Black Friday Sale - Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70dumps

CCP Questions and Answers

Question # 6

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?

A.

Ratio/level of effort

B.

Start/finish

C.

Units completed

D.

Incremental milestone

Full Access
Question # 7

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The longest path depends upon relationships driving the timing of activity starts, therefore the following scheduling features should not be used in calculating file longest path.

A.

milestone activities

B.

activities with lag

C.

activities with short durations

D.

constraints, resource leveling, and interruptible activities

Full Access
Question # 8

Budgeted cost of work scheduled is all of the following except:

A.

Total costs incurred in accomplishing work in a given-time period

B.

Baseline for performance measurement

C.

Sum of the budgets for work scheduled

D.

Includes portion of the budget for level-of-effort work

Full Access
Question # 9

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If you are scheduled for a $100,000 payment at the end of each year for the next five years, what is the equivalent amount if you were to make a lump sum payment now?

A.

$162,370

B.

$679,397

C.

$379,100

D.

$500,000

Full Access
Question # 10

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

It S480 is the target net profit, then the total sales volume (in dollars) is:

A.

$30,000

B.

$37,500

C.

$34,400

D.

$32,400

Full Access
Question # 11

Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

A.

ACWP/BCWS

B.

BCWS/BCWP

C.

ACWP/BCWP

D.

BCWP/ACWP

Full Access
Question # 12

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)

A.

4.62

B.

4.24

C.

4.10

D.

4.31

Full Access
Question # 13

A contract clause that provides the owner with the right to terminate the contract irrespective of the general contractor's liability is:

A.

Termination of contract - convenience

B.

Termination of contract - default

C.

Substantial completion

D.

Breach of contract

Full Access
Question # 14

Which of the following is NOT an advantage specific to a cost reimbursable contract?

A.

Evaluation of proposals are much simpler

B.

Provides flexibility in dealing with changes

C.

An early start can be made

D.

Owner controls all aspects of the work

Full Access
Question # 15

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?

A.

82%

B.

75%

C.

90%

D.

84%

Full Access
Question # 16

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow’s hierarchy of needs?

A.

Belonging needs

B.

Self-actualization

C.

Knowledge

D.

Pay and compensation

Full Access
Question # 17

Which statement best describes the constructability review for a project?

A.

Is concerned primarily with resource scheduling and organizational planning

B.

The review by a multi-discipline team to Improve the methods of delivering the intended scope

C.

A method to reduce costs by considering alternate designs

D.

The systematic application of recognized techniques which identify the functions of the product or service

Full Access
Question # 18

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $10,000 is scheduled to be paid out 5 years from now, what is the minimum amount we can invest today?

A.

$3,855

B.

$8,129

C.

$6,209

D.

$3,791

Full Access
Question # 19

Which of the following is used for measuring productivity loss?

A.

Central limit theorem

B.

Value engineering

C.

Earned formula

Full Access
Question # 20

A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:

A.

Surety bond

B.

Performance bond

C.

Bid bond

D.

Liability bond

Full Access
Question # 21

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the cost variance (CV)?

A.

BCWP-ACWP = 105,000-110,000 = -5,000

B.

ACWP-BCWP = 110,000-105,000 = 5,000

C.

BCWS-ACWP = 100,000-110,000 = -10,000

D.

ACWP-BCWS = 110,000-100,000 = -10,000

Full Access
Question # 22

A work breakdown structure (WBS) is developed because:

A.

It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.

B.

It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

C.

It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup

D.

It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Full Access
Question # 23

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The value of the truck at the end of year five (5) would be:

A.

$0

B.

$14,265

C.

$25,000

D.

$23,366

Full Access
Question # 24

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Present worth calculations is represented by which of the following equations?

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 25

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The following question requires your selection of Scenario 1.4.162 from the right side of your split screen, using the drop down menu, to reference during your response/choice of response.

The budgeted cost work performed is;

A.

$90,000

B.

$100,000

C.

$95,000

D.

$108,000

Full Access
Question # 26

How can the quality of a cost/capacity factor estimate be improved?

A.

Validate the capacity factor from similar, recently completed projects

B.

Validate law productivity from recently completed projects

C.

Verify the labor rates used in the estimate

D.

Verify the equipment costs used in the estimate

Full Access
Question # 27

When a person hears the words being said to him/her, but does not receive the message of the words, it is called

A.

Reflective listening

B.

Judgmental listening

C.

Passive listening

D.

Directive listening

Full Access
Question # 28

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has aschedule performance index of 0.80. What would you advise the management about the scheduled completion date?

A.

Project will be completed in 20 more weeks

B.

Project will be completed this week - on schedule

C.

Project will be completed in 4 more weeks

D.

Project will be completed in 12.8 more weeks

Full Access
Question # 29

What relationship more accurately defines a situation model of parallel activities that require a partial start of one activity?

A.

Start to start

B.

Star to finish

C.

Finish to start

D.

Finish to finish

Full Access
Question # 30

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

All of the following are included in "income tax" calculations except:

A.

Annual income

B.

Annual expenditures

C.

Depreciation

D.

Initial cost of investment

Full Access
Question # 31

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

According to Maslow's hierarchy of needs, giving the employees an award that acknowledges their achievements is most likely to satisfy which level of need?

A.

Belonging needs

B.

Safety needs

C.

Power needs

D.

Self-actualization

Full Access
Question # 32

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

What is the median unit cost?

A.

$48.22

B.

$48.35

C.

$40.00

D.

$46.59

Full Access
Question # 33

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

According to Maslow's hierarchy of needs, which level should be satisfied first?

A.

Physiological

B.

Self-actualization

C.

Safety needs

D.

Ego-status

Full Access
Question # 34

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs amounting to $55.00/unit?

A.

22.22%

B.

$55.00

C.

2

D.

338.5

Full Access
Question # 35

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best:

A.

Engineer — cost plus, contractor fixed price

B.

Engineer — cost plus, contractor cost plus

C.

Engineer fixed price, contactor cost plus

D.

Engineer — fixed price, contractor fixed price

Full Access
Question # 36

After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

Is the percent complete stated by the contractor correct?

A.

No, it should be 55.0%

B.

No, it should be 50.0%

C.

No, it should be 52.5%

D.

Yes, it is 60%

Full Access
Question # 37

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

A good description of quantitative data would be as follows:

A.

There is no difference between Qualitative data and Quantitative data

B.

Quantitative data can be categorized or summarized.

C.

Quantitative data can be described graphically or numerically.

D.

Quantitative data is a subset of data randomly selected from a population; the size of a sample is usually denoted by n.

Full Access
Question # 38

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Why is a +/- notation necessary when developing an estimate?

A.

Contingency cushion

B.

It makes up for the lack of time to develop a real estimate

C.

It is a government requirement

D.

There are unknowns that affect the final cost of a project

Full Access
Question # 39

A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

A.

Cost breakdown structure

B.

Code of accounts

C.

Cost estimate classification

D.

Schedule identification number

Full Access
Question # 40

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?

A.

Recalculate the early finish for each activity

B.

Recalculate the early start for each activity

C.

Update the remaining duration for each activity

D.

Recalculate the critical path

Full Access
Question # 41

Develop a CPM method considering the below tasks and logical relationships. Use this information to answer the related questions.

What is the late finish date of activity 50?

A.

Day 47

B.

Day 38

C.

Day 28

D.

Day 37

Full Access
Question # 42

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The following question requires your selection of Scenario 1.4.15Q from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses

What is the amount of capital recovery with salvage?

A.

$11,499.00

B.

$4,124.00

C.

$9,876.00

D.

$10,765.00

Full Access
Question # 43

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4?

A.

$1890/ton

B.

$1863/ton

C.

$1948/ton

D.

$1836/ton

Full Access
Question # 44

A _________contract allows the contractor to freely employ whatever methods and resources it chooses in order to complete the work.

A.

Guaranteed maximum price

B.

Cost reimbursable/Fixed fee

C.

Measured unit price

D.

Lump-sum/Fixed price

Full Access
Question # 45

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

What Kind of optimization modeling is used in making investment analysis to evaluate the risks associated with the potential investment?

A.

Linear Probability Model

B.

Business Modeling

C.

Five-stop Regression Model

D.

Monte Carlo Simulation

Full Access
Question # 46

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following methods a used for creating critical path schedules:

A.

Precedence diagram method

B.

Precedence and arrow diagram methods only

C.

Gantt chart (bar chart) method

D.

Arrow diagram method

Full Access
Question # 47

refers to the process of calculating and reporting the non-monetary functions of the strategic asset portfolio.

A.

Asset performance assessment

B.

Asset project reporting

C.

Asset investment decision and funding

D.

Asset performance measurement

Full Access
Question # 48

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Given a unit price contract between the owner and contractor, each assumes the following:

A.

Bid unit rate, owner quantities can exceed estimate range Contractor can perform above

B.

Bid unit rate, owner quantities are within estimate range

C.

Contractor can perform at or below bid unit rate, owner quantities can exceed estimate range

D.

Contractor can perform at or below bid unit rate, owner quantities are within estimate range

Full Access
Question # 49

If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period?

A.

$2,424

B.

$2,976

C.

$2,688

D.

$2,697

Full Access
Question # 50

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Which of the following calculations would not be needed to determine "net income?'

A.

Depreciation

B.

Taxes

C.

Present value

D.

Income before taxes

Full Access
Question # 51

In a fixed price contract the:

A.

Contractor has no risk in the project

B.

Contactor assumes all the performance risk

C.

Contractor is paid for actual costs

D.

Owner has all the risk

Full Access
Question # 52

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the range of estimated quantities?

A.

$26.78 to $75.00

B.

$485

C.

$45 to $530

D.

$48.22

Full Access
Question # 53

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually?

A.

$31,875

B.

$12,550

C.

$29,600

D.

$13,515

Full Access
Question # 54

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Student will receive scholarship when the GPA is within top 2%. The mean GPA is 2.8 and standard deviation is 0.5.

How high must the GPA be to qualify for the scholarship?

A.

3.62

B.

3.35

C.

3.91

D.

3.83

Full Access
Question # 55

______________can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.

A.

Economic optimization

B.

Simulation

C.

Linear programming

D.

Dynamic programming

Full Access
Question # 56

Which of the following are used for profitability analysis in a construction company?

A.

Sum of years digits

B.

Return on Investment (ROI) and Rate of Return (ROR)

C.

Opportunity costs

D.

Booked costs

Full Access