New Year Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

CTAL-TM Questions and Answers

Question # 6

Which of the following are primary activities in conducting product risk analysis? [1]

A.

Risk testing, risk management

B.

Risk identification, risk assessment

C.

Risk identification, risk testing

D.

Risk management, risk assessment

Full Access
Question # 7

You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the

project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.

At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely,

particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as

"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.

Given this information, which lifecycle model should you recommend?[3]

A.

Spiral

B.

Iterative/incremental

C.

V-model

D.

Waterfall

Full Access
Question # 8

The Test Manager must assemble team members that have which of the following characteristics? [1]

A.

Thrive in a routine, structured environment

B.

Will not change the severity of a defect report

C.

Will spark informal cross training among themselves

D.

Possess identical skill sets

Full Access
Question # 9

Mary is an external IT auditor. She is conducting a review of the system-level testing done by Greg's functional testing team.

Which of the following items from Mary's assessment summary should concern Greg the most? [2]

A.

All the Business requirements could be traced to Test Objectives. However there was no tracing from the Business Requirements to the project's test

schedule.

B.

Some of the Test Objectives could only be mapped back to a single Business Requirement.

C.

A few of the Test Objectives did not have any Test Conditions assigned to them.

D.

There were Test Conditions which didn't tie back to any Business Requirement.

Full Access
Question # 10

The test team is using a distributed model for testing.

What is the primary factor you should consider with this model? [1]

A.

Alignment of methodologies

B.

Co-location of test team

C.

Provision of growth opportunities for the individual testers

D.

Planned vs. actual hours

Full Access
Question # 11

Your organization is considering using open-source tools. You have been told you need to be aware of the terms of the GNU general public license.

What is the basic concept of this license? [1]

A.

Anyone can use the software anytime for any reason.

B.

A small license fee must be paid to the supplier of the software.

C.

If you're going to distribute the software, you need to do so with the same terms as were applied when you received the

software.

D.

You are allowed to use the software internally, but it cannot be incorporated into any product for which you will receive a profit.

Full Access
Question # 12

While mining the defect database for patterns of problems in the last release, a Test Manager notices that many of the most damaging failures were caused by defects

injected during the low-level design phase.

Which of the following actions will likely give this project the most effective solution to this problem? [3]

A.

Increased static analysis during the implementation phase

B.

Mandatory reviews of all important design work products

C.

Formal inspections of the code modules affected by the last release

D.

Increased white-box coverage during system testing

Full Access
Question # 13

You have been promoted to Test Manager within your company. Your new manager states that your test team utilized a risk-based test approach for the last release but in production, a number of

serious failures in lightly tested areas have occurred.

What would be your first action prior to the start of the next test phase for the next release? [3]

A.

Ensure you have the correct stakeholders' participation during the risk assessment process

B.

Review the test cases executed from the previous release.

C.

Request functional requirements be prioritized in order of importance to the stakeholder.

D.

Review the production defects and determine if they are valid.

Full Access
Question # 14

What is a "depth-first" risk-based testing technique? [1]

A.

Highest risk test cases are executed first

B.

All risk items are tested at least once

C.

Lowest risk test cases are executed first

D.

Non-functional test cases are executed first

Full Access
Question # 15

You have been carefully monitoring the progress of testing for your project. You have been using the established traceability to verify that the requirements and test

conditions are being adequately addressed. The test team is proceeding well in their test case execution and you can see that you are achieving about 80% coverage of

the test conditions per the traceability mapping in your test management system. You have seen a number of defects being logged against test conditions that are failing,

but you do not see a mapping of the test cases to those conditions.

What is likely to be occurring in the testing area that is causing the traceability to break down? [2]

A.

The test cases are mapped to the test strategy and are bypassing the test conditions.

B.

The testers are running exploratory tests that are not mapped to the test conditions.

C.

The testers are executing the wrong tests.

D.

The testers are not updating the test execution information in the test management system.

Full Access
Question # 16

Most managers in your company consider the efforts of your test team valuable, while others see comprehensive testing as an unnecessary cost overhead to the SDLC.

What action could the Test Manager take to quantify the value of testing to the organization? [3]

A.

Develop metrics that illustrate planned and actual testing hours.

B.

Review the Test Plan with the management team.

C.

Determine the cost of external failures.

D.

Demonstrate the role QA has in similar size organizations.

Full Access
Question # 17

Which of the following metrics would be most beneficial to collect to determine the effectiveness of a review process? [2]

A.

The number of defects found in production for each module that was reviewed

B.

The development language used to create each module that was reviewed

C.

The elapsed time between each module's review and its corresponding deployment into production

D.

The business criticality of each module that was reviewed

Full Access
Question # 18

You are reviewing the project's traceability matrix after the first cycle of testing. You have discovered that new requirements have been introduced and others have

changed.

What should you do? [2]

A.

Assign the new requirements to a maintenance release, update the test documentation for the changed requirements.

B.

Ask for more time and budget for testing.

C.

Update the "lessons learned" document to avoid future issues similar to this.

D.

Re-assess the test coverage.

Full Access
Question # 19

Which of the following aspects should test progress metrics be mapped to? [1]

A.

Lines of code

B.

Exit criteria

C.

Post-implementation defect discovery rate

D.

Defect resolution rate

Full Access