Question # 6

Below are descriptions of five companies in the UK. Each company has a unique organisational culture and a key Cultural Web Influence that shapes its structure and operations.

Your task is to match the correct type of organisational culture and cultural web influence to each company.

Company Descriptions

    Company 1

      Description: Authority is centred around the founder. There are strict financial systems and a reward/bonus scheme for meeting targets.

Company 2

    Description: Employees operate independently and often bring in their own clients. There is a strong corporate identity and branding.

Company 3

    Description: Strict hierarchy determines salary and job titles. The organisation is described as bureaucratic and follows stringent rules.

Company 4

    Description: Employees work in small teams or individually on projects. There is a strong emphasis on weekly team meetings where tasks for the upcoming week are discussed.

Company 5

    Description: Authority is held by senior leadership who make all decisions. There are few rules, and culture is reinforced by storytelling about past successes.

Full Access
Question # 7

The Human-Relations Model describes a type of organization with a set of values. Which TWO of the following apply?

A.

high levels of flexibility

B.

low levels of flexibility

C.

a focus on internal business functions

D.

a focus on the external environment

Full Access
Question # 8

Cyril Engineering entered into a contract with Dojo Ltd for electrical engineering services to a power station.

    The contract was successful for two years, but Cyril Engineering failed to fulfill obligations recently.

Q: What is this situation known as?

Answer Options:

A.

Consequential Loss

B.

Damages

C.

Default

D.

Direct Loss

Full Access
Question # 9

A positive work culture can lead to which of the following benefits? Select all that apply

A.

lower levels of redundancy

B.

improved performance

C.

increased productivity

D.

higher levels of resistance to change

E.

higher retention

Full Access
Question # 10

Ali is a team manager at his organisation and has been instructed by senior leadership to implement a change that requires his staff to come into the office an hour earlier than usual. Although he knows the change won’t be popular, he plans to tell his team that the change will start next month and insinuate that non-compliance may affect promotion eligibility. What type of influence is Ali exerting?

A.

explicit coercion

B.

implied coercion

C.

bribery

D.

persuasion

Full Access
Question # 11

According to Hofstede's Cultural Dimensions, Individualism is when a person prioritises themselves over a group. Is this correct?

A.

yes – individualism is seen as a selfish culture

B.

yes – this is the opposite of collectivism

C.

no – this is where an individual does not take risks that may have an adverse affect on themselves

D.

no – individualism means accepting immediate gratification

Full Access
Question # 12

Scenario (same as Question 16):

    What type of power does the CFO have at Fin Inc?

A.

positional power

B.

expert power

C.

personal power

D.

negative power

Full Access
Question # 13

Green Thumb Ltd, a landscaping company, is considering investing in a new lawn mower costing £10,000. The CFO estimates that the new machinery would increase annual income by approximately £2,000. What is the payback period of the investment?

A.

20%

B.

10 years

C.

5 years

D.

£8,000

Full Access
Question # 14

Jennifer is drafting a contract with a "termination for convenience" clause.

Q: What obligations should be included in this clause? (Select all that apply.)

✔ The return of any advance payments

✔ The destruction of confidential information

✔ The smooth transition of services to a new supplier

Full Access
Question # 15

XYZ is a large construction organization running five different projects. Each project has a specific type of contract and pricing mechanism.

Your task is to match the correct type of contract and pricing mechanism to each project.

Projects and Descriptions

    Project 1

      Description: Construction of an apartment block, where XYZ is responsible for both design and construction. Upon completion, ownership is transferred to the client.

      Pricing Mechanism: Based on past experience of similar projects.

Project 2

    Description: Facilities management for a 6-year period after construction. The budget is constantly adjusted due to industry volatility.

    Pricing Mechanism: Budget changes continuously over time.

Project 3

    Description: XYZ was involved from an early stage, but does not bear the design risk. The budget resets at the start of each new accounting period.

    Pricing Mechanism: The budget is refreshed periodically.

Project 4

    Description: XYZ is responsible for certain parts of the design and build, while another company handles other aspects. XYZ is paid upon milestone completion.

    Pricing Mechanism: Payment is milestone-based.

Project 5

    Description: Construction of a new toll bridge which will be operated by XYZ for the first 6 years post-construction. The pricing includes costs of raw materials, labor, and a profit margin.

    Pricing Mechanism: Costs plus profit.

Full Access
Question # 16

KCJ Ltd is a public sector organisation planning five projects for the next financial year. Each project has a distinct cost estimation method and source of power for the project leader.

Your task is to match the correct cost estimation method and source of power to each project.

Project Descriptions

    Project 1

      Description: Budget estimation is calculated using an algorithm.

      Project Lead’s Power: Founder of the organisation.

Project 2

    Description: The Head of R&D (PhD in Data Science) is using costing from similar past projects to determine the budget.

    Project Lead’s Power: Expertise in Data Science.

Project 3

    Description: The project is led by a key stakeholder and involves creating a Bill of Materials. Costs are worked out item by item.

    Project Lead’s Power: Authority due to stakeholder influence.

Project 4

    Description: The Project Leader has calculated the base cost, most likely cost, and worst-case scenario.

    Project Lead’s Power: Has the authority to cancel the project at any time.

Project 5

    Description: The project leader is a well-liked Board Member who has selected a team he is comfortable with. He determined the budget based on his own research.

    Project Lead’s Power: Personal relationships with team members.

Full Access