Black Friday Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

ECBA Questions and Answers

Question # 6

Which type of requirements are temporary in nature?

A.

Business requirements

B.

Solution requirements

C.

Stakeholder requirements

D.

Transition requirements

Full Access
Question # 7

What of the following represents a typical factor that influences the prioritization of requirements?

A.

Scope

B.

Impact

C.

Value

D.

Cost

Full Access
Question # 8

When do the participants start generating ideas during a collaborative game?

A.

Closing step

B.

Exploration step

C.

Opening step

D.

Iteration step

Full Access
Question # 9

What is the input status of requirements used by business analysts (BAs) for undertaking requirement verification activities?

A.

Stated and Unconfirmed

B.

Maintained and Reusable

C.

Specified and Modeled

D.

Validated and Prioritized

Full Access
Question # 10

Which core concept defines a specific way of satisfying one or more needs in a context?

A.

Value

B.

Change

C.

Solution

D.

Priority

Full Access
Question # 11

What are matrices in modelling formats used to describe?

A.

Detailed procedure flow

B.

Gaps in capability analysis

C.

Complex but uniform structures

D.

Hierarchical structure of stakeholders

Full Access
Question # 12

What is the main purpose of the “Approve Requirements” task?

A.

Obtain agreement

B.

Establish requirements baseline

C.

Select appropriate techniques

D.

Assess alternative approaches

Full Access
Question # 13

What characterizes a good collaboration with stakeholders?

A.

Direct and frequent communication with the most influential stakeholders

B.

Regular, frequent and bi-directional communication with all stakeholders

C.

Occasional communication with stakeholders when obstacles occur

D.

Regular exchange of information, ideas, innovations with only supportive stakeholders

Full Access
Question # 14

Elicitation results need to be confirmed to ensure:

A.

stakeholders are encouraged to work towards a common goal.

B.

information relevant to change is explored, drawn out and identified.

C.

scope of elicitation activity is understood and the right technique is selected.

D.

information gathered is accurate and consistent with other information.

Full Access
Question # 15

Which of the following items is commonly used by a business analyst (BA) during requirements verification?

A.

A checklist with a standard set of quality elements

B.

A business model canvas with financial estimates

C.

A benchmarking report with industry comparisons

D.

A user story with inputs and outputs

Full Access
Question # 16

For which part of an initiative is the business analyst (BA) responsible?

A.

Authorizing the project

B.

Approving solution execution plans

C.

Defining the solution approach

D.

Accepting risk mitigation plans

Full Access
Question # 17

Which of the following accurately describes a stakeholder’s role during future state analysis?

A.

A regulator would ensure an envisioned future state can be sufficiently tested and can help set an appropriate level of quality to target.

B.

An end user would help determine which business needs to address and sets the business objective that a future state will achieve.

C.

A project manager would be directly involved in supporting the operations of the enterprise.

D.

A domain subject matter expert would provide insight into current state and potential states.

Full Access
Question # 18

When planning elicitation activities, which technique could be used to determine the possible participants and their roles?

A.

Stakeholder list, map, or personas

B.

Data mining

C.

Roles and permissions matrix

D.

Risk analysis and management

Full Access
Question # 19

Which of the following characteristics verifies that a requirement has been fulfilled?

A.

Atomic

B.

Concise

C.

Feasible

D.

Testable

Full Access
Question # 20

The requirements elicitation technique used to iteratively validate the needs of stakeholders that interact with the application is:

A.

interface analysis

B.

observation.

C.

prototyping

D.

reverse engineering.

Full Access
Question # 21

When stakeholder collaboration is not properly managed, poor relationships can have the following damaging effect on business analysis:

A.

strong negative reactions to obstacles.

B.

lack of support for organizational goals.

C.

resistance to approving elicitation results.

D.

failure to meet project deadlines.

Full Access
Question # 22

What are the participant roles in reviews?

A.

Domain SME, regulator, sponsor, project manager

B.

Customer, supplier, end user, business analyst

C.

Author, reviewer, facilitator, scribe

D.

Approver, administrator, reviewer, tester

Full Access
Question # 23

When validating requirements, assumptions are:

A.

documented after conducting further analysis.

B.

based and assessed on previous experience.

C.

vital to support strategic decisions and goals.

D.

defined so that associated risk can be managed.

Full Access
Question # 24

Requirements allocation is an element of which task?

A.

Specify and model requirements

B.

Verify requirements

C.

Define requirements architecture

D.

Define design options

Full Access
Question # 25

Which approach aligns to approval of requirements at the end of a phase?

A.

Adaptive

B.

Modelling

C.

Predictive

D.

Prioritization

Full Access
Question # 26

In addition to schedule, which other factor must be considered when evaluating changes to requirements?

A.

Number of customers and end-users affected

B.

Capacity of the requirements management tool

C.

Amount of time needed to create new documents

D.

Agreement by executive board members

Full Access
Question # 27

One element of the task plan business analysis information management is:

A.

complexity and risk.

B.

change control process.

C.

level of abstraction.

D.

decision making authority.

Full Access
Question # 28

If a business analyst (BA) does not properly identify stakeholders, then the long-term implications are:

A.

increased costs.

B.

reduced requirements.

C.

higher satisfaction.

D.

decreased risk.

Full Access
Question # 29

Which of the following are criteria used to determine quality requirements relationships?

A.

Necessity, validate, derive

B.

Complexity, stability, status

C.

Necessary, consistent, correct

D.

Penalty, benefit, cost

Full Access
Question # 30

Which action would a business analyst (BA) propose to improve the operation of the business?

A.

Simplify the work people perform

B.

Outsource the operation team

C.

Assist in the daily activities

D.

Shadow the expert staff

Full Access