A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?
The human resources department of an organization needs a new report. The business analyst (BA) assigned to this effort has scheduled a requirements workshop with the users. Users from the legal department have also been invited to the workshop. As the BA sets up the workshop, what can be done in advance to ensure a productive and focused workshop?
For a new account payable (AP) solution, the solution owner has provided the business analyst (BA) with goals the AP management team would like the solution to support. To ensure the solution meets these needs, the BA documents key performance indicators (KPIs). Which of the following is an example of a KPI?
The business analyst (BA) is helping the business stakeholders prioritize requirements for a new customer portal for managing orders, delivery, and payment information. A number of requirements address compliance with regulations regarding access for people with disabilities. What factor should the BA use to guide the stakeholders when assigning a priority for these specific requirements?
A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort. How should the business analyst (BA) handle the situation?
A newly implemented personal loan financing system has been in operation for one month. The business objective is to reduce the loan processing time from 11 days to 3 days but it is currently occurring in 4.5 days. What must the business analyst (BA) do next?
A business. analyst (BA) is working on a project to implement a commercial off-the-shelf application for tracking customers. In an observation session with a Domain subject matter expert (SMF). the BA notes that the SME keeps separate records for the customers who are also vendors. The BA knows that the new software has a module for vendor management that would integrate the vendor and customer records. Which type of opportunity has the BA identified?
A business analyst (BA) is facilitating a meeting with subject matter experts (SMEs) in which the SMEs are answering questions about the major business processes and associated activities the business performs. The BA will create a deliverable from this discussion that will assist in defining scope. What technique is the BA using?
During a lesson learned session, stakeholders had a heated discussion on the performance measures being employed and why they are necessary. The business analyst (BA) explained that performance measures are required to:
During a senior management meeting about a project at the requirements analysis stage, a business analyst (BA) stated that there were a number of workarounds associated with the current application. The Chief Information Officer (CIO) was looking for ways to improve the situation and the BA suggests a solution. Which of the following can the BA suggest that the organization consider to increase efficiencies?
A business analyst (BA) spent three months eliciting, specifying, and modelling the detailed stakeholder and solution requirements. Right before requirement sign-off, the BA realized that the Vice President was unable to approve the requirements and the Chief Financial Officer should do so. What element of requirement approval did the BA miss?
A new contract requires a thorough level of documentation to be developed and maintained with planned phases of reviews and authorized sign offs. Which approach fits this contract?
A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the business requirements elicitation task. Upon review with the rest of the project team, it is determined that not all requirements can be implemented by the set deadline. What must the BA do to ensure maximum business value?
A business analyst (BA) is working on a project that has a number of stakeholder conflicts and issues. The BA is finding it difficult to resolve the conflicts and issues effectively. What should the BA do to prevent a similar situation in the future?
A business analyst (BA) is tasked with performing a gap analysis between two existing systems to combine into a single system or run just one system. Which of the following modelling formats will show the requirements for both systems side by side?
Stakeholder requirements where approved for a business process reengineering initiative along with the Creation of a | roadmap. Due to market conditions, the product roadmap is modified to move the default process to the next iteration. What should the business analyst (BA) modify in the stakeholder requirements?
A Chief Information Officer (CIO) was discussing a solution approach for a technology project in a meeting where a business analyst (BA) was also present. Stakeholders were discussing advantages and disadvantages of each solution approach. What should be the top priority for the BA in assessing the solution approach?
The Chief Executive Officer (CEO) of a company presents a new corporate strategy that will introduce a new system to the organization. The CEO has expressed a concern about the impact to the staff once the strategy has been implemented. What must the business analyst (BA) do to address concerns of the CEO?
A business analyst (BA) held a formal walk through of requirements developed on a project. Stakeholders expressed concerns because they had different interpretations of the requirements. What activity would help ensure a common understanding?
The claims intake workflow of an insurance company is being standardized across all branch offices. The business analyst (BA) assigned to this project has interviewed users individually in all the offices and plans to schedule a workshop with all the users. What should the BA do to prepare for the workshop?
A business analyst (BA) is examining the relationships between elicited requirements on a project. What quality criteria must be satisfied when the BA is defining requirements relationships?
A business analyst (BA) plans to organize a focus group to bring all the interested parties together and discuss the issues and possible risks for the new initiative. Due to the geographical differences of each participant a videoconferencing service will be used to satisfy stakeholder preferences. Which approach is the BA defining?
A business analyst (BA) has spent the week conducting work sessions with a project's key stakeholders. Together, they have been reviewing user requirements and high-level design flowcharts to ensure that they have been correctly defined and documented. Which of the following describes the purpose of their work?
A business analyst (BA) is assigned a new project and is beginning to prepare for elicitation. Which task must the BA complete before preparation of the elicitation process can begin?
A company has bought a customizable software product and the vendor's business analyst (BA) is visiting the company's office to perform a requirements assessment. The business sponsor expresses an interest in improving a specific process that is in scope. What should the BA do?
A business analyst (BA) conducted a requirements elicitation session with project stakeholders and communicated the results. The project sponsor expressed concern with certain requirements that address the federal government legislation. What must the BA do to address the concern of the project sponsor?
A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system. The BA aims to define the solution definition before implementation, capture the information in standardized templates, and ensure that all activities are identified first and then divided into tasks. Which approach provides the appropriate level of formality for this project?
A solution that was implemented several years ago has achieved its stated objective of consolidating data from multiple sources. However, end user feedback reveals problems and inefficiencies. What should the business analyst (BA) do first?
A long-established company selling ice cream is entering its crucial sales period leading up to summer. Based on the company's risk tolerance, a business analyst (BA) has advised against replacing the most popular flavors with new untested flavors. What is the company's attitude toward risk, as assessed by the BA?
The emergence of self-driving vehicles has disrupted the auto insurance industry. The Chief Information Officer (CIO) has asked the business analyst (BA) to modify the existing business model to include self-driving vehicles. Which of the following will be valuable information for the BA to use?
A business analyst (BA) has recently joined a large consultancy firm where BAs are globally distributed on different assignments. Where would the BA find expectations for business analysis work as mandated by the consultancy firm?
A business analyst (BA) is in the process of specifying the confirmed results of a requirements elicitation workshop. Which of the following help to ensure that the correct information about the requirements is provided to the participants?
Which tool will allow a business analyst (BA) to determine how information is input, processed, stored, and extracted from a collection of systems?
The business analysis deliverables went through a formal performance review process. The performance report stated that changes to the business analysis approach must be made in order to maximize the project's chances of success. Who must be consulted regarding these changes before they are implemented in this project?
A business analyst (BA) develops a template to document the product feature requirements for an enterprise software solution. Within the template, the BA includes the following additional information: source, priority level, level of complexity, and last modified date. What does the additional information describe?
A project team member is confused about why a small change requires the team to look at the different enterprise-level business objectives when a desired state can be achieved easily without this analysis. What can the business analyst (6A) do to help the team member understand?
A business analyst (BA) is working on a project to revise the way a company bills its customers. At the onset of the project, the BA creates the following matrix:
Stakeholder requirements were approved for a business process reengineering initiative along with the creation of a roadmap. Due to market conditions, the product roadmap is modified to move the default process to the next iteration. What should the business analyst (BA) update in the stakeholder requirements?
The Business Requirements Document (BRD) prepared by the business analyst (BA) was circulated to stakeholders for approval. Some stakeholders objected to the Use Case diagrams and could not understand them. Why would these be included in the document?
A Chief Information Officer (CIO) was discussing a solution approach for a technology project in a meeting where a business analyst (BA) was also present. Stakeholders were discussing advantages and disadvantages of each solution approach. What should be the top priority for the BA in assessing the solution approach?
The business analyst (BA) is investigating techniques that would be appropriate for determining how and who uses data across the identified processes. Which technique should the BA select?
A new regulation results in organizations needing to change online contractual wording. A business analyst (BA) has elicited the requirements and documented them in a change control request. Where will the BA find out which stakeholder has the authority to approve, deny, or defer the change request?
A business analyst (BA) has been tasked with examining and analyzing the relationship between a set of requirements by verifying that they are unambiguous. What will the BA be looking for?
A newly implemented personal loan financing system has been in operation for one month. The business objective is to reduce the loan processing time from 11 days to 3 days, but it is currently occurring in 4.5 days. What must the business analyst (BA) do next?
A business analyst (BA) decided to capture requirements by inviting all the stakeholders to meet at an office location. After invitations were sent, it turned out that not everyone could attend this meeting because of their individual dispersed locations. Which of the following does the BA need to adjust to handle this situation?
Project work is taking place to evaluate whether a system's requirements can be met via creating internally, purchasing from others, or a combination of the two. What goal is addressed by this analysis?
Several user groups are impacted by a proposed change to their daily workflow. How should the business analyst (BA) convey these changes so that the user groups understand the impact?
A business analyst (BA) has recently joined a large consultancy firm where BAs are globally distributed on different assignments. Where would the BA find expectations for business analysis work as mandated by the consultancy firm?
After an initial project kick-off meeting, the business analyst (BA) determined that the project has a short deadline and a regulatory mandate with stiff penalties for non-compliance. The stakeholders do not want to risk missing the deadline, and management is willing to commit any amount of resources to meet the deadline. Which kind of approach is suitable for the initiative?
A business analyst (BA) is facilitating a meeting with subject matter experts (SMEs) in which the SMEs are answering questions about the major business processes and associated activities the business performs. The BA will create a deliverable from this discussion that will assist in defining scope. What technique is the BA using?
A business analyst (BA) is developing requirements for a project with a limited budget. The business owner will be prioritizing requirements so that low-value requirements can be de-scoped and the project remains within budget. Which of the following should the BA take into account to facilitate prioritization and ensure business objectives are met?
Market studies projected a 28% year-over-year growth for five (5) years for commercial vehicle loans. A company that provides lending for commercial vehicles wanted to keep up with industrydemand; however, their applications were not capable of scaling to the increased demand for loan processing and billing. The company is deploying a new system to meet the demand. The project started five (5) years ago and cost $2 million USD. The project metrics are to be evaluated after five (5) years. The return on investment (ROI) for the project is calculated at 11%. The project sponsors are upset that the desired ROI for the project was not met. What was the root cause of this issue?
After a number of requirements elicitation workshops, the business analyst (BA) notices that two business stakeholders did not speak up during any of the discussions. What should the BA do in the next workshop?
A business analyst (BA) is managing stakeholder collaboration to ensure positive reactions are capitalized upon. There is uncertainty as to whether the correct stakeholders have been identified. Which technique can be used to correct this situation?
A business analyst (BA) has been asked to develop a plan to complete the associated business analysis activities for a project in which an organization is switching from a manual to an automated process for receiving payments. As the final step in developing the plan, which technique will the BA use?
A business analyst (BA) has structured information so it is easy to find, does not conflict with other information, and is not duplicated unnecessarily. Which additional factor does the BA need to take into account when deciding how to structure the information?
For a new accounts payable (AP) solution, the solution owner has provided the business analyst (BA) with goals the AP management team would like the solution to support. To ensure the solution meets these needs, the BA documents key performance indicators (KPIs). Which of the following is an example of a KPI?
The business analyst (BA) is preparing for a requirements review with a group of stakeholders. The BA must determine how best to model the requirements for the review. Which of the following guidelines and tools will the BA use?
A business analyst (BA) elicits requirements from end users for a new application and then documents a set of use cases and use case scenarios. What should the BA do next?
A business analyst (BA) is proposing design options and a number of opportunities are occurring that need to be understood further. One particular opportunity will prevent different stakeholders from performing the same function in distinctly different ways. What type of opportunity is this?
The Chief Executive Officer (CEO) is concerned about how two client bases are going to be integrated and serviced in the newly formed company after a merger. A project has been initiated to implement a Customer Relationship Management (CRM) system for the new company that will contain the client information from both companies. What must the business analyst (BA) do to address the concerns of the CEO?
A company wants to increase its market share in the industry, and its Board has prioritized capabilities that need to be implemented to achieve the goal. The business requirements for the top priority were signed off, and the solution design has been completed. Due to technical constraints, it is not feasible to implement all the requirements at the same time. What must the business analyst (BA) do to deal with this situation?
A business analyst (BA) is preparing for a requirements review with a group of stakeholders. The BA must determine how best to model the requirements for the review. Which of the following guidelines and tools will the BA use?
A finance manager wants to begin a new project to replace the existing expense processing system. The finance manager feels that the current expense submission-to-reimbursement process takes too long and is substantiated by 50% more complaints regarding incorrect reimbursement amounts than the same time last year. What should the business analyst (BA) investigate first?
A business owner has identified a high-priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to conduct an impact analysis of this change. Which factor will the BA need to consider?
A business analyst (BA) is examining the relationships between elicited requirements on a project. What quality criteria must be satisfied when the BA is defining requirements relationships?
A company has bought a customizable software product, and the vendor's business analyst (BA) is visiting the company's office to perform a requirements assessment. The business sponsor expresses an interest in improving a specific process that is in scope. What should the BA do?
A business analyst (BA) spent three months eliciting, specifying, and modeling the detailed stakeholder and solution requirements. Right before requirement sign-off, the BA realized that the Vice President was unable to approve the requirements and the Chief Financial Officer should do so. What element of requirement approval did the BA miss?
A project is being initiated to create new financial reports for the accounting department, and the accountants have a wide range of views as to what would serve them best. What should the business analyst (BA) do to develop the correct set of requirements?
A business analyst (BA) has discovered an old checklist prepared for another initiative, which includes the following characteristics:Complete, Feasible, Unambiguous, Testable. What is the purpose of this checklist?
An organization's board of directors has funded a new mobile application to support external customers. The business case was developed with an emphasis on objectives to broaden the organization's brand and increase customer engagement. The business analyst (BA) is reviewing a group of user stories with the product owner. One of these user stories is:
"As a customer service representative, I need to enter my time on the mobile application so that I can leave work to pick up my sick daughter from school."
The product owner wants to take advantage of this opportunity to provide the staff with a way to enter their time away from the office and create an interface to the Payroll application. How must the BA evaluate alignment with the existing objectives?
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?
A business analyst (BA) is tasked with performing a gap analysis between two existing systems to combine into a single system or run just one system. Which of the following modeling formats will show the requirements for both systems side by side?
During planning, elicitation, and sign-off of requirements, the stakeholders felt that their opinions were not heard and information was not frequently shared. What major competency was lacking in this process?
Stakeholders must be able to determine the audit and approval history of requirements and designs. Which of the following provides a means to document traceability and change?
A business analyst (BA) has developed requirements for a project containing sensitive information. The requirements were approved, and the solution was implemented. What should the BA do to ensure these requirements are maintained for future reference?
Beth is the business analyst for her organization and she wants to be certain that she and her team follow the correct procedures for enterprise analysis. What document can provide the governances for enterprise analysis efforts?
When a business analyst performs requirements tracing, he may need to trace the requirements backward through their lineage and may need to trace the requirements forward through their relationship to other requirements. What is the forward tracing activity called in requirements traceability?
Some of the requirements in the solution must be completed because of laws and regulations in your industry.
Management would like you, the business analyst, to rank the requirements according to the relevant laws. What type of requirements prioritization is management having you complete?
In a change-driven environment, what's more important than formal communications in regard to effective requirements management?
What business analysis process is needed to define the solution scope and prepare the business plan for the endeavor?
What type of a business analysis approach focuses on the rapid delivery of business value in short iterations?
In order to define the business need for an organization, there are two inputs. What are the two inputs a business analyst will need to define the business need?
As a business analyst, you'll often have to coach stakeholders on the processes, knowledge areas, and tasks
you'll complete for an organization. One of the knowledge areas is enterprise analysis. This knowledge area completes all of the following activities except for which one?
You are a business analyst for your organization and you're working with the stakeholders to identify the primary inputs to the business analysis approach. Which of the following will help determine whether a plan- driven or change-driven approach is appropriate?
Each correct answer represents a complete solution.
Business needs do not always originate from the business analyst or from business owners. There are several stakeholders which may identify or contribute to the identification of a business need. Which one of the following stakeholders are most likely to have the most direct awareness of problems that could lead to a business need?
You are a business analyst for your organization and you're working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you're already the business analyst for your organization. This approach helps to find out the following except for which one?
You are working with several business analysts to determine the solution approach for an identified problem. All of the following techniques are acceptable for identifying the solution approach except for which one?
Henry and Fred are working together on business analysis duties for the implementation of new software. Henry, the business analyst, tells Fred that they should take the current measurement of productivity, and then measure again after the solution has been implemented. This benchmarking approach will allow Henry and Fred to see the real effect of the solution on the business need. What term is assigned to this measurement?
If a requirement has been satisfied, why is it still considered a requirement?
Which stakeholder analysis technique shows stakeholders that fall outside the scope of the solution but still interact with it in some way?
An organization is engaged in an effort to streamline the online customer experience. The business analyst (BA) prepares a business analysis information package to discuss the changes the customer will experience. Which one of the following tools will assist the BA in this discussion?
All of the following are documented approaches to business analysis work except for which one?
You are a Business Analyst for your organization, and you're preparing to elicit requirements from stakeholders. You've gathered several inputs to help with the elicitation process. Which input will you use to ensure that you understand the type of information that should be elicited from stakeholders?
Sam is preparing for the task of prioritizing requirements and he'll need five inputs to accomplish the task. Which one of the following is not an input that Sam will use to prioritize requirements?
You are the business analyst for a smaller project where there are few requirements. Management would still like you to create a method to trace the few requirements for this project. What type of matrix would be best in this instance?
A business analyst (BA) is working on a project that follows incremental and iterative approaches. The BA and the stakeholders have shortlisted several user stories to be considered in the project scope. Which of the following methods would enable them to arrive at a common understanding on delivering value in the product and ranking the stories?
The Business Requirements Document (BRD) prepared by the business analyst (BA) was circulated to stakeholders for approval. Some stakeholders objected to the Use Case diagrams and could not understand them. Why would these be included in the document?
A business analyst (BA) has discovered an old checklist prepared for another initiative, which includes the following characteristics: Complete, Feasible, Unambiguous, Testable. What is the purpose of this checklist?
A business analyst (BA) creates several use case scenarios to specify the requirements for a system. When the beta version of the system is released, there are problems because several important pieces of information are missing. What should the BA have done to avoid this situation?
A business analyst (BA) was asked by the vice president (VP) to evaluate the organization's claims processing capability and recommend improvements. The VP agreed to the BA's recommended solution approach and identified an external vendor to develop the modernized claims processing system. Before contracting with the external vendor, the BA realized that the budget should be approved by the Chief Financial Officer. What was missed by the BA when performing stakeholder analysis?
A senior business analyst (BA) is tasked with verifying a set of requirements written by a junior BA for a
system. During this exercise, the junior BA will ensure that the requirements exhibit atomic characteristics. The senior BA will be verifying that the requirements:
Sam is the project manager of the NHT Project. His project has stakeholders from the end users, server administrators, functional managers, external customers, technicians, and executive managers. In this high- profile project, which group of stakeholders is the most important?
Bradley is working with the business analyst Marsha to prioritize requirements for their organization. Marsha insists that the requirements be ranked on the cost-benefits analysis of the relative value to the organization. What type of prioritization approach does Marsha want to use in this scenario?
You are the business analyst in your organization. Management comes to you with a customer complaint that they'd like you to analyze. What's the common task associated with customer complaints or loss of revenue?
Which solution scope creation technique can be best described as the depiction of the scope of work required to integrate the new solution into the business and technical environments?
Which of the following defines all of the features and functions of the thing, solution, or service the project or organization will create?
As a business analyst, you should work to identify opportunities to improve the operations of your organization. Which one of the following improvement opportunities aims to improve the experience of the customer?
You are the business analyst for your organization and you're working with your manager to discuss the constraints and assumptions that may affect the requirements. Your manager wants to know from where you've derived the list of constraints and assumptions. What's the best answer as to where assumptions and constraints are identified?
A business analyst has been assigned the task of developing a model of the current state of an organization. The business analyst doesn't understand why a current state may be needed. All of the following are good reasons to create a current state model of an organization except for which one?
Enterprise analysis provides many things for an organization. All of the following are tasks included in enterprise analysis except for which one?
A business analyst (BA) has been asked to develop a plan to complete the associated business analysis activities for a project in which an organization is switching from a manual to an automated process for receiving payments. As the final step in developing the plan, which technique will the BA use?
A business analyst (BA) identified that a stakeholder requirement for an online system led to a functional requirement to provide a user login screen. This is an example of which type of traceability relationship?
A business analyst (BA) is planning the requirements attributes. The BA received a long list of requirements that must be implemented in different phases. Which requirements attribute can the BA include to allocate the requirements to the proper phase?
In order to plan the business analysis approach, the business analyst must understand the organizational process needs and what other thing?
A business analyst (BA) has completed an impact analysis of a proposed change, gained approval for the change, and has updated the requirements. The project sponsor wants to be updated with an overview of the results. How should the BA communicate the results?
You are the business analyst for your organization and you're training Marcy, a new business analyst, on how requirements are defined. Which one of the following best describes how requirements are defined?
There are three business analysis planning techniques that a business analyst can use to help plan business analysis processes. Which one of the following is not one of the three techniques?
Marcy is working with stakeholders to understand the stakeholders' needs as part of the business requirements. The stakeholders are describing their needs for new computers for their designers. The stakeholders have specifications, monitors, and software selected for the business requirements. What are the stakeholders actually defining in this scenario?
Enterprise analysis creates just five outputs. Which one of the following is an output of the enterprise analysis tasks?
A business analyst has identified four different solutions for a business need. In the light of solution assessment, how many solution assessment iterations should he do?
An organization has invested $750,000 into a technology to help secure, automate, and communicate customer ordering. The solution has worked well for the past six months, but a newer technology has been developed that surpasses the abilities of the current solution and solves many defects and issues the company has with the existing solution. Purchasing the newer solution, however, means that the company will have to discard the solution that's only been in place for the past six months. What term can be assigned to the monies already implemented into the existing solution?
Bonny is the business analyst for her organization and she's making a determination from which vendor the solution should be purchased. She has identified several categories to measure each vendor's overall performance and solution. cost, schedule, experience, certification, references, and years in business. For each category, she has identified scores the vendor may earn; for example, cost is worth 25 points, schedule is worth up to 20 points, and years in business is worth up to ten points. The vendor who gets the most points in the assessment will win the contract. What is Bonny using in this scenario?
You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved. What is management asking you to create?
Mark is the business analyst for his organization. He is working with the solution development team and he believes that the team does not want to implement a certain portion of the requirements. The team is expressing the difficulty of the requirements and how it will be extremely challenging to complete. When Mark asks about a similar project that the team completed, they insist that this is a different type of requirements though Mark believes that it is not. What is the solution development team appearing to do to the requirements?
One of the techniques to assess capabilities in an organization is to use SWOT. What does SWOT accomplish?
The business analyst (BA) has traced the requirements for the interaction between a customer and the new online ordering system. Besides enabling the BA to ensure quality of the requirements to stakeholders, tracing the requirements will also enable the BA to:
A business analyst (BA) is determining the current state as part of a new project. What is an internal enterprise asset that the BA must include in the analysis?
A business analyst (BA) was asked to send the requirement details to the project manager (PM), director, vice president (VP), and Chief Information Officer (CIO). The BA shares the complete set of requirements to the PM and director, while creating a summarized version for the VP and CIO. Which aspect of requirement specification and modeling was the BA performing?
A lead business analyst (BA) analyzed the performance of all BA's within the organization. How should the BA approach communicating the results to stakeholders?
Due to a change in regulation, a solution being implemented has a new compliance requirement that must be evaluated. The requirements change strategy focuses on total cost of change as the primary driver for decisions. The business analyst (BA) compiled the following impact assessment of the proposed change based on the new compliance requirement.
What recommendation should the BA make to the stakeholders based on the above information?
A business analyst (BA) is preparing the elicitation activity plan for a project. How will understanding the elicitation scope assist the BA with the elicitation activity?
A business analyst (BA) is planning the traceability approach for a project. Why should the BA conduct this planning activity?
A business analyst (BA) needs approval for the requirements which were elicited, collated, and verified by a peer. The BA needs to understand the approval process and appropriatestakeholders who have the authority to approve the requirements. Which of the following artifacts contains this information?
A business analyst (BA) is working to identity the business need, specifically the problems with the current state of a process. At which level of the enterprise can the BA identify problems with the current state?
A business analyst (BA) is conducting a workshop with the purpose of analyzing a business process. Stakeholders of different business units are in attendance. Each stakeholder is able to explain their unit's contribution to the process, however, there is no end to end process owner who can provide a consolidated view. Which technique should the BA use to compare the stakeholder's inputs against each other in order to check for consistency and omissions?
A business analyst (BA) has documented the components of an information technology (IT) library, in preparation for establishing a consolidated catalogue of IT services. When interviewed, several of the IT managers indicated they already have a catalogue, and have no additional information to provide. What activity is necessary to support the project?
A business analyst (BA) identifies a design option that enhances the performance of the business by automating repetitive tasks that require multiple staff touchpoints to complete a single task. Which type of improvement opportunity is identified by the BA?
A business analyst (BA) is assessing risks on a project addressing the implementation of a new web portal. Which of the following would the BA classify as a project risk?
A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity. What must the BA do to ensure maximum benefit for the stakeholders?
A company wants to increase its market share in the industry and its Board has prioritized capabilities that need to be implemented to achieve the goal. The business requirements for the top priority were signed off and the solution design has been completed. Due to technical constraints, it is not feasible to implement all the requirements at the same time. What must the business analyst (BA) do to deal with this situation?
The business analyst (BA) is analyzing the formal relationships between people working in the enterprise. Which technique will the BA use to perform this task?
A business analyst (BA) is working on a project to provide a temporary solution that will last for two months. The BA is feeling overwhelmed with the work needed to create the huge number of links to provide full traceability from solution requirements to design for this solution. How can the BA justify omitting all possible links?
The business analysis (BA) team is evaluating a new commercial off-the-shelf (COTS) application that will be implemented in the coming months. The company has over 20 legacy systems deployed. The Chief Information Officer (CIO) is worried about the need for integration and that some key linkages are missing.
What is the BA team evaluating?
A large online retailer is introducing new technology to upgrade its aging ordering process. The business analyst (BA) has drawn a stakeholder matrix showing information on how to engage with the stakeholders throughout the project.
Using the stakeholder matrix as a guide, how should the BA engage the suppliers?
A business analyst (BA) is verifying requirements for a software solution. The BA needs to confirm that items determined to be important are included in the final requirements deliverable. Which of the following will help the BA complete this task?
A business analyst (BA) is working on a project involving the purchase of a commercial off-the-shelf (COTS) product. All internal risks have been identified and assessed. What is the BA's next course of action?
A business analyst (BA) has identified the impacts and resolution for a proposed change. Based on the Responsible, Accountable, Consulted, informed (RACI) matrix, who must approve the change before it is implemented?
Several user groups are impacted by a proposed change to their daily work flow. How should the business analyst (BA) convey these changes so that the user groups understand the impact?
A business analyst (BA) is developing the requirements for an inventory management system. Some current accounting processes are automated but other departments like purchasing, marketing, sales and distribution departments work in isolation and have a manual process. They extensively use spreadsheets to maintain the transactions and at the end of the day the department managers manually verify and reconcile transactions before supplying the information to the accounting department. In order to verify and validate the elicited requirements, the BA will need to prepare a:
A banking giant recently found a major security loophole in their online banking platform that could expose customer information. Security experts and the business analyst (BA) develop a low cost, low effort emergency fix to address this issue. What factor should the BA use to convince the bank to move forward with the emergency fix?
A business analyst (BA) is reviewing the elicitation results of several workshops in order to decide which technique to use to model the requirements. The elicitation identified user roles needed in a future solution, the functionality needed by each of these roles, and how the desired interaction with the solution should look.
Which technique allows the BA to model this type of information?
A new regulation is introduced that the project must comply with to remain competitive and industry compliant. Management wants to understand the effect of this new requirement on the project. What will the business analyst (BA) use to evaluate the change?
A company is embarking on a software project in a heavily regulated domain. The client expects large upfront planning and detailed documentation for the project. The recommended approach for the project will be:
A business analyst (BA) is informing stakeholders about the importance of quality when eliciting requirements. What characteristic describes a quality requirement?
You are the business analyst for your organization and you're notifying the key stakeholders of a need to gather requirements for an endeavor. One of the stakeholders that you'll need to attend your requirements workshop is the project manager. What role will the project manager have in this workshop?
Which task in the requirements analysis knowledge area is best described as ensuring that the requirements specifications and models meet the necessary standard of quality to allow them to be used effectively to guide further work?
Management in your organization wants you to create a graphical model to show the business logic of the requirements. What other term are graphical models known as?
A business analyst needs to prepare the requirements package for her endeavor in a predefined template for her company. What term can be assigned to this standardized template for packaging the requirements?
You are the business analyst for your organization and you're preparing the solution for your organization's review and implementation. Some of the requirements of the solution, however, must be inspected by compliance officers before the project and implementation can move forward. The requirements of the inspection can be best described as what?
You are the business analyst for your organization. You are currently identifying opportunities for a customer to improve their business processes. The customer wants to streamline their business efforts either through new technologies, better processes, or a combination of both. The customer demands, however, that the solution should not cost more than $300,000 to implement and support for one year. What does the $300,000 represent?
Barry is a project stakeholder that is excited about the deliverable your project wants to create for the organization. He's helpful, provides information, and offers support whenever your project needs it. How would you classify Barry based on this information?
What should an organization do if the business analyst has determined that the existing capabilities are inadequate to seize an opportunity?
In order to have high quality in requirements, all of the following characteristics should exist in the requirements except for which one?
Complete this statement.are longer-term, ongoing, and qualitative statements of a state or condition that the organization is seeking to establish and maintain.
In order to plan business analysis activities, you will need four inputs. Which one of the following inputs is not valid for this task?
A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?
You are a business analyst for your organization. Your current business analysis endeavor includes working with stakeholders located in offices around the world. Because these stakeholders are dispersed, what is likely to increase in this endeavor as opposed to a collocated group of stakeholders?
There are four inputs to the plan business analysis activities. Which one of the following is not an input to the plan business analysis activities process?
When a business analyst assists in the planning of the solution implementation, she must always consider the constraints for implementation. Which one of the following cannot be considered as an implementation constraint?
As a candidate for CCBA, you should be able to recognize the activities associated with each knowledge area. Which of the following is an elicitation process that is a part of job observation?
You are the business analyst for an organization and you're managing your stakeholders through the requirements validation activities. Your stakeholders are categorized by executives, functional managers, directors, end users, and customers. Which of these stakeholders are involved in the requirements validation
activities?
What does the decomposition of activities and tasks based on the work breakdown structure create for the business analyst?
A business analyst wants to use benchmarking, but the project manager recommends against the approach. There are, as the project manager points out, several disadvantages to benchmarking. Which one of the following is not a disadvantage to benchmarking?
Which of the following defines all of the required work to satisfy the requirements of the project?
The business need is considered to be the most critical step in the business analysis effort. Why is the definition of the business need considered the most critical step?
Which of the following approaches describes the project management approach of refining requirements and project scope?
According to the book 'A Guide to the Business Analysis Body of Knowledge', effective business analysis practices can do what to the amount of change to requirements in a stable business environment?
When a business analyst is using alternative generation, what should she always include as an output?
Wanda is the business analyst for her organization and she is currently working on the specify and model requirements process. One of the elements of this process is the documentation of the textual requirements. Wanda must describe the capabilities of the solution, any conditions that must exist for the requirements to operate, and what third component of the textual requirement?
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?
A business analyst (BA) is verifying a set of requirements. One of the requirements is “After the customer has received an email confirmation, the customer is likely to access the order status in the order history which is available upon order submission.” Which one of the following requirements quality characteristic is breached?
By which of the following is the performance of all requirements management and communication activities governed?
Henry is meeting with Janet, the business analyst of the organization. They are discussing an opportunity to create a new service their company can provide, though the startup of the service would take time and an investment. Henry wants Janet to explore the possibility of this new venture. What activity is Henry asking Janet to complete?