Black Friday Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

PMI-PBA Questions and Answers

Question # 6

The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?

A.

Create a requirements traceability matrix for review and approval by the customer.

B.

Create a requirements baseline approval form for the customer to review and approve.

C.

Request that the customer create a baseline of the requirements in the contract specification.

D.

Perform a variance analysis on the design specification and report the results to the customer.

Full Access
Question # 7

A company has developed a new product for a customer. The customer provided a specification, but the company did not produce the system requirements in the verification matrix.

The customer is having difficulty determining if the product is meeting the requirements during the test event because the:

A.

customer did not adequately review the test procedure before the test.

B.

test engineer is not communicating effectively with the customer.

C.

requirements in the technical specification are unclear and ambiguous.

D.

customer cannot make this determination until the entire test is complete.

Full Access
Question # 8

What should be done to ensure that the product design meets the stated requirements?

A.

Conduct multiple internal design reviews.

B.

Use a traceability matrix.

C.

Review lessons learned results.

D.

Engage an experienced development team.

Full Access
Question # 9

The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?

A.

Which stakeholders have the most influence?

B.

Which functional areas are impacted?

C.

How is the organizational chart structured?

D.

What is the business need?

Full Access
Question # 10

A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?

A.

Meet with the stakeholder and discuss timeline impact.

B.

Refer changes to the project manager.

C.

Define requirements baseline and implement a change control process.

D.

Implement only the original requirements.

Full Access
Question # 11

A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.

What document should the business analyst use to determine the relationship of the requirement to the business need?

A.

Traceability matrix

B.

Requirements management plan

C.

Requirements package

D.

Reliability matrix

Full Access
Question # 12

One of the main purposes for creating a requirements traceability matrix is to:

A.

track how requirements can be connected to the solution.

B.

provide test cases to validate solution deliverables.

C.

document stakeholder approval of project requirements.

D.

track the project solution scope.

Full Access
Question # 13

An organization is evaluating the possibility of conducting business internationally. Which factors should be investigated at the onset of the initiative?

A.

Deliverables to be produced

B.

Impacts on requirements baseline

C.

External dependencies

D.

Change control processes

Full Access
Question # 14

Company A has initiated a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder, is excluded from the list of stakeholders.

In which reference material can the business analyst find information about the missing project stakeholders?

A.

Organizational chart

B.

Business case

C.

Business analysis plan

D.

Business analyst communication plan

Full Access
Question # 15

A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:

A.

requirements gathering workshops with the stakeholders.

B.

requirements acceptance with the customer.

C.

requirements validation with the testers.

D.

requirements sign-off with the customer.

Full Access
Question # 16

What can a business analyst use to track requirements documentation?

A.

Affinity diagram

B.

Data dictionary

C.

Business rules matrix

D.

Version control system

Full Access
Question # 17

A business analyst is conducting a cost-benefit analysis of potential solution options. The stakeholders have indicated that the estimated growth rate is very important to them.

Which technique will allow the business analyst to determine this information?

A.

Payback period

B.

Net present value (NPV)

C.

Internal rate of return

D.

Return on investment (ROI)

Full Access
Question # 18

When eliciting requirements, a good time to consider using the interviewing method is when:

A.

attempting to obtain sign-off on requirements from stakeholders.

B.

there is not enough time to gather requirements from many different sources.

C.

there are communication challenges among stakeholders.

D.

assembling a requirements traceability matrix.

Full Access
Question # 19

A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.

What would be the most viable technique to use in this scenario?

A.

A review of the solution prototype

B.

A brainstorming session

C.

A use-case development session

D.

A review of the previous version

Full Access
Question # 20

The requirements traceability matrix should primarily be used to:

A.

identify the risks associated with dependent requirements.

B.

define a convention to map the requirements to their sources.

C.

ensure that all requirements have been met.

D.

address the responsibility owner for each requirement.

Full Access
Question # 21

An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.

What analysis should the business analyst conduct to facilitate a successful migration?

A.

Document

B.

User interface

C.

Interface

D.

Systems

Full Access
Question # 22

In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be

reported.

What should the business analyst use?

A.

Configuration management system

B Work breakdown structure

B.

Traceability matrix

C.

Context models

Full Access
Question # 23

A national company with offices in every state in the country has deployed a solution to allow employees to view their health benefits online. The business analyst on the project team is validating solution results to assess whether or not the solution has achieved the desired business result.

Which is the best technique to gather information from employees regarding their satisfaction with the solution?

A.

Survey

B.

Focus groups

C.

Interface analysis

D.

Organization modeling

Full Access
Question # 24

A business analyst is developing a traceability matrix to determine whether or not any gaps exist and to identify any discrepancies.

Which critical field is needed to ensure that the traceability matrix is usable?

A.

Status

B.

Hierarchy

C.

Owner

D.

Requirements description

Full Access
Question # 25

For a large, highly complex project with significant risk, which elicitation technique should be used to analyze input to and output from the product?

A.

System analysis

B.

Dependency analysis

C.

Risk analysis

D.

Interface analysis

Full Access
Question # 26

A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.

Which of the following is the best strategy to define the appropriate acceptance criteria?

A.

Quantify the risks associated with the measurement errors and update the risk register.

B.

Ask the operations manager to formally accept the requirements documents.

C.

Plan a training session for the new system before it is handed over to the operations manager.

D.

Clearly define the maximum acceptable error rate for the new system.

Full Access
Question # 27

During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?

A.

Ask the developer to correct the logo as stated in the requirement.

B.

Confront the stakeholder that requested the change.

C.

Follow the change control process as defined in the business analysis plan.

D.

Discuss the change in the next stakeholder meeting.

Full Access
Question # 28

Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:

A.

prepare a test procedure for the product to discuss at the requirements review.

B.

start designing the product to impress the customer with the amount of progress achieved early in the project.

C.

evaluate the requirements and highlight those that cannot be met or need to be deferred.

D.

request a contract amendment to delete any requirements from the contract that will be difficult to meet.

Full Access
Question # 29

A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems. Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

A.

Data modeling

B.

B. Interface modeling

C.

Rules modeling

D.

Enterprise modeling

Full Access
Question # 30

Which of the following can be used to determine if requirements align to the product's objectives?

A.

Five Whys

B.

Activity network diagrams

C.

Context diagrams

D.

Business use cases

Full Access
Question # 31

After implementation of the product, the customer reports defects. What is the best course of action to take?

A.

Compare reported defects with user acceptance test results.

B.

Escalate the issue to the project manager since the acceptance was given by the customer.

C.

Do nothing since the solution is now the responsibility of the operations manager.

D.

Involve the end users and plan a new round of acceptance tests to check the gaps.

Full Access
Question # 32

A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.

Which of the following types of surveys would be most appropriate to create and why?

A.

A closed-ended survey to pose several multiple-choice questions and ask the users if the current business process Is correct

B.

A closed-ended survey using the Likert scale to rank specific areas of the current business process

C.

An open-ended survey to allow users the opportunity to explain their opinions on the current business process

D.

An open-ended survey to collect different opinions on the current business process

Full Access
Question # 33

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.

What could have caused this?

A.

The product was not adequately tested in accordance with the test plan.

B.

The requirements matrix did not adequately track back to client requirements.

C.

Requirement changes were not properly identified in the project charter.

D.

The product design was not properly reviewed by the quality department.

Full Access
Question # 34

The business managers had clearly stated that the delivered website must simultaneously accommodate millions of users around the globe. However, within the first week of the production launch, the website crashes frequently.

This situation could have been averted if:

A.

quality attributes were captured and tested.

B.

critical business requirements were accommodated and tested.

C.

nonfunctional requirements were identified and tested.

D.

essential product requirements were captured and tested.

Full Access
Question # 35

Which of the following is an example of a functional requirement?

A.

The system is able to require passwords.

B.

The system can be accessed from multiple locations.

C.

The system provides an user-friendly interface.

D.

The system can handle 3,000 user requests concurrently.

Full Access
Question # 36

A financial company deployed a new online product to their customers to invest in the stock market. The company notices a problem regarding financial calculations and starts the problem analysis. The company discovers that the new rules for taxes and fees were not implemented.

This problem could have been avoided by:

A.

using a table that shows each applicable business rule with the implemented functional requirement.

B.

implementing an automated issue tracking system to facilitate the tracing of defects to the requirements.

C.

involving a business analyst during all phases of system development.

D.

rolling back the operations using a contingency process in order to avoid loss and client dissatisfaction.

Full Access
Question # 37

Which of the following actions will contribute most to the success of the initial stage of the project?

A.

Interview stakeholders to clearly define the problem.

B.

Document the requirements and obtain sign-off.

C.

Establish the change control process of the project.

D.

Define the acceptance criteria required during the acceptance phase.

Full Access
Question # 38

A business analyst has elicited, documented, and verified the requirements, discovering that there are not enough resources to deliver all the requirements. Which technique should the business analyst employ to rectify the issue?

A.

Hold a brainstorming workshop to build the rationale for the requirements.

B.

Perform traceability to find out where the requirements originated.

C.

Survey stakeholders on their likes and dislikes about the requirements.

D.

Ask stakeholders to vote on the requirements.

Full Access
Question # 39

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Full Access
Question # 40

Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.

What could the business analyst have established to help manage this situation?

A.

Change control process

B.

Configuration management system

C.

Communication plan

D.

Sponsor signoff

Full Access
Question # 41

Which of the following is a properly written requirement statement?

A.

The pot shall be lightweight and heat up quickly.

B.

The pot shall be usable in the oven or on the stove.

C.

The pot shall be manufactured in the following colors: yellow, red, brown, blue.

D.

The pot shall prominently display the company brand.

Full Access
Question # 42

The business analyst has been assigned to a project which delivers functionality for a much larger solution. The project has many requirements but has not received adequate funding. In addition, the stakeholders’ views conflict.

Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?

A.

Weighted matrix, process flow, and organizational chart

B.

Stakeholder register, decision tree, and capability matrix

C.

Traceability matrix, context diagrams, and scope document

D.

Decision trees, weighted matrix, and context diagrams

Full Access
Question # 43

To reduce the amount of time and effort needed to create a product specification for a project, the business analyst plans to reuse:

A.

quantitative analysis.

B.

risk assessments.

C.

qualitative analysis.

D.

requirements.

Full Access
Question # 44

A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?

A.

Storyboard

B.

Project charter

C.

Business case

D.

Survey

Full Access
Question # 45

What is a standardized, effective, and efficient way to manage changes to project documentation?

A.

A configuration verification and audit system

B.

A requirements traceability matrix

C.

A configuration management system

D.

A change control board

Full Access
Question # 46

A business analyst is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.

Which technique should the business analyst use to investigate the problem?

A.

Interviews

B.

Root cause analysis

C.

Observation

D.

Process modeling

Full Access
Question # 47

The business analyst has been assigned to a project involving a low number of stakeholders. Which technique should be used to elicit requirements?

A.

Survey

B.

Interview

C.

Document analysis

D.

Interface analysis

Full Access
Question # 48

A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may

face monetary penalties.

What should the business analyst do next?

A.

Obtain approval from the project manager.

B.

Define the project scope.

C.

Follow the change control process.

D.

Update the requirements.

Full Access
Question # 49

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Full Access
Question # 50

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Full Access
Question # 51

Which solution should be chosen according to the completed weighted-ranking matrix?

A.

Outsource the development.

B.

Purchase off-the-shelf software.

C.

Develop in-house software.

D.

Enhance the existing system.

Full Access
Question # 52

A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.

How can the business analyst determine how well the solution meets the business case?

A.

Conduct a user survey.

B.

Ask the sponsor for feedback.

C.

Survey the project.

D.

Compare the results of day-in-the-life (DITL) testing and integration testing.

Full Access
Question # 53

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Full Access
Question # 54

The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

A.

Test readiness review

B.

Production readiness review

C.

System requirements review

D.

Critical design review

Full Access
Question # 55

The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:

A.

vote on the product's highest-value business needs.

B.

negotiate to best meet each department's objectives.

C.

collaborate on a product scope that aligns with the company’s objectives.

D.

delegate the decision to be made by the product sponsor.

Full Access
Question # 56

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?

A.

Requirements cards

B.

Requirements baseline

C.

Requirements management tool

D.

Requirements traceability matrix

Full Access
Question # 57

A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?

A.

Meet with the customer and apologize for misunderstanding the business's need.

B.

Suggest re-estimating the requirement and following the change control process.

C.

Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.

D.

Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.

Full Access
Question # 58

A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst

will add an estimate of the time needed to complete the work.

Which type of estimation technique is the business analyst using?

A.

Delphi

B.

Bottom-up

C.

Analogous

D.

Parametric

Full Access
Question # 59

When faced with a tight timeline, the project sponsor suggests that the project team start development without creating traceability artifacts. What should the business analyst do?

A.

Start development activities without traceability items.

B.

Explain the value of requirements traceability.

C.

Negotiate for a quick approval of a reduced set of traceability artifacts.

D.

Eliminate traceability activities for the project.

Full Access
Question # 60

A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.

Which tool or technique could have been used by business analyst to avoid this situation?

A.

Prototyping

B.

Surveys

C.

Document analysis

D.

Decision tree

Full Access