A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
Which tool or technique is used to manage change requests and the resulting decisions?
Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
The scope of a project cannot be defined without some basic understanding of how to create the specified:
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
Which can be used to determine whether a process is stable or has predictable performance?
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:
Which of the following correctly explains the term "progressive elaboration'?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
In which process is a project manager identified and given the authority to apply resources to project activities?
Which of the following tools and techniques is used in the Verify Scope process?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
What is the number of stakeholders, if the project has 28 potential communication channels?
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
For a stakeholder with low interest and high power, the project manager should:
Stakeholder communication requirements should be included as a component of:
The milestone list is an input to which process from the Planning Process Group?
Which items are an output of the Perform Integrated Change Control process?
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
The following is a network diagram for a project.
What is the critical path for the project?
One of the key benefits of the Plan Human Resource Management process is that it:
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
The purpose of the Project Communications Management Knowledge Area is to:
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Which of the following is an output of the Distribute Information process?
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Which of the following includes how requirements activities will be planned, tracked, and reported?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Which of the following response strategies are appropriate for negative risks or threats?
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
A large portion of a projects budget is typically expended on the processes in which Process Group?
Which tool or technique is used to develop the human resource management plan?
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:
The formal and informal interaction with others in an organization industry, or professional environment is known as:
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
The process to ensure that appropriate quality standards and operational definitions are used is:
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project: