control system

Full Access
Question # 59

Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system. Which of the following has the business analyst defined?

A.

Solution design

B.

Business requirements

C.

Solution scope

D.

Business case

Full Access
Question # 60

During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement.

What should the business analyst have defined to avoid this?

A.

Communications approach in the business analysis plan

B.

Decision-making process in the project management plan

C.

Decision-making process in the business analysis plan

D.

Communications approach in the project management plan

Full Access