1z0-1057-24 Questions and Answers

Question # 6

As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.

Whichthreeare parameters that are based on which the system identifies the new resources?

A.

Department

B.

Project Unit

C.

Jobs

D.

Business Unit

E.

Organization

Full Access
Question # 7

Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

A.

Effort

B.

Cost

C.

Manual Entry

D.

Remaining Plan

Full Access
Question # 8

Your client has decided to import time cards into Project Costing from Oracle Fusion Time and Labor. They have a requirement to make adjustments to time card entries whenever needed.

In which work area will the employees and contingent workers be able to modify their time cards?

A.

Both Time and Cost

B.

Cost

C.

Asset

D.

Time

Full Access
Question # 9

A project administrator is trying to assign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)

A.

The employee is not assigned to the project-owning organization.

B.

The employee is not assigned with a supervisor.

C.

Project roles are not assigned in the project.

D.

The employee is not assigned to a department.

Full Access
Question # 10

Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)

A.

Calendar Types

B.

Project Accounting Periods

C.

Accounting Periods

D.

PA Calendar

E.

PA-GL Periods

Full Access
Question # 11

You havedefined two expenditure types, but they are not available for selection when you enter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)

A.

The two expenditure types are not assigned to the reference data set that is assigned to theproject unitin which the transaction is performed.

B.

The two expenditure types are not assigned to the reference data set that is assigned to the project-owning organization in which the transaction is performed.

C.

The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.

D.

The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.

Full Access
Question # 12

You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).

Then Bill Plan A is allocated against Project X – Task 10, and Bill Plan B is allocated against Project Y – Task 30.

Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)

A.

Both the contract lines create only a single invoice because they are using the same contract.

B.

Two invoices are created using the same contract.

C.

Bill set number drives the grouping of transactions.

D.

Invoice generation does not depend on bill plan. The invoices are created based on the contract line.

Full Access
Question # 13

You are trying to create a custom infolet but are not able to find the "Create Infolet" option in the Infolet repository window. Whichtwosteps should be completed before you can access the "Create Infolet" option?

A.

You must activatePage Composer.

B.

You should be on the Project Custom Objects page.

C.

You must be in anactive sandbox.

D.

You should enable the "Create Infolet" option from the Personalize Springboard page.

Full Access
Question # 14

You are now the project manager of a newly created implementation project. Which two items arenotpart of managing an implementation project?

A.

Assign tasks to various users who are responsible for managing setup data.

B.

Monitor the progress of completing setup tasks.

C.

Select the offering you want to implement.

D.

Generate a list of setup tasks.

E.

Enable optional functional areas and features by opting in.

Full Access
Question # 15

You search for resources to fulfill a project resource request but are unable to proceed after receiving the following error message: “The search for resources cannot be completed because the project resource search index is not available. Contact your help desk.”

Identify the cause for this error message. (Choose the best answer.)

A.

The index is not in the process.

B.

The index has been built.

C.

The index is in the process of being updated.

D.

The most recent update of the index finished successfully.

Full Access
Question # 16

You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)

A.

Exceptions

B.

Accounting Calendar

C.

Workday Patterns

D.

Time Off

E.

Expenditure Type

Full Access
Question # 17

Identify theattribute of a project typethatdetermines if expenditure items are billable, and theamount type to be used as the basisfor transfer pricing. (Choose the best answer.)

A.

work type

B.

event type

C.

cost type

D.

expenditure type

Full Access
Question # 18

Stigma consulting has been hired by a client to implement Project Management Cloud. Which role should they assign to a user for using the rapid implementation feature to set up the Project Financial Management offering by populating and uploading a Microsoft Excel workbook?

A.

Project Executive

B.

Project Integration Specialist

C.

Project Administrator

D.

Project Application Administrator

Full Access
Question # 19

Your customer has a requirement to import and process third-party transactions that are “costed” and “accounted”.

Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)

A.

Import Options

B.

Document Options

C.

Transaction Source Options

D.

Document Entry Options

Full Access
Question # 20

Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this.(Choose the best answer.)

A.

Cascade change to the start date.

B.

Do not cascade date changes.

C.

Cascade change to the finish date.

D.

Cascade change to the start date and the finish date.

Full Access
Question # 21

What are three configuration items that you need to set up by using the Project Organizations functional area in Project Financial Management configurations? (Choose three.)

A.

Manage Project Unit Organizations

B.

Mange Business Unit

C.

Manage Project Organization Classifications

D.

Mange Project Types

E.

Manage Project Unit Options

Full Access
Question # 22

Which component of performance measures allows you to select the method that is used to measure accounts such as budget, forecast, and actual?

A.

Accounts Member

B.

Time Member

C.

Category Member

D.

Scenario Member

Full Access
Question # 23

Which two statements describe how the Resource Qualification Score is calculated?

A.

An individual's score is 100% if the resource request has a qualification with a specified proficiency and the resource does not have the qualification.

B.

An individual's score is 100% if the resource request has a qualification, but no proficiency is specified, and the resource has the qualification.

C.

An individual's score is 100% if the resource request has a qualification with a specified proficiency and the resource has the qualification that meets the specified proficiency.

D.

An individual's score is 100% if the resource request has a qualification with a specified proficiency and the resource has the qualification with a proficiency that is lower or higher than specified.

Full Access
Question # 24

Where should you specify the Default Capitalized Interest Rate Schedule?

A.

Manage Capitalized Interest Rates page

B.

Manage Expenditure Type page

C.

Manage Capitalized Interest Rate Schedules page

D.

Manage Project Type page

E.

Manage Project Plan Type page

Full Access
Question # 25

You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want todefine deliverables for your project requirementsthat are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)

A.

A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.

B.

The association of a deliverable with a task is dependent on associating a requirement with a task.

C.

A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.

D.

You associate a deliverable with a task, independent of associating a requirement with a task.

Full Access
Question # 26

You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)

A.

1000

B.

900

C.

800

D.

600

Full Access
Question # 27

You have defined two expenditure types but they are not available for selection when you enter an expenditure batch.

What is the reason for this problem?

A.

The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.

B.

The two expenditure types are not assigned to the reference data set that is assigned to the project unit in which the transaction is performed.

C.

The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.

D.

The two expenditure types are not assigned to the reference data set that is assigned to the project-owning organization in which the transaction is performed.

Full Access
Question # 28

Which two statements are true about the cross-charge method, Borrowed and Lent?

A.

This method creates accounting entries that move an amount equal to the transfer price between the provider and receiver organizations within a legal entity.

B.

Costs or revenue are shared based on transfer price rules with this method.

C.

You must set up the contract business unit to use this method.

D.

This method creates a formal internal invoice.

Full Access
Question # 29

Which three tasks can be performed using the project requirements work area? (Choose three.)

A.

creating projects and tasks in the context of backlog items.

B.

creating issues for the backlog items.

C.

adding scrum master to backlog items.

D.

tracking backlog item status from the requirement storyboard.

E.

creating change orders for the backlog items.

Full Access
Question # 30

In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)

A.

common costs on the project/task

B.

expenditure type exclusions on the Capitalized Interest rate name

C.

expenditure type exclusions on the Capitalized Interest rate schedules

D.

expenditure items whose cost spreads across multiple assets that are capitalized

E.

expenditure items whose costs are applied to a single asset or multiple assets

Full Access
Question # 31

Your customer wants to perform billing based on the Percent Spent invoice method. Identify two setups that are required in project contracts for calculating invoice amounts as per their requirement. (Choose two.)

A.

billing events

B.

bill plan

C.

expenditure items

D.

billing controls

E.

invoice method

Full Access
Question # 32

Whichthreefile-based data imports are available for use in Oracle Project Portfolio Management Cloud?

A.

Project Tasks

B.

Project Budgets

C.

Project Billing Events

D.

Project Templates

E.

Capital Rate Schedule

Full Access
Question # 33

Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)

A.

Enable track missing time atproject unit.

B.

Enable track missing time at project type.

C.

Enable track missing time at project template.

D.

Enable track missing time at business unit.

Full Access
Question # 34

Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified thattheir cost spread distribution factor on a 10 spread point scale resembles:

0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two)

A.

Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to a project template.

B.

Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to the resource class.

C.

Use the predefined Bell Curve spread with small deviations on the spread points.

D.

Use the predefined S-Curve spread with small deviations on the spread points.

Full Access
Question # 35

When scheduling the Update Project Performance Data process to run on a periodic basis, which summarization method would you select? (Choose the best answer.)

A.

Bulk

B.

Detail

C.

Incremental

D.

Summary

Full Access
Question # 36

When implementing Project Performance Reporting, your customer has the following requirements:

    Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.

    As long as a project cost is less than the threshold, the project should be shown as on-track.

Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)

A.

multiple threshold levels

B.

single threshold level value

C.

single threshold level range

D.

multiple threshold level value

Full Access
Question # 37

Your customer accounts revenue based on, product class category. Because all your customer's projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category “Funding Source” and assign it to all projects. However, you notice that the accounting is still happening based on product class category. Identify the reason for this problem. (Choose the best answer.)

A.

Funding source class category is assigned to all project types.

B.

Funding source class category is not enabled for “available as accounting source”.

C.

Product class category is not enabled for “available as accounting source”.

D.

Funding source class category is enabled for “available as accounting source”.