In the UK, Unfair Contract Terms Act 1977 regulates which of the following?
Under general legal principles of contract formation, which of the following will always automatically result in the termination of an offer?
1. Negotiation
2. Rejection
3. Failure conditionality
4. Non-disclosure
Which of the following is an example of liquidated damages clause?
1. "In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price."
2. “If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay"
3. "The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer."
4. "The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery"
Under a price adjustment agreement, which of the following would be supplier's justification for increasing unit price?
Which of the following are likely to feature within an outcome-specification?
1. Dimension
2. Performance requirement
3. Input material
4. Product function
A procurement manager is setting KPIs measurement for user satisfaction. He also wants to encourage users to share the reason why they feel the way they do. Which of the following types of KPI should the procurement manager apply?
According to mailbox rule in some common law countries, at which point the offeree's acceptance will be effective?
If service level agreement is used as a schedule that makes up the contract, it will be most likely to be a part of...?
Which of the following are features of performance specification?
1. Method of achieving the buyer's desired result
2. What needs to be achieved when using the product
3. Purposes of the product
4. Technical and physical characteristics of the product
Which of the following is used to detail the complex matter that may be verbiage to the main document?
Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark’s procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard. Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?
In a contract, both buyer and supplier agreed the lead time is 3 days. The contract also requires that any variation must be made in writing. Then the buyer places an order by phone call and requests delivery the next day, but the supplier delivers on the third day since the order. Can buyer refuse to pay as supplier did not deliver per time?
Which of the following are typically included in an SLA? Select TWO that apply:
To expand its operation, Steel Co. decides to build a new plant. Despite of excitement, the senior management is very concerned about the complexity and risks of such project. Hugo, the procurement manager, suggests that the company can adopt a model form of contract. What is the advantage of using model form of contract?
XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation. Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier's poor performance?
1. Warranties
2. Force majeure clauses
3. Penalty clauses
4. Service credits
CMS Corp goes into a gainshare agreement with the contractor, EIP Ltd. Both parties agree that the final fee will be calculated on target cost - target fee basis. Which of the following will affect the final fee payable in this gainshare agreement? Select TWO that apply:
Which of the following is likely to reduce risks of different rules regarding when offers and acceptance become effective between legal systems?
Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.
Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?