Which of the following are primary activities in conducting product risk analysis? [1]
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the
project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely,
particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as
"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.
Given this information, which lifecycle model should you recommend?[3]
The Test Manager must assemble team members that have which of the following characteristics? [1]
Mary is an external IT auditor. She is conducting a review of the system-level testing done by Greg's functional testing team.
Which of the following items from Mary's assessment summary should concern Greg the most? [2]
The test team is using a distributed model for testing.
What is the primary factor you should consider with this model? [1]
Your organization is considering using open-source tools. You have been told you need to be aware of the terms of the GNU general public license.
What is the basic concept of this license? [1]
While mining the defect database for patterns of problems in the last release, a Test Manager notices that many of the most damaging failures were caused by defects
injected during the low-level design phase.
Which of the following actions will likely give this project the most effective solution to this problem? [3]
You have been promoted to Test Manager within your company. Your new manager states that your test team utilized a risk-based test approach for the last release but in production, a number of
serious failures in lightly tested areas have occurred.
What would be your first action prior to the start of the next test phase for the next release? [3]
You have been carefully monitoring the progress of testing for your project. You have been using the established traceability to verify that the requirements and test
conditions are being adequately addressed. The test team is proceeding well in their test case execution and you can see that you are achieving about 80% coverage of
the test conditions per the traceability mapping in your test management system. You have seen a number of defects being logged against test conditions that are failing,
but you do not see a mapping of the test cases to those conditions.
What is likely to be occurring in the testing area that is causing the traceability to break down? [2]
Most managers in your company consider the efforts of your test team valuable, while others see comprehensive testing as an unnecessary cost overhead to the SDLC.
What action could the Test Manager take to quantify the value of testing to the organization? [3]
Which of the following metrics would be most beneficial to collect to determine the effectiveness of a review process? [2]
You are reviewing the project's traceability matrix after the first cycle of testing. You have discovered that new requirements have been introduced and others have
changed.
What should you do? [2]
Which of the following aspects should test progress metrics be mapped to? [1]